1. PREGROUTING<br />

• Grouting holes 10-20 m are<br />

drilled into water bearing zones<br />

(fracture zone)<br />

• Cement grout is pumped into<br />

the zone to prevent water<br />

leakage<br />

• Grouting decision<br />

• Water loss test -> Lugeon<br />

value L/min.m.P<br />

2. DRILLING<br />

• Drilling holes are done for<br />

excavation (length 3-6 m)<br />

• The rock is removed by<br />

blasting<br />

• Different drilling patterns are<br />

used depending on the tunnel<br />

profile and rock quality<br />

3-6 m<br />

3