08.09.2013 Views

i137 GEO binnen - GeoTechniek

i137 GEO binnen - GeoTechniek

i137 GEO binnen - GeoTechniek

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Rigidity of the station<br />

The tilt meters have been installed in the station to<br />

calculate the vertical deformation of the south side<br />

of the station under the assumption that the station<br />

sections behave rigid. During the building activities<br />

this hypothesis was questioned, because of small<br />

leakages of the station and unexplainable differences<br />

between results of the automatic monitoring<br />

system and the measurements of RPW. To investigate<br />

the rigidity of the station additional points were placed<br />

in the centre of the station. With these points<br />

cross profiles of the station could be constructed.<br />

However, after installation of these points no<br />

significant displacements of the station were<br />

measured anymore. As a result no conclusion could<br />

be drawn about the hypothesis of the rigidity of the<br />

station sections (Huisman and Berkelaar, 2006).<br />

CONCLUSIONS AND<br />

RECOMMENDATIONS<br />

CONCLUSIONS<br />

The most prominent risk, interference of operation of<br />

the metro station, did not occur. Full accessibility of<br />

all services was maintained during all building<br />

activities.<br />

The monitoring system operated according to<br />

contract specifications. The on-line presentation and<br />

checking on hazard warning levels was very helpful in<br />

detecting the effect of building activities on the<br />

metro station. The examples in this paper show how<br />

monitoring has been used to control building risks.<br />

RECOMMENDATIONS<br />

As a result of the problems with refraction due to the<br />

semi-confined structure of the station and the<br />

questioned rigidity of the station, a system with<br />

more internal control was recommended for phase<br />

2 of the project and for semi-confined spaces in<br />

general. With 2 tachymeters points are measured<br />

from different positions. Refraction problems will be<br />

eliminated and/or detected in time because it is<br />

unlikely that refraction and temperature peaks would<br />

have the same effect on measurements from two<br />

directions. The monitoring specifications for phase 2<br />

were set up in such a way that the recommendations<br />

from phase 1 were taken into account. Two tachymeters<br />

were specified in combination with crack<br />

meters placed over the station section joints. <br />

ACKNOWLEDGEMENTS<br />

The authors acknowledge the graphical contributions<br />

from Ton de Keiser of Rotterdam Public Works –<br />

Engineering Department.<br />

DEFORMATION MONITORING OF THE UNDERGROUND METRO STATION ROTTERDAM CS<br />

FIGURE 9<br />

REFERENCES<br />

– Berkelaar, R. (2006) Coping with underground risks<br />

during the development of a new underground metro<br />

station in Rotterdam, Proceedings of the 10th IAEG<br />

International Congres, Nottingham, United<br />

Kingdom.<br />

– Huisman, L. (2005) Deformatiemetingen staartspoor<br />

Metro CS week 25 (Results of verification measurements<br />

metro station week 25), Internal memo RPW,<br />

Rotterdam, the Netherlands.<br />

– Huisman, L., and Berkelaar, R. (2006), Evaluatie<br />

monitoring Metro CS Fase I (Evaluation monitoring<br />

metro station CS Phase 1), Internal report RPW,<br />

R.2006.012.RR, Rotterdam, the Netherlands.<br />

– Luijten, C.J.L.M. (2002) Betuweroute en grondverzet,<br />

Handboek Bouwstoffenbesluit (Betuweroute<br />

and earth moving, Manual of building materials<br />

regulations), part 9-16 page 1-20, Weka Uitgeverij,<br />

Amsterdam, the Netherlands.<br />

– Man, C.H. (2005) Een systematiek voor risicomanagement<br />

tijdens de uitvoeringsfase in een complex<br />

stedelijk civieltechnisch project (Systematic approach<br />

for risk management in complex urban construction<br />

projects), M.Sc. thesis C.H. Man, University of<br />

Twente, Enschede, the Netherlands.<br />

RELATION BETWEEN STATION TEMPERATURE AND VERTICAL DEFORMATION.<br />

– Visser, A. (2005) Meetopzet deformatiemetingen<br />

Metro CS (Design of deformation measurements<br />

metro CS), Internal memo RPW, Rotterdam,<br />

the Netherlands.<br />

Reprinted with permission from ASCE.<br />

1 Robert Berkelaar is Geotechnical Engineer, MSc<br />

Engineering Geology, Rotterdam Public Works –<br />

Engineering Department, PO Box 6633,<br />

3002 AP Rotterdam, the Netherlands<br />

r.berkelaar@gw.rotterdam.nl<br />

2 Lennard Huisman is Geodetic Engineer, MSc<br />

Geodetic Engineering, Iv-Infra b.v., PO Box 1155,<br />

3350 CD Papendrecht, the Netherlands,<br />

currently working for University of Technology Delft,<br />

Faculty of Aerospace Engineering,<br />

l.huisman@tudelft.nl<br />

3 Cor J.L.M. Luijten is Monitoring Supervisor, MA<br />

Geography, Rotterdam Public Works – Engineering<br />

Department, PO Box 6633, 3002 AP Rotterdam,<br />

the Netherlands, cjlm.luijten@gw.rotterdam.nl<br />

4 Rotterdamse Electrische Tram i.e.<br />

Rotterdam public transport company.<br />

5 Rotterdam Public Works.<br />

<strong>GEO</strong>international – October 2008 43

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!