TIGHTENING TORQUE FOR THE FLANGE CONNECTIONS<br />

Pipe Tightening torque Corresponding effort<br />

[Kg / cm]<br />

(using a 20 cm spanner)<br />

6,35 mm ( 1 / 4” ) 140-180 wrist force<br />

9,52 mm ( 3 / 8” ) 330-420 arm force<br />

12,70 mm ( 1 / 2” ) 500-620 arm force<br />

15.88 mm ( 5 / 8” ) 630-770 arm force<br />

TIGHTENING TORQUE FOR PROTECTION CAPS<br />

Tightening torque (Kg / cm)<br />

Service connection 70 - 90<br />

Protection caps 250 - 300<br />

Length of the piping<br />

The maximum length of the connection piping is 10 m . When the piping is<br />

longer than 5 m, pay attention to the quantity of refrigerant that should be<br />

added per metre.<br />

Should the external unit have to be installed higher up than the internal unit<br />

with a difference in height of more than 3 m, then traps should be fitted on the<br />

return piping so that the oil trickling down the pipe walls deposits in the trap<br />

until the latter is full. The oil plug that forms will be shot upwards by the gas.<br />

2.9 Making a vacuum and checking the tightness<br />

The air must be expelled from the circuit using a vacuum pump, pump transition<br />

fitting and pressure gauge assembly which are suitable for R410A.<br />

Ensure that the vacuum pump is filled with oil to the level indicated by the oil<br />

gauge.<br />

Link the vacuum pump to the service connection, after ensuring that both<br />

cocks on the external unit are shut.<br />

1. unscrew the caps on the cocks of the two-way and three-way valves, and<br />

on the service valve,<br />

2. connect the vacuum pump to the small service valve in the three-way valve<br />

of the external unit and to the vacuum pump transition fitting,<br />

3. once you have opened the corresponding valves on the pump, start the latter<br />

and leave it to operate, Make a vacuum for approximately 20/25 minutes,<br />

4. check that the needle on the left-hand pressure gauge has moved towards<br />

-76 cm Hg (vacuum of 4 mm Hg or less),<br />

5. shut the cocks on the pump and turn it off. Check that the needle on the<br />

pressure gauge does not move for approximately 5 minutes. If the needle<br />

moves, this means that air is seeping into the system, and you must check<br />

that all connections are tight enough and that the pipe connections were all<br />

made correctly; then repeat the procedure from step 3,<br />

6. disconnect the vacuum pump,<br />

7. open the cocks on the two-way and three-way valves fully,<br />

8. screw the plug tightly to the service outlet ensuring that it is well sealed,<br />

9. after having tightened all the plugs, check that there are no gas leaks<br />

around their circumference.<br />

WARNING<br />

Always protect the connection cables and pipes to prevent their being<br />

damaged, as they could cause gas leaks when damaged. (personal injury<br />

from cold burns)<br />

vacuum<br />

pump<br />

cock<br />

8 m max<br />

service connection<br />

internal unit<br />

gas valve<br />

protection<br />

caps<br />

service<br />

connection<br />

liquid valve<br />

cock<br />

29

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!