<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

ANALISI DELLA SITUAZIONE DEI LUOGHI<br />

SEZIONE PIANTA


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

SI <strong>IN</strong>IZIA L’OPERAZIONE CREANDO LE GUIDE <strong>IN</strong> C.A. PER LA BENNA


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

PER SCAVARE SI UTILIZZA UNA PARTICOLARE BENNA MORDENTE


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

BENNA<br />

CORDOLI <strong>IN</strong> C.A.<br />

SEQUENZA OPERATIVA PER ESEGUIRE LO <strong>SCAVO</strong><br />

BENNA<br />

CORDOLI <strong>IN</strong> C.A.


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

LA <strong>BENTONITE</strong> FUNZIONA COME UN<br />

COLLOIDE, RIVESTENDO LE PARETI<br />

DELLO <strong>SCAVO</strong> CREA UNA SORTA <strong>DI</strong><br />

ARMATURA<br />

SEZIONE TEORICA DELLO <strong>SCAVO</strong> OTTENUTO<br />

LO <strong>SCAVO</strong> E’ RIEMPITO<br />

<strong>DI</strong> <strong>BENTONITE</strong><br />

LE PARETI DELLO <strong>SCAVO</strong><br />

SONO IRREGOLARI


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

NELLO <strong>SCAVO</strong>, PIENO <strong>DI</strong> <strong>BENTONITE</strong>, SI <strong>IN</strong>SERISCE L’ARMATURA METALLICA<br />

ARMATURA METALLICA<br />

<strong>SCAVO</strong> RIEMPITO <strong>DI</strong> <strong>BENTONITE</strong>


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

SOSTITUZIONE DELLA <strong>BENTONITE</strong> <strong>CON</strong> IL CACLCESTRUZZO<br />

ARMATURA METALLICA<br />

<strong>SCAVO</strong> RIEMPITO <strong>DI</strong> <strong>BENTONITE</strong><br />

IL CALCESTRUZZO VIENE IMMESSO<br />

DEPOSITANDOLO SUL FONDO , <strong>IN</strong><br />

MODO CHE SP<strong>IN</strong>GA VERSO L’ALTO LA<br />

<strong>BENTONITE</strong> E MANTENGA <strong>IN</strong>ALTERATA<br />

LA <strong>DI</strong>STIBUZIONE GRANULOMETRICA


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

I SETTI SONO <strong>IN</strong>CASTRATI <strong>UNO</strong> <strong>CON</strong> L’ALTRO<br />

<strong>DI</strong>AFRAMMA <strong>IN</strong> C.A.F<strong>IN</strong>ITO I GIUNTI <strong>DI</strong> COLLEGAMENTO SONO REALIZZATI:<br />

• <strong>IN</strong>SERENDO PRIMA DEL GETTO UN TUBO <strong>DI</strong><br />

PVC<br />

• ROMPENDO MEZZO TUBO <strong>IN</strong> MODO CHE IL<br />

CLS POSSA SAGOMARSI


<strong>ESECUZIONE</strong> <strong>DI</strong> <strong>UNO</strong> <strong>SCAVO</strong> <strong>CON</strong> <strong>DI</strong>AFRAMMI <strong>IN</strong> <strong>BENTONITE</strong><br />

IPOTESI <strong>DI</strong> SEQUENZA OPERATIVA DA OSSERVARE PER LA COSTRUZIONE<br />

1<br />

1 3<br />

1 2<br />

1 2 3<br />

1<br />

SI COSTRUISCE IL <strong>DI</strong>AFRAMMA N.1<br />

MENTRE AVVIENE LA MATURAZIONE DEL N.1, SI COSTRUISCE IL N.3<br />

2 5<br />

3<br />

4<br />

MENTRE AVVIENE LA MATURAZIONE DEL N.3, SI COSTRUISCE IL N.2 VIC<strong>IN</strong>O AL N.1 GIA’ <strong>IN</strong>DURITO<br />

SI PROCEDE POI <strong>IN</strong> SEQUENZA RISPETTANDO LO STESSO CRITERIO 4 5<br />