POLO DEL TERZIARIO SOVRAREGIONALE PROGETTO PRELIMINARE<br />

Veneto City<br />

Nuova fermata SFMR di Dolo/Pianiga<br />

Opere di fermata(banchine, rampe, scale, arredo)<br />

Opere civili<br />

COMPUTO METRICO ESTIMATIVO<br />

Articolo INDICAZIONE DEI LAVORI E DELLE PROVVISTE UNITÀ PREZZO<br />

DI SIMILI LUNGH. LARGH. ALT./SPESS. QUANTITÀ IMPORTO<br />

N. Codice MISURE MISURA UNITARIO<br />

PT0564P--AS0001DCM00211 Rev 0 09.02.00.00<br />

Scale - muri<br />

(1*2) * (5,50+6,00+6,00) * 4,00 2,000 17,500 4,000 140,000<br />

(2,00*2) * 17,50 * 1,20 4,000 17,500 1,200 84,000<br />

(2*2) * 4,20 * 4,00<br />

Elevazione<br />

muri<br />

4,000 4,200 4,000 67,200<br />

1 * (7,50+4,00+4,00) * 4,00 1,000 15,500 4,000 62,000<br />

(1*2) * (7,50+4,00+4,00) * 1,20<br />

muri ascensore<br />

2,000 15,500 1,200 37,200<br />

1 * (4,00+2,00+2,00+4,00) * 6,50<br />

rampe<br />

1,000 12,000 6,500 78,000<br />

2 * 29,00 * ((4,00+1,50)/2) 2,000 29,000 2,750 159,500<br />

2 * 29,00 * (2,00*2) 2,000 29,000 4,000 232,000<br />

2 * 4,10 * (2,00/2) 2,000 4,100 1,000 8,200<br />

2 * 29,00 * (1,50/2) 2,000 29,000 0,750 43,500<br />

(2*2) * (29,00-1,80) * ((3,50+1,20)/2) 4,000 27,200 2,350 255,680<br />

(2*2*2) * 29,00 * 1,20 8,000 29,000 1,200 278,400<br />

(2*2) * 4,10 * 1,20<br />

rampe (rampa con ascensore)<br />

4,000 4,100 1,200 19,680<br />

1 * 33,00 * ((4,50+1,50)/2) 1,000 33,000 3,000 99,000<br />

1 * 33,00 * (2,50*2) 1,000 33,000 5,000 165,000<br />

1 * 6,20 * (2,50/2) 1,000 6,200 1,250 7,750<br />

1 * 33,00 * (1,50/2) 1,000 33,000 0,750 24,750<br />

(1*2) * (33,00-3,00) * ((3,50+1,20)/2) 2,000 30,000 2,350 141,000<br />

(1*2*2) * 33,00 * 1,20 4,000 33,000 1,200 158,400<br />

(1*2) * 6,20 * 1,20<br />

Muro di separazione con A.V. - elevazione<br />

2,000 6,200 1,200 14,880<br />

1 * (305,00+0,40) * 1,20 1,000 305,400 1,200 366,480<br />

(1,00*2) * (305,00+0,30) * 3,00<br />

Elevazione<br />

Muro sostegno barriera e banchina ferroviaria<br />

2,000 305,300 3,000 1.831,800<br />

1 * 202,00 * 3,00<br />

Muro sostegno barriera<br />

1,000 202,000 3,000 606,000<br />

(1*2) * 58,00 * 2,00<br />

Muro sostegno<br />

2,000 58,000 2,000 232,000<br />

(1*2) * 24,00 * 1,00 2,000 24,000 1,000 48,000<br />

- 264 -