5. Commissioning<br />
Plug the mains plug of the control unit into the socket. The plant<br />
will initialise automatically.<br />
Note: The mains power supply cable must be equipped with a<br />
fault current circuit breaker.<br />
During the first initialisation of the plant, the control unit requests<br />
four basic settings. The control unit display shows a<br />
query for<br />
1. the language for the user prompting<br />
2. the date and the time<br />
3. the desired purification class C or D<br />
4. the required nominal size of the plant.<br />
5.3. Instruction of the customer based on the installation<br />
instructions<br />
- Perusing the installation and operating instructions with the<br />
customer<br />
- Operating the plant (explaining and describing)<br />
- Explaining the operator duties to the customer (disposal,<br />
maintenance, operation of a small biological sewage treatment<br />
plant, operations diary)<br />
By pressing the movement keys / direction keys, the desired<br />
setting can be highlighted with a marking bar. Pressing the<br />
enter key stores the selected setting in the system memory. As<br />
soon as the 4 presettings have been made, the control unit<br />
loads the program memory and automatically enters into operating<br />
mode.<br />
The plant is now ready for operation.<br />
5.2 Operator's duties<br />
Checking<br />
- for transport or installation damage<br />
- for structural defects<br />
- all electrical and mechanical components for seat and function<br />
- floater function<br />
- hose connections<br />
- line connections<br />
- syphons (see point 8)<br />
- aerator<br />