CAPITULO VIII : INSTALACIONES
SISTEMA DURAMAX MR
199
TABLA 54
Tabla para diseño de tanques sépticos
SISTEMA DURAMAX MR
SERVICIO
DOMÉSTICO
PERSONAS SERVIDAS
SERVICIO
ESCOLAR
(EXTERNOS)
CAPACIDAD
DEL TANQUE
EN LITROS
DIMENSIONES EN METROS
L A h1 h2 h3 H Tabique Piedra
Hasta 10 Hasta 30 1500 1.90 0.70 1.10 1.20 0.45 1.68 0. 14 0. 30
11 a 15 31 a 45 2500 2.00 0.90 1.20 1.30 0.50 1.78 0. 14 0. 30
16 a 20 46 a 60 3000 2.30 1.00 1.30 1.40 0.55 1.88 0. 14 0. 30
21 a 30 61 a 90 4500 2.50 1.20 1.40 1.60 0.60 2.08 0. 14 0. 30
31 a 40 91 a 120 6000 2.90 1.30 1.50 1.70 0.65 2.18 0. 28 0. 30
41 a 50 121 a 150 7500 3.40 1.40 1.50 1.70 0.65 2.18 0. 28 0. 30
51 a 60 151 a 180 9000 3.60 1.50 1.60 1.80 0.70 2.28 0. 28 0. 30
61 a 80 181 a 240 12,000 3.90 1.70 1.70 1.90 0.70 2.38 0. 28 0. 30
81 a 100 241 a 300 15,000 4.40 1.80 1.80 2.00 0.75 2.48 0. 28 0.30
E
1 I GUÍA RÁPIDA PARA DISEÑO
POR DURABILIDAD DE ESTRUCTURAS
DE CONCRETO
En servicio doméstico
En servicio escolar
El número de personas para servicio escolar se determinó para un período de
habrá que buscar la relación que existe entre el período de retención y el período
de trabajo escolar, relacionándola con la capacidad doméstica.
Ejemplo:
cuántas personas dará servicio escolar si el período de trabajo diario es de seis
horas?.
Cálculo
= 24 = 4
Período de Trabajo 6
Puede dar servicio escolar para: 4 x 60 = 240 personas.