CONCEPTO 1 RENDIMIENTO \ \

3. DRENAJES Un Grupo Optimo í Medio | Mínimo \

3.01 CAMA DE ARENA DE

0.10 cm.

0.20 cm.

3

m 1 8.00 7.00 6.00

3

m 1 10.00 9.00 8.00

3.02 TENDIDO TUBO CONCRETO

1 (f) 10 (19 kg/ml) mi 5 40.00 38.00 36.00

0 15 (29 kg/ml) mi 5 36.00 32.00 34.00

0 20 (44 kg/ml) mi 5 34.00 32.00 30.00

<p 25 (60 kg/ml) mi 5 30.00 28.00 26.00

0 30 (90 kg/ml) mi 5 26.00 24.00 20.00

0 40 (134 kg/ml) mi 2 14.00 12.00 10.00

0 60 (345 kg/ml) mi 2 8.00 7.50 7.00

0 100 (1000 kg/ml) mi 2 5.00 4.75 4.50

3.03 REGISTRO DE 40 X 60 cm.

Hasta 1.00 pza 5 2.50 2.25 2.00

Hasta 1.50 pza 5 2.00 1.75 1.50

Hasta 2.00 pza 5 1.50 1.25 1.00

3.04 TAPAS REGISTRO 40 X 60 cm.

Concreto armado 70 X 90 X 10 cm. pza 5 10.00 8.00 6.00

De marco con concreto para pisos pza 5 8.00 6.50 5.00

3.05 POZOS DE VISITA BROCAL 90 cm

Hasta 2.00 metros pza 5 1.00 0.80 0.60

Hasta 3.00 metros pza 5 0.70 0.60 0 50

Hasta 4.00 metros pza 5 0.40 0.35 0.30

3.06 BROCALES CONCRETO pza 5 5.00 4.50 4.00

brocales FO. pza 5 4.00 3.50 3.00

Parámetros para edificación 179