Directors’ Report on <strong>PGNiG</strong> S.A.’s Operations in 2008<br />

Chapter VI: Investment Projects<br />

In 2008, <strong>PGNiG</strong> S.A. carried out a number of projects in all of its business areas. According to the<br />

financial statements, capital expenditure on property, plant and equipment and intangible assets<br />

incurred by <strong>PGNiG</strong> S.A. in 2008 amounted to PLN 1,161.9m. The table below presents the<br />

expenditure structure by business segments.<br />

Capital expenditure of <strong>PGNiG</strong> S.A. in 2008<br />

PLNm<br />

Exploration and Production 935.0<br />

Trade and Storage 226.7<br />

Other 0.2<br />

Total 1,161.9<br />

1. Investment Projects in the Exploration and Production Segment<br />

The expenditure on projects incurred in the Exploration and Production segment in 2008 amounted to<br />

PLN 935.0m. Below are described the major projects in the segment.<br />

Exploration<br />

In the area of exploration, capital expenditure totalled PLN 362.1m, including PLN 211.7m incurred<br />

mainly on positive boreholes and boreholes which were not completed. In 2008, eleven positive<br />

boreholes were drilled. The balance of PLN 150.4m was incurred on negative boreholes and was<br />

charged to costs of the financial year.<br />

Lubiatów-Międzychód-Grotów Project<br />

The objective of the project is to develop the Lubiatów-Międzychód-Grotów reserves of crude oil and<br />

natural gas and to facilitate transport, storage and sale of crude oil, natural gas, liquid sulphur and<br />

propane-butane mixture from the LMG Crude Oil and Natural Gas Mine. The LMG project involves:<br />

• construction of the LMG Central Facility to serve as a hub for collection, distribution and<br />

treatment of reservoir fluids,<br />

• construction of the Dispatch Terminal in Wierzbno to support collection and shipment of crude<br />

oil in rail tank cars and handle the pumping of crude oil collected from the LMG Crude Oil and<br />

Natural Gas Mine to the PERN Druzhba Pipeline,<br />

• construction of a gas pipeline to the Denitriding Plant in Grodzisk to support the transmission of<br />

surplus gas from the LMG Mine to Grodzisk Denitriding Plant.<br />

In 2008, the construction of the Dispatch Terminal was completed. The expenditure incurred in 2008<br />

was PLN 26m. The total value of the project is estimated at approx. PLN 1.6bn.<br />

The Grodzisk Project<br />

The objective of this project is to support the sale of gas from nitrogen-rich reserves after the gas has<br />

been treated (cryogenic denitriding of nitrogen-rich gas) to the parameters of high-methane gas. The<br />

Grodzisk Denitriding Plant is constructed with a view to increasing nitrogen-high gas production<br />

volume at the existing mines and from reserves earmarked for development.<br />