8.0 ENVIRONMENTAL IMPACT MITIGATION MEASURES<br />

This chapter discusses the proposed measures for mitigation of the environmental<br />

impacts idnetified in Chapter 5. The impacts discussed in Chapter 5 are segregated<br />

into two main categories; impacts associated with construction and impacts<br />

associated with operation. Therefore this chapter will present the proposed mitigating<br />

measures in a similar orgianization.<br />

8.1 Mitigation of Construction Related lmpacts<br />

Although the first power unit is planned to be on-line within 2 years, it is expected to<br />

take approximately 6 years to complete construction of the <strong>Krasnodar</strong> power plant.<br />

The general phases of construction that will occur are:<br />

preparation of contractors area,<br />

site preparation,<br />

temporary and permanent road construction,<br />

temporary and permanent building and utility construction,<br />

equipment installation,<br />

services connection.<br />

Each phase of the' project will involve specific activities each of which have the<br />

potential to generate environmental and socio-economic impacts. Targets of the<br />

environment at risk to impact include air quality, surface and ground water quality,<br />

vegetation, soil quality, soil erosion, dust, and noise levels. Socio-economic impacts<br />

may include land use, jobs, and overuse of limited public services. Table 8-1 indicates<br />

types of construction activities that will cause impacts, what targets may be<br />

affected, and the potential type of impact which may result i.e. none, insignificant,<br />

moderate, severe, positive, or negative. A discussion of each impact is presented in<br />

Chapter 5 of this report.<br />

8.1 .I Mitigation Measures for Impacts Related to Construction<br />

The proposed mitigative measures are intended to either minimize an impact or<br />

whenever possible prevent the impact completely. Table 8-2 presents specific<br />

impacts and the mitigating measures that have been implemented or are proposed.<br />

PAGE 8-1