ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
TENDER DOCUMENT<br />
PROCUREMENT OF ELECTRICS<br />
FOR COKE PUSHER<br />
<strong>PUR</strong>CHASE DEPTT. / MM DIVISION<br />
HEAVY MACHINE BUILDING PLANT<br />
HEAVY ENGINEERING CORPORATION LIMITED<br />
P.O.-DHURWA, RANCHI<br />
Page 1 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
<strong>Tender</strong> Enq.<strong>No</strong>.<strong>HMB</strong>P/<strong>PUR</strong>/2011/961723/EL-3405 Dated: 14.08.2012<br />
<strong>Enquiry</strong> Schedule<br />
Due Date of <strong>Tender</strong> opening: 30.08.2012<br />
Scope of Work: This tender specification calls for turnkey execution of the job<br />
covering the design, engineering, manufacture, supply FOR <strong>HMB</strong>P stores<br />
at Ranchi, receipt of material from purchaser‟s store at DSP,<br />
transportation from purchaser‟s store at DSP to coke oven site, handling,<br />
storage and re-conservation at DSP site, erection, testing, commissioning<br />
of electrics with standard accessories and attachment as covered in this<br />
specification. Demonstration of the proper functioning of the electrical<br />
system during performance guarantee test of the equipment in a<br />
coordinated and integrated manner as per the relevant clauses of this<br />
specification.<br />
QUALIFYING CRITERIA:<br />
1) The tenderer should have carried out electrical work related to steel plant equipment including<br />
VFD & PLC in past, covering design, engineering, supply, erection, testing &<br />
commissioning. The claim should be substantiated with submission of documentary<br />
evidence including performance certificate from the users/customers.<br />
2) The annual turnover of the tenderer shall be minimum 3 cores in last three consecutive<br />
financial years. <strong>Tender</strong>er shall submit audited balance sheet for last three years.<br />
Terms and Conditions:<br />
1) The offer must be prepared taking reference to the detailed technical specifications & other details in the<br />
enclosed DAP-203/12M<br />
2) Please submit your quotation strictly in three part system i.e.:-<br />
a. Techno-commercial bid-Part I (This Techno Commercial bid shall be confirming all technical<br />
specification, commercial terms & conditions and price format with price column blanked ( Unpriced ). The<br />
price format should contain item wise list of items for which the price has been quoted.)<br />
b. Price Bid -Part II (This part will comprise price format duly filled in) and<br />
c. Earnest Money Deposition (EMD) -Part III (This part will contain only DD / Bank guarantee in favor of<br />
HEC Limited Ranchi-4, for Earnest Money deposit.)<br />
Page 2 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
3) a. The technical and commercial aspects to be sealed in a separate envelope super scribing Part-I<br />
on it .The Price bid to be super scribed as Part – II and EMD to be super scribed as Part-III.<br />
b. All the three bids i.e. Part-I, Part II & Part III shall be in separate sealed covers clearly super<br />
scribing on the top of each envelope the relevant part number, tender reference number with date<br />
and due date of opening.<br />
c. All the three bids i.e. Part-I, Part II & Part III shall be enclosed in one envelope. This envelop shall<br />
also be super scribed on the top with relevant tender no. and due date of opening.<br />
4) The Payment Terms shall be as under:<br />
“90% of the total value of supply part along with hundred percent taxes & duties shall be released through<br />
Cheque/RTGS within 60 days of receipt of materials complete in all respect along with Guarantee<br />
Certificate, Test<br />
Certificate, Inspection Certificate (to be issued by HEC), EDGP (if applicable), Original Invoice, <strong>10</strong>% PBG<br />
(Performance Bank Guarantee) to be valid till full guarantee period from any nationalized bank only in<br />
HEC’s format and all the drawings and documents as per enquiry specifications. “<br />
“Balance <strong>10</strong>% of the value of supply part along with the erection and commissioning charges shall be<br />
released through Cheque/RTGS within 30 days from the date of issue of Commissioning Certificate by<br />
HEC/Customer “<br />
5) Guarantee Clause: The materials supplied shall be guaranteed for 12 months from the date of<br />
commissioning or 18 months from receipt of material whichever is earlier.<br />
6) Liquidated Damages (L.D):For late delivery, the L.D. @0.5% per week limited to <strong>10</strong>% maximum shall<br />
be levied on the order value.<br />
7) Place and Time of submission of quotation:<br />
Place: Purchase Deptt./<strong>HMB</strong>P/HEC Limited, Dhurwa, Ranchi – 834 0<strong>04</strong>.<br />
Date & Time of receipt of tender: 30.08.2012 Upto 1.00 P.M.<br />
Date & Time of opening of tender: 30.08.2012 at 3.00 P.M.<br />
8) EMD of 2% of the quoted price shall be submitted in separate sealed cover. The E.M.D. shall be<br />
submitted in the form of Demand draft / Bank Guarantee from any nationalized bank and in favor of <strong>Heavy</strong><br />
Engineering Corporation Limited payable at Ranchi. The firm shall mention about the submission of<br />
EMD in their techno-commercial bid indicating DD <strong>No</strong>./Bank Guarantee <strong>No</strong>., Date etc. BUT THE<br />
AMOUNT OF D.D. /VALUE OF BANK GUARRANTEE SHALL NOT BE MENTIONED IN THE TECHNO-<br />
COMMERCIAL BID. IT MAY PLEASE BE NOTED THAT EMD SHALL BE REFUNDED TO THE<br />
UNSUCCESSFUL TENDERERS.<br />
9) Security Deposit: The successful tenderer will have to deposit Security deposit for 5% of the basic order<br />
value (in form of bank guarantee) within 30 days time after placement of order .The validity of security<br />
deposit shall be up to receipt of last consignment .<br />
<strong>10</strong>) Performance Bank Guarantee (PBG): The successful tenderer will have to furnish PBG of <strong>10</strong>% of<br />
the Basic order value of purchase order valid till full guarantee period from any nationalized Bank<br />
only in HEC's Format .<br />
11) Schedule of <strong>Tender</strong> receipt by 30.08.2012 up to 1.00 PM. Opening of <strong>Tender</strong> on 30.08.2012, at<br />
3.00PM, TENDERS must be submitted in sealed cover with <strong>Tender</strong> <strong>No</strong>. and the Due date super scribed on<br />
it failing which <strong>Tender</strong>s may be ignored.<br />
12) The rate quoted shall be firm and the prices quoted must be on FOR: Destination i.e.<br />
Stores/<strong>HMB</strong>P/HEC Ltd RANCHI - 4 Basis including packing, forwarding, freight & insurance charges.<br />
Page 3 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
13) The Price quoted by the tenderer should be exclusive of sales tax. The rate and nature of sales tax<br />
applicable should be shown separately. Sales tax will be paid to the seller at the rate at which it is liable to<br />
be assessed or has actually been assessed on the date of supply provided the transaction of sale is legally<br />
liable to sales tax and within the delivery period. Any change on the taxes & duty structure beyond the<br />
delivery period will not be considered by HEC.<br />
14) The rates quoted must be firm and offer‟s validity for acceptance must be valid for minimum <strong>04</strong><br />
months from the date of opening of tender.<br />
15) Quotations erased or over written are likely to be rejected unless all corrections are authenticated with<br />
the tenderer's signature.<br />
16) Delivery date offered must be specified and guaranteed. Delivery within 2 to 3 Months is preferred.<br />
17) Full particulars i.e. specification, literature and / or drawing wherever applicable should be submitted<br />
along with the quotation. The brand and 'Make' name must be indicated.<br />
18) The Corporation does not pledge itself to accept the lowest or any tender and reserves to itself the right<br />
of accepting the whole or any part of tender or portion of the quantity offered and you shall supply the same<br />
at the rate quoted.<br />
19) Supplies will be subject to Inspection by our Inspection wing / or inspection agencies prescribed by us.<br />
20) Order placed as a result of this tender will be subject to the Corporation's General Terms and<br />
Conditions of contract which can be down loaded from our website (www.hecltd.com)<br />
21) Corporation reserves the right to call for and examine at any time the books of accounts and other<br />
documents and papers of the firm for the purpose of ascertaining whether any excess payments has been<br />
made or the firm likely to be received / received undue benefit out of execution of the particular contract.<br />
22) Delivery: The time for and the date of delivery of the Stores stipulated in the acceptance of tender shall<br />
be deemed to be the essence of the contract and delivery must be completed not later than the dates<br />
specified therein. Otherwise:<br />
a) The purchaser to recover from the contractor a sum of 0.5 % per week (completed week) of the price of<br />
The stores (up to maximum <strong>10</strong> %) as liquidated damages, which the contractor has failed to deliver as<br />
Aforesaid or<br />
b) The purchaser may procure the undelivered stores / similar items from elsewhere, without notice to the<br />
Contractor at the risk of the contractor without canceling the contract in respect of the consignment not yet<br />
due for delivery or,<br />
c) To cancel the contract or a portion thereof.<br />
23. Income Tax Clearance Certificate - All tenderers shall submit along with their tender an Income Tax<br />
Clearance Certificate duly countersigned by the Income Tax Officer of the circle concerned under the seal<br />
of the office. Copy of Permanent Account <strong>No</strong>. (PAN) (Of Income Tax) to be enclosed with the bid.<br />
24. There is no obligation on our part to accept delayed / late tenders. <strong>Tender</strong>s received after the due date<br />
of opening are liable to be summarily rejected.<br />
26. The rates quoted shall also be inclusive of embossing on the material. The Ownership namely <strong>HMB</strong>P /<br />
FFP / HMTP should be at a predominant place of the material to a size / thickness upon the volume of the<br />
material.<br />
25. Way Bills/ Road Permit: <strong>No</strong> consignment from outside the state of Jharkhand shall be dispatched by the<br />
Supplier without a valid way bill / Road Permit, to be issued by <strong>PUR</strong>CHASER.<br />
26. The Supplier shall produce documentary evidence as may be called for by <strong>PUR</strong>CHASER in respect of<br />
taxes, duties etc. paid by the Supplier.<br />
27. Termination of Order:i.<br />
The order can be terminated if the supplier fails to deliver the goods in time.<br />
ii. Any other reason due to which company thinks it fit to terminate the order.<br />
iii. In the event of the termination of the contract in part/ full the company can get the work<br />
Completed from any other agency/ departmentally at the risk and cost of the supplier.<br />
28. MODE OF DESPATCH<br />
Page 4 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
By road to the consignee: In-charge, Stores, <strong>HMB</strong>P, HEC Ltd, Ranchi. For the consignments to be<br />
dispatched by Road, the supplier shall ensure that the following are observed by them:<br />
i) All dispatches must be affected only on receipt of written dispatch clearance from <strong>PUR</strong>CHASER.<br />
ii) You shall dispatch all the materials consigned to In-charge Stores, <strong>HMB</strong>P, HEC Ltd, Ranchi<br />
iii) Care shall be taken to avoid damages during transit to ensure that all packages are firmly<br />
secured.<br />
29. PACKING, FORWARDING AND SHIPMENT<br />
a) The Supplier shall notify the Purchaser of the date of each shipment from his works, and the expected<br />
date of arrival at the site for the information.<br />
30. OTHER TERMS AND CONDITIONS<br />
Other terms and conditions which are not mentioned above shall be as per General Terms and<br />
Conditions of Contract of the Corporation which can be downloaded from our website<br />
(www.hecltd.com).<br />
Important: While submitting tender please mentioned your Registration <strong>No</strong>. with HEC as a registered<br />
vendor with valid paper. If not please get registered your firm with HEC Limited immediately.<br />
(P.K.Singh)<br />
Sr.DGM/<strong>PUR</strong>/<strong>HMB</strong>P/HEC Ltd.<br />
Page 5 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
CONTENTS<br />
Chapter Description<br />
<strong>No</strong>.<br />
1. Introduction & Machine details<br />
2.<br />
3.<br />
Scope of Supply & Work<br />
Climatic condition<br />
4.<br />
5.<br />
Standards<br />
Power supply condition<br />
6. Technical Specifications<br />
7. Specification of Motors<br />
8. Power distribution on machine<br />
9. Specification of main control desk<br />
<strong>10</strong>. Specification of control panels.<br />
11. Control modes<br />
12. Limit switches & Junction boxes<br />
13. Brakes<br />
14. Resistance boxes<br />
15. Light fittings<br />
16. Specification of cables<br />
17. Identification of circuits & cables etc.<br />
18. Earthing<br />
19. Air conditioning<br />
20. VVVF<br />
21. PLC<br />
22. Particular requirements<br />
23. Tests<br />
24. Drawings & documents<br />
25. Make of electrical equipments<br />
26. Preferred makes<br />
27. List of drawings<br />
Page 6 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Schedules<br />
Schedule -1 List of commissioning spares<br />
Schedule -2<br />
Special tools, tackles &<br />
instruments<br />
Schedule -3:-<br />
Schedule -3<br />
Format for LT motor data sheet<br />
Schedule -4<br />
Schedule -5<br />
Schedule -6<br />
Schedule -7<br />
Schedule -8<br />
Standard specification for<br />
programmable logic controller<br />
Standard specification for VVVF<br />
converters(AC drives)<br />
Standard specification for LT<br />
inverter duty motor<br />
Standard specification for<br />
uninterrupted power supply system<br />
List of commissioning spares for<br />
two years operation & maintenance<br />
Drawings<br />
Sl. <strong>No</strong>. Drg. <strong>No</strong>. Title<br />
1 1522.96.001 Single line diagram<br />
dule -3:- 2 SK-EDB-<strong>10</strong>91 PLC configuration diagram<br />
3 SK-EDB-<strong>10</strong>55 Sketch of electric panel room<br />
4 1522.61.000 GA Drg. of coke pusher<br />
Page 7 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
QUALIFYING CRITERIA:<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
1)The tenderer should have carried out electrical work related to steel plant equipment<br />
including VFD & PLC in past, covering design, engineering, supply, erection, testing &<br />
Commissioning. The claim should be substantiated with submission of documentary<br />
evidence including performance certificate from the users/customers.<br />
2)The annual turnover of the tenderer shall be minimum 3 crores in last three consecutive financal<br />
years. <strong>Tender</strong>er shall submit audited balance sheet for last three years.<br />
1.0 INTRODUCTION<br />
1.1 BACKGROUND<br />
1.1.1 SAIL-DSP was set up as an integrated steel plant in India. The plant is<br />
located at Durgapur, in Burdwan district of West Bengal & is located on<br />
the main Howrah- Delhi railway line.<br />
SAIL- DSP desires to rebuild Coke oven battery no. 2<br />
1.2 COKE OVEN BATTERIES<br />
Main parameters of the batteries are given below:<br />
Parameters Battery <strong>No</strong>. 2<br />
<strong>No</strong>. of ovens 78 (2 blocks of 39 ovens each)<br />
Oven Dimensions<br />
Height 4450 mm<br />
Avg. width 450 mm<br />
Length 13590 mm<br />
Useful volume 23.8 m3<br />
Page 8 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
1.3 Oven Parameters<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
a) Number of Ovens 78<br />
b) Oven height 4450 mm<br />
c) Oven width 450 mm(average)<br />
d) Oven length 13590 mm<br />
e) Oven taper 60 mm<br />
f) Oven volume 23.8 m3<br />
g) Oven pitch 1<strong>10</strong>0 mm<br />
h) Oven sole level +84296 (Cold)/ +84326 (Hot)<br />
i) Pushing series 5-2<br />
j) <strong>No</strong>. of charging holes 4<br />
k) <strong>No</strong>. of gas collecting mains 2<br />
l) Quenching system Wet quenching<br />
m)<br />
n)<br />
Coking Time<br />
)<br />
Track level<br />
18 Hours<br />
+77590<br />
1.3.1 Pertinent data in respect of the machine tracks (machine tracks are<br />
covered in Battery proper) are as follows:-<br />
Machine<br />
Tracks<br />
Pusher<br />
Car<br />
Rail Gaug<br />
e<br />
CR-<strong>10</strong>0<br />
(178.5 lb/yd)<br />
(mm)<br />
<strong>10</strong>058<br />
(C/C)<br />
Wheel<br />
Load<br />
(max)<br />
19t<br />
(max.)<br />
Maximum<br />
length<br />
(mm)<br />
Power<br />
Feed<br />
15700 Trolley<br />
Wire<br />
1.4 Travel Mechanism<br />
Travel mechanism shall be designed to prevent derailing of the machine.<br />
Provision for easy re-railing shall be provided.<br />
Spring grid couplings shall be used between motor and reducer of LT<br />
mechanisms.<br />
Page 9 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
Car<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Emergency stop provision shall be provided near LT drives for Pusher<br />
Generally the LT speed shall be kept on lower side subject to fulfilment of<br />
average pushing rate of 96 ovens per day considering 22 hr/day pushing<br />
time and other technical/operational requirement.<br />
Fail safe spring engaged DC electromagnetic brake shall be provided as<br />
parking brake.<br />
1.5 Track details:<br />
a) Track rail size CR <strong>10</strong>0 (178.5 lb/yd)<br />
b) Weight of rail per meter 88.96 kg<br />
c)<br />
d)<br />
Track center to<br />
center distance<br />
Gradient<br />
<strong>10</strong>058 mm<br />
Level<br />
e) Curvature Nil<br />
1.6 Main Features of Machine:<br />
Type Single spot with hydraulic drives<br />
Arrangement of leveller with<br />
respect to pusher ram.<br />
Control of drives By PLC<br />
Speed control of LT drives<br />
Speed control of ram drive -do-<br />
Speed control of leveller drive -do-<br />
Right of pusher ram ( looking at the<br />
battery from pusher side)<br />
By means of A.C. squirrel cage motors<br />
with VVVF control and frequency<br />
converters.<br />
Centralised Lubrication Motorised multi line/ two-line system<br />
System<br />
Power Collectors As existing<br />
Page <strong>10</strong> of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
Spotting System<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Refer electrics write – up (Annexure-II)<br />
Emergency drive for Pusher Withdrawal by air motor & an electrical<br />
Ram<br />
winch with manual operation facility<br />
Pusher Ram Straight with rack & pinion<br />
Cleaning of rack teeth By compressed air<br />
Measurement of pushing Force By Ammeter, to be displayed digitally in<br />
the Operator‟s Cabin<br />
Degraphitising By ram head mounted cutters and<br />
compressed air<br />
Protection covers for Pusher To be provided.<br />
Ram<br />
Leveller emergency drive Electric winch along with manual<br />
operation facility<br />
Leveller spillage coal bunker To be provided. Capacity to suit at least<br />
14 (fourteen) oven cycles<br />
Leveller door opener Upward opening, mechanized by<br />
means of LDT mounted hydraulic<br />
cylinder<br />
Leveller muff With air curtain. Muff sleeve movement<br />
by hydraulic cylinder<br />
Safety barriers To prevent access through service<br />
bench during pushing.<br />
Door Extractor With Vertical compensation<br />
Door turn by Hydraulic Cylinder<br />
Frame Cleaner Spring mounted scrapers to clean<br />
sealing surfaces, internal side surfaces,<br />
oven sole & side surfaces, mounted on<br />
carriage with vibrator.<br />
Oven sole cleaning with compressed<br />
air. Vertical & Horizontal movements by<br />
means of Hydraulic cylinders<br />
Door Cleaner Spring mounted cleaning tools<br />
Page 11 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
mounted on travelling carriage with<br />
vibrator. Hydraulic cylinder operated<br />
Operator‟s Cabin Double – walled with insulation.<br />
Air conditioned. Roof & side sheeting –<br />
SS plates<br />
Hydraulic cabin Double – walled with insulation.<br />
Air conditioned. Roof & side sheeting –<br />
SS plates<br />
Electronic panel Cabin: Double – walled with insulation.<br />
Air conditioned. Roof & side sheeting–<br />
SS Plates<br />
Electric Panel Cabin Ventilated with pressurised filtered air<br />
UPS<br />
Interlocking with other Oven<br />
Machines<br />
See Electrics (Annexure-II)<br />
See Electrics (Annexure-II)<br />
Hydraulic System :<br />
Fluid Water Glycol<br />
Main Pumps Pressure compensated axial piston<br />
pumps ( 1 working, 1 standby)<br />
Cooling filtration System Separate with air – oil cooler and<br />
duplex filter<br />
Tank Stainless Steel oil tank, t = 6 mm<br />
Piping Stainless Steel pipelines & fittings<br />
Emergency Drive By accumulator and hand pump<br />
Pneumatic System - 2 Compressors on each pusher car.<br />
- Air Receiver of <strong>10</strong> m 3 capacity.<br />
- for Degraphitising of oven roof<br />
and stand pipe ports<br />
- Blowing soot from the ram rack<br />
surface<br />
- For emergency withdrawal<br />
mechanisms<br />
Page 12 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Air conditioners Split type (LINTERN,USA make)<br />
Laser gun To be provided for spotting<br />
<strong>Heavy</strong> duty Industrial Vacuum For Cleaning Cabins & equipments<br />
Cleaner<br />
Water jet with SS tank To Quench spilt coke & door blazing<br />
Pushing Load transfer To civil foundation of Pusher car track<br />
Page 13 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
1.7 Desired Speeds:<br />
1.8 Other Parameter:<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
a) Long Travel 60 m/min.<br />
b) Pusher 25 m/min.<br />
c)<br />
d)<br />
Leveller:<br />
Door screw turning<br />
45 m/min.<br />
Through cyclo gear box<br />
e)<br />
f)<br />
Other mechanisms:<br />
<strong>No</strong>. of pushes<br />
Designed speed of drives<br />
shall be commensurate<br />
with the overall machine<br />
cycle time<br />
96/day<br />
g)<br />
h)<br />
Cycle time<br />
Speed of hydraulically<br />
operated devices<br />
Less than 600 seconds<br />
6 m/min<br />
1.8.1 Height of end buffers above rail 755mm<br />
level<br />
1.8.2 Clearance with the battery As per machinery diagram<br />
1.8.3 Buffer to buffer distance 15700 mm<br />
1.8.4 Distance from oven face (Hot) to<br />
first rail<br />
3862 mm<br />
1.8.5 Clearance 320<strong>04</strong> mm between CL of<br />
battery and extreme point<br />
of machine outer edge<br />
along the length of oven.<br />
1.8.6 Oven sole level (Hot) +84323 mm<br />
1.8.7 Pusher ram length 22320 mm<br />
1.8.8 Pusher ram travel 19750 mm<br />
1.8.9 Max. Pushing force 28t<br />
1.8.<strong>10</strong> Leveller Bar length 21600 mm<br />
Page 14 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Leveller bar travel 144<strong>10</strong> mm<br />
1.8.11 Wheel loads <strong>No</strong>t more than 19 tons<br />
(Max. permissible load due<br />
to limitations of the<br />
existing track)<br />
1.8.12 Power Supply and Electrical<br />
Systems<br />
1.9 Drives:<br />
Power Supply 415 Volt.,3 phase ,50 Hz<br />
Control Voltage 230 Volt, single phase ,AC,<br />
50 Hz<br />
Lighting, air- conditioning and fans 230 Volt, single phase ,AC,<br />
50 Hz<br />
Solenoid valves 24V D.C<br />
Motion Drive<br />
- Travel Electric motor with gear box<br />
- Pushing Electric motor with gear box<br />
- Leveller Electric motor with gear box<br />
- Door screw turning Through Cyclo gear box<br />
- Door swiveling By Hydraulic cylinders<br />
- Door Extractor Travel Hydraulic Cylinder<br />
- Door Lift LDT mounted hydraulic cylinder<br />
- Door Latch bars Hydraulic Cylinder<br />
- Vertical<br />
Compensation device<br />
for door extraction<br />
LDT mounted hydraulic cylinder<br />
Page 15 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
- Frame Cleaner Travel<br />
- Frame Cleaner<br />
swiveling<br />
Hydraulic Cylinder<br />
By Hydraulic cylinders<br />
- Frame Cleaning Hydraulic Cylinder<br />
- Frame cleaner spring<br />
pressing<br />
Hydraulic Cylinder<br />
- Frame cleaner fixing Hydraulic Cylinder<br />
- Frame cleaner<br />
blocking<br />
- Door Cleaner Carriage<br />
- Door top horizontal<br />
cleaning<br />
- Door bottom<br />
horizontal cleaning<br />
Hydraulic Cylinder<br />
Hydraulic Cylinder<br />
Hydraulic Cylinder<br />
Hydraulic Cylinder<br />
- Door vertical cleaning Hydraulic Cylinder<br />
- Door Cleaning travel<br />
- Leveller Door opening<br />
- Leveller Hood muff<br />
- Leveller Sluice travel<br />
Hydraulic Cylinder<br />
LDT mounted hydraulic cylinder<br />
Hydraulic Cylinder<br />
Hydraulic Cylinder<br />
Page 16 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
- Spillage Coke<br />
deflector<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Hydraulic Cylinder<br />
- Coal spillage chute Hydraulic Cylinder<br />
- Spillage Coal Bin<br />
Discharge Gate<br />
1.<strong>10</strong> Functional Description<br />
1.<strong>10</strong>.1 List of Functions:<br />
1.<strong>10</strong>.2 Spotting<br />
Hydraulic Cylinder<br />
These are the functions required for servicing the ovens:<br />
- Machine travelling<br />
- Door servicing including slewing<br />
- Interlocking the machine during the pushing procedure<br />
- Pushing of the coke<br />
- Removal of roof carbon in the gas collecting space in the oven<br />
chamber.<br />
- Removal of carbon from the standpipe port in the oven<br />
chamber.<br />
- Opening and closing the leveller door.<br />
- Sealing the leveller hole during levelling by leveller muff & air<br />
curtain.<br />
- Levelling the coal charge.<br />
- Cleaning the oven door.<br />
- Cleaning the door frame.<br />
- Collection and removal of leveller coal.<br />
- Removal of door cleaning residue into a collecting device.<br />
- Guiding of spilt coke to the spillage conveyor.<br />
- Collection & disposal of debris collected during ram withdrawal<br />
& door cleaning<br />
- Generation of compressed air.<br />
- Generation of hydraulic pressure.<br />
- Air-conditioning of operator‟s cabin, electronic panel cabin &<br />
hydraulic cabin.<br />
- Emergency withdrawal of the pusher and leveller beams.<br />
- Spotting with the aid of laser spotting.<br />
Page 17 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
The Coke Pusher machine shall be spotted into working position at an<br />
accuracy of ± 5 mm or even better.<br />
For further details, refer Electrical write-up Annexure-II<br />
1.<strong>10</strong>.3 Door Extracting:<br />
The door servicing equipment is slewed into working position and<br />
moved in front of the oven. The hydraulically operated lifting device<br />
moves the extraction arms under the extraction beams of the door.<br />
The door latches are disengaged the unscrewing them with the help of<br />
Cyclo gear box.<br />
Hydraulic cylinder of the Vertical Compensation Device is blocked in<br />
tilted position. This is to ensure that the deviation from the vertical,<br />
which is caused by the chamber frame, shall be maintained while<br />
latching the door back after its pushing operation is over so that<br />
damage to the chamber frame and door sealing is avoided.<br />
The door is then lifted by 30 mm approx. with the help of LDT<br />
mounted hydraulic cylinder, run back, lifted into the final position (to<br />
obtain the same level for the cleaning equipment) and slewed into the<br />
door cleaning equipment.<br />
Re-installation of the door after completion of the pushing procedure<br />
and cleaning of the chamber frame is carried out in reverse sequence.<br />
1.<strong>10</strong>.4 Pushing and Carbon Removal:<br />
Prior to the beginning of pushing procedure, the machine sub<br />
structure shall be securely held in position with the help of a wedge<br />
type mechanism which can be lowered & lifted in order to provide a<br />
firm rest on the vertical impact surface on the machine track<br />
foundation. The traveling drives are then interlocked.<br />
Pusher and leveller shall be driven by electric motors which, in<br />
connection with mill duty electro- magnetic DC brakes and /or<br />
proximity switches, ensure precise attainment of final or intermediate<br />
positions.<br />
Page 18 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
1.<strong>10</strong>.5 Levelling:<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
For the removal of carbon from the gas collecting space, a carbon<br />
scraper on the pusher head and additional nozzles made of stainless<br />
steel charged with compressed air shall be provided.<br />
An additional stainless steel nozzle supplied with compressed air<br />
cleans the pusher side standpipe port in the Oven Chamber.<br />
The equipment for leveling and for opening and closing the leveller<br />
doors are located 5 oven pitches away from the center line of the<br />
pusher beam.<br />
The leveller doors shall be opened or closed from the driver‟s cabin.<br />
Thus, it is possible to open the leveller door of oven N-5, level oven<br />
and close the leveller door again of oven N-5 when the pusher<br />
machine is in the proper position for pushing oven N.<br />
The spilled coal during leveling shall be collected in a bunker which<br />
shall be so designed that the coal from 14 (fourteen) oven cycles<br />
(working cycles) can be accommodated in it. Bunker inner surfaces<br />
shall be provided with stainless steel liners.<br />
The leveller coal is emptied from the collecting bunker into the<br />
existing spillage coal bunker of skip hoist at the coal tower.<br />
1.<strong>10</strong>.6 Door and frame Cleaning:<br />
During the pushing procedure, the door cleaning machine is moved to<br />
the slewed coke oven door and cleaning is done by horizontal and<br />
vertical tools moving to and fro, on the surfaces which are important<br />
for satisfactory sealing of the coke oven doors. All cleaning<br />
procedures are affected by resiliently compressing scraping tools.<br />
These are fixed at such intervals that the cleaning strokes overlap<br />
each other.<br />
After completing the pushing procedure, the door frame cleaning<br />
machine, by slewing and moving it in front of the chamber frame,<br />
cleans the front surface of the door frame using tools moving to and<br />
fro, which is important for satisfactory sealing of the coke oven doors.<br />
Internal side surface are cleaned by separate set of cleaning tools.<br />
Page 19 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Additionally, with a special provision, the oven sole in the area of the<br />
door plug and the lateral wall sections up to a height of 0.5 m approx.<br />
are likewise cleaned. This is carried out by resiliently compressing<br />
scraping tools, the distances of which ensure safe overlapping of the<br />
intended cleaning strokes. The cleaning of stubborn deposits is<br />
assisted by vibrator & oven sole is cleaned by compressed air<br />
supplied through nozzles suitably located on the door frame cleaner.<br />
Thereafter, the oven door is reinstalled again.<br />
The spilled coke after each pushing and door frame cleaning<br />
procedure is quenched by high pressure water jet & guided on to the<br />
spillage conveyor located on the service platform.<br />
The door cleaning spillage is caught by a chute and likewise<br />
transferred to the collecting bin.<br />
1.<strong>10</strong>.7 Emergency Drive for Pusher/ Leveller<br />
An emergency air motor drive connected through a reduction gear<br />
box and hand operated clutch arrangement to the main drive of the<br />
ram beam shall be provided for emergency withdrawal of the ram.<br />
Additionally, an electrical winch with manual operation facility shall be<br />
provided as a failsafe device.<br />
The air motor shall be able to withdraw the Pusher Ram even at an<br />
operating pressure of 2.5 Bar.<br />
For withdrawing the Leveller bar in case of emergency an electrical<br />
winch with manual operation facility shall be provided.<br />
1.<strong>10</strong>.8 Water tank with compressed air lines and outlet water lines for coke<br />
quenching & putting off door blazing to be provided.<br />
1.11 Control and Interlocks:<br />
The machine shall be controlled by the Operator from a position at the<br />
main control desk. This shall be laid out in an ergonomical manner and<br />
each main function shall be controlled in “automatic mode” by one desk<br />
switch e.g. “Remove Door” or “Replace Door”. The individual motions of<br />
each main function shall be controlled by individual switches when in<br />
“manual mode”, this feature is being provided for maintenance purpose.<br />
Interlocks<br />
Page 20 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Travel Drive Operation by Frame Cleaner, Retracted<br />
Left or Right Control handle<br />
with dead mean<br />
feature<br />
Door Extractor<br />
Remove Door<br />
Replace Door<br />
Automatic from<br />
desk switch<br />
Pusher Ram Push Operation<br />
by control handle<br />
on desk<br />
Door Extractor, Retracted<br />
Leveller Door Opener,<br />
Retracted<br />
Pusher Ram, Retracted<br />
Leveller Retracted<br />
Pusher Beam, Retracted<br />
Door frame Cleaner,<br />
Retracted<br />
Door Cleaner, Retracted<br />
Travel Stopped<br />
Door frame Cleaner,<br />
Retracted<br />
Arm, retracted<br />
Door Hooks, Engaged<br />
Door, Lifted<br />
Cross Battery, Signalled<br />
Interlock<br />
NOTE : Beam shall return automatically from end of stroke<br />
Door Cleaner Automatic from<br />
switch on control<br />
desk<br />
“Clean” Desk or bench<br />
control (by<br />
Door frame<br />
Cleaner<br />
selection)<br />
Automatic from<br />
switch on control<br />
desk<br />
Door Extractor Retracted<br />
Door Extractor, Hooks<br />
Raised<br />
Pusher Beam, Retracted<br />
Door Extractor, Retracted<br />
“Clean” Control desk Door Hooks Raised<br />
Long Travel Stopped<br />
Leveller Door Automatic from Long Travel Stopped<br />
Opener switch on control<br />
desk<br />
Open/Close Automatic from Long Travel Stopped<br />
Levelling switch on control<br />
desk (number of<br />
strokes variable)<br />
Coal Spillage Hydraulic valve Ramp on bench operates<br />
control by bench- permissive valve to dump<br />
man<br />
coal to elevator boot at<br />
Page 21 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
coal bin.<br />
Additional interlocks, if required shall be incorporated during detail<br />
engineering.<br />
1.12 Operator Cabin:<br />
The Operator‟s cabin shall consist of a steel framed cabin with bay<br />
type front window in toughened glass set in rubber strip. The control<br />
console shall be situated at the front of the cabin where there shall be<br />
good visibility of all the motions of the machine. The cabins shall be<br />
double-walled with thermal insulation and shall be air-conditioned.<br />
Outer walls & roof of operator‟s cabin shall be of stainless steel. All<br />
fixtures, fasteners & fittings on the cabin shall be of Stainless steel.<br />
Ambient temperature of machine operation shall be 60°C. Inside cabin<br />
the temperature shall be maintained at 24± 2˚C.<br />
The cabin shall have double door entrance, with heavy duty door<br />
fixtures. The cabin shall be provided with cabin fans at suitable<br />
locations.<br />
1.13 Electronic & Electric Cabin:<br />
Immediately behind the operator‟s cabin shall be a wall with access<br />
door leading on to the adjacent but separate cabin, to house the<br />
electronic control equipment. The electronic panels shall be housed in<br />
this cabin. This cabin shall be double-walled with thermal insulation<br />
and air-conditioned. Outer walls & roof of Electronic cabin shall be of<br />
stainless steel. All fixtures, fasteners & fittings on the cabin shall be of<br />
Stainless steel. Inside cabin the temperature shall be maintained at<br />
24± 2˚C.<br />
The electric cabin shall be pressurized and ventilated by filtered air<br />
from fan filter units to prevent ingress of dust/ outside air. The cabin<br />
shall be provided with double door entrance. Outer walls & roof of the<br />
electrical cabin shall be of stainless steel. All fixtures, fasteners &<br />
fittings on the cabin shall be of Stainless steel. Ambient temperature<br />
of machine operation shall be 60°C.<br />
1.14 Hydraulic Cabin:<br />
Page 22 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
A separate cabin shall be built on the lower platform level of the<br />
machine to house the hydraulic equipment. The cabin shall be doublewalled<br />
with thermal insulation and shall have double door entrance.<br />
The cabin shall be air- conditioned. Outer walls & roof of hydraulic<br />
cabin shall be of stainless steel. All fixtures, fasteners & fittings on the<br />
cabin shall be of Stainless steel. Inside cabin the temperature shall be<br />
maintained at 24± 2˚C.Ambient temperature of machine operation shall<br />
be 60°C.<br />
Layout of the hydraulic equipments within the hydraulic cabin shall<br />
ensure adequate space for maintenance. The tank, main pumps &<br />
valve stand shall have separate location within the Hydraulic cabin.<br />
ELECTRICS<br />
2.0 Scope of supply & work:<br />
i) Work order no. 0093-002-1<strong>10</strong><br />
ii) Item code 5531711158<br />
-3:iii)<br />
Qty.<br />
1 set. for each coke pusher<br />
-3:iv)<br />
Total Qty.<br />
2 sets.<br />
2.1 (a) This tender specification calls for turnkey execution of the job<br />
covering<br />
the design, engineering, manufacture, supply FOR <strong>HMB</strong>P stores at<br />
Ranchi, receipt of material from purchaser‟s store at DSP,<br />
transportation from purchaser‟s store at DSP to coke oven site,<br />
handling, storage and re-conservation at DSP site, erection, testing,<br />
commissioning of electrics with standard accessories and attachment<br />
as covered in this specification. Demonstration of the proper<br />
functioning of the electrical system during performance guarantee test<br />
of the equipment in a coordinated and integrated manner as per the<br />
relevant clauses of this specification.<br />
(b) The technical specification shall be read in conjunction with General<br />
Page 23 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Technical Specification (GTS).The provisions given in these<br />
documents shall be complimentary to one another. However, in case of<br />
any conflict between the provisions of these documents with respect<br />
to technical matter, the provisions in the technical specification shall<br />
prevail.<br />
(c) The scope of supply and work covers turnkey execution of complete<br />
electrics for coke pusher machine. The BOQ indicated in this<br />
specification covers all major electrical components. Any component<br />
not covered in this BOQ, but considered essential for proper<br />
functioning of the electrical system within the parameter of this<br />
specification shall be deemed to be included in the scope of work of<br />
this tender.<br />
2.2 Reference drawings & documents(Intrested tenderer may request for soft copy of<br />
the drawings/documents.<br />
1) Single line diagram- 1522.96.001<br />
2) PLC configuration diagram- SK-EDB-<strong>10</strong>91<br />
3) Sketch for electrical panel room-SK-EDB-<strong>10</strong>55<br />
4) GA Drg. of coke pusher-1522.61.000<br />
5) GCC- Relevant clauses applicable to tenderer.<br />
2.3 The scope of work of <strong>Tender</strong>er shall include but not be limited to the following:<br />
� Current collectors.<br />
� Isolators and protective switch gear<br />
� AC Motors, Inverter duty motors fed from VVVF Drives, D.C.<br />
Electromagnetic brakes.<br />
Page 24 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Rotary type, lever type, non-contact type limit switches and<br />
safety switches.<br />
� Various types of sensors.<br />
� Resistances.<br />
� Motor control panels.<br />
� Control desks for housing HMI system and other equipment as<br />
per specifications and inductive master controller for VFD<br />
drives etc.<br />
� Programmable logic controller complete with required inputs /<br />
outputs for Pusher car. Touch screen monitors (15” or higher )<br />
with inbuilt RAM, key board, printers and other required<br />
peripherals. Cold standby system with redundant CPU, Power<br />
supply and communication porcessor shall be provided in each<br />
machine PLC. CPU shall be of latest version type.<br />
� Variable voltage & variable frequency AC drives, tacho-<br />
generators/pulse encoders.<br />
� Uninterrupted power supply system.<br />
� Lighting transformer, lighting distribution panels, lighting<br />
fixtures with lamps, socket outlets..<br />
� Power, control, heat resistant, communication & special cables.<br />
� Earthing equipment and materials including electronic earthing.<br />
� Submission of Drawings and documents including GA, SLD,<br />
BOM, Control scheme, QAP and all layout drawings, technical<br />
catalogues/ Data sheets.<br />
� Arranging construction power supply and temporary lighting<br />
during storage, erection, testing and commissioning.<br />
� Adequate number of shock treatment charts, danger and<br />
caution notice boards, first aid boxes, keys with key boxes,<br />
rubber mats.<br />
Page 25 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Electrical room / operator room furniture.<br />
� Erection/installation/fixing materials like GI pipes, supporting<br />
structures for mounting of equipment, cable trays and<br />
their supporting structures, cable and pipe clamps, ferrules,<br />
asbestos wire rope etc.<br />
� Commissioning spares & Consumables as required till the plant<br />
is commissioned and handed over to Purchaser. Minimum<br />
commissioning spares shall be supplied along with main<br />
equipment.(as per schedule- 1)<br />
� Two years spares for normal operation & maintenance of<br />
equipment.(as per schedule-8)<br />
� Tools & tackles required for maintenance of equipment. (as per<br />
schedule- 2).<br />
� Radio positioning & interlocking system for Pusher Cars shall be<br />
provided under Coke Heating & Control System (CHCS) Package.<br />
Following shall be provided by <strong>Tender</strong>er (Machine package supplier)<br />
to ensure proper implementation of Radio positioning & interlocking<br />
system and CHCS System and included in scope of supply of<br />
<strong>Tender</strong>er.<br />
a. Porfibus connectivity to CHCS system PLC (Siemens<br />
make CPU-315-2DP). One number panel enclosure<br />
(800mm width) for mounting CHCS PLC and other<br />
accessories shall be provided inside the electric cabin.<br />
b. Machine operated related data generation essentially<br />
required for interlocking<br />
c. Joint implementation of communication software between<br />
m/c PLC and RTUs under CHCS system Package.<br />
d. UPS Power supply (<strong>10</strong>00VA) for CHCS PLC and other<br />
accessories.<br />
e. Aux. power supply as required.<br />
f. VVVF Drive for Machine travel mechanism shall be<br />
provided with Torque & Vector control so that Machine<br />
should operate at 3% creep speed.<br />
g. HMI Screen implementation (5 pages min.)<br />
h. Number of Tags as required.( 200 minimum).<br />
Page 26 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
i. <strong>Tender</strong>er shall work in close coordination with other<br />
automation suppliers and CHCS Package supplier for<br />
establishment of proper communication between oven<br />
machines, integrated operation of Oven machine radio<br />
positioning & interlocking up to 6 months from the date of<br />
commissioning for maximum three visits of one week<br />
each.<br />
j. Space for cabling, cable trays, GI pipes etc by CHCS<br />
supplier.<br />
� Data as required for CHCS system shall be provided by<br />
<strong>Tender</strong>er and the same shall be finalized during detail<br />
engineering as per system requirement.<br />
� <strong>Tender</strong>er scope of supply includes all the components,<br />
materials and accessories required to render the equipment<br />
and system offered complete and fully operative in all<br />
respects even though every individual item necessary might<br />
not have been detailed out explicitly in this specification.<br />
� Items not specifically mentioned but required for successful<br />
completion of the work are included in the scope of work of the<br />
<strong>Tender</strong>er.<br />
� The drawings shall be furnished by the tenderer during detail<br />
engineering as listed in clause-27 of this specification. Approval<br />
of these drawings from DSP/ MECON shall be responsibility of the<br />
tenderer<br />
Page 27 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
2.4 The scope of supply for each coke pusher shall cover, but not be<br />
limited to the following items :-<br />
Sl.<br />
<strong>No</strong>.<br />
BILL OF QUANTITY (BOQ), for each coke pusher<br />
Description Qty.<br />
1 Spring loaded current collector, 500A 8 <strong>No</strong>s.<br />
2 Gravity type current collector, 500A (for earthing through rail) 2 <strong>No</strong>s.<br />
3 Isolator Panel, 630A 1 <strong>No</strong>.<br />
4 PDB (for details refer SLD) 1 Set<br />
5 MCC (for details refer SLD) 1 Set<br />
6 Control supply transformer, <strong>10</strong> KVA 2 <strong>No</strong>s.<br />
7 UPS system, 5 KVA, 30 min. Back-up time.<br />
The UPS shall confirm to the specification as indicated in<br />
schedule-7.<br />
1 Set<br />
8 VFD for Travel motors(<strong>Heavy</strong> duty continuous current rating<br />
at 50 0C should be minimum-202A).<br />
The VFD shall confirm to the specification as indicated in<br />
2 Sets.<br />
9 schedule-5 DC Power pack, input 240V AC, output 24VDC,rated-50A 1 Sets<br />
<strong>10</strong> continuous.<br />
DBR for Travel VFD (Continuous rating minimum 12 Kw) 2 Sets.<br />
11 DC Brake and BRP for Travel motors (4 X Ø300 mm Brake + 4<br />
nos. BRP, for each brake separate rectifier panel shall be<br />
provided)<br />
1 Set<br />
12 Incremental Pulse encoder for Travel motors 2 <strong>No</strong>s.<br />
13 30 KW Travel motors, Frame – 225 M, 6 Pole.<br />
The Motor shall confirm to the specification as indicated in<br />
schedule-6<br />
4 <strong>No</strong>s.<br />
14 VFD for Pusher RAM motors(<strong>Heavy</strong> duty continuous current<br />
rating at 500C should be minimum- 358 A)<br />
The VFD shall confirm to the specification as indicated in<br />
schedule-5<br />
1 <strong>No</strong>.<br />
15 DBR for Pusher RAM VFD(Continuous rating minimum 22 Kw) 1 <strong>No</strong>.<br />
Page 28 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
16 DC Brake and BRP for Pusher motor (1 X Ø500 mm + 1 no. BRP) 1 Set<br />
17 Incremental Pulse encoder for Pusher RAM motor 1 <strong>No</strong>.<br />
18 1<strong>10</strong> KW Pusher RAM motor, Frame – 315 L, 8 Pole<br />
The Motor shall confirm to the specification as indicated in<br />
schedule-6<br />
1 <strong>No</strong>.<br />
19 VFD for Leveller RAM motor (<strong>Heavy</strong> duty continuous current<br />
rating at 500C should be minimum-<strong>10</strong>3A)<br />
The VFD shall confirm to the specification as indicated in<br />
schedule-5<br />
1 <strong>No</strong>.<br />
20 DBR for Leveller RAM Drive(Continuous rating minimum 6<br />
Kw)<br />
1 <strong>No</strong>.<br />
21 DC Brake & BRP for Leveller RAM motor (1 X Ø300 mm + 1 no.<br />
BRP)<br />
1 <strong>No</strong>.<br />
22 Incremental Pulse encoder for Leveller RAM motor 1 <strong>No</strong>.<br />
23 30 KW Leveller RAM motor, Frame – 250 M, 8 Pole<br />
The Motor shall confirm to the specification as indicated in<br />
schedule-6<br />
1 <strong>No</strong>.<br />
24 2.2 KW screw turning motor, Frame – 112 M, 6 Pole 2 <strong>No</strong>s.<br />
25 Resistance boxes for Door screw motor (8 Ω / ph, 29A<br />
continuous)<br />
2 Sets<br />
26 Lighting supply transformer, <strong>10</strong> KVA 1 <strong>No</strong>.<br />
27 Red warning lamp, ambulance type 2 <strong>No</strong>s.<br />
28 Laser Gun for spotting the machine 1 <strong>No</strong>.<br />
29 Machine illumination fittings with lamp 1 Set<br />
30 Absolute encoder for Pusher RAM Drive 1 <strong>No</strong>.<br />
31 Absolute encoder for Leveller RAM Drive 1 <strong>No</strong>.<br />
32 Control Desk (all the three master controllers in the control<br />
desk shall be suitable for 4-20mA analog signal, equivalent to<br />
GUSSMAN make, type no. – V81LB1T)<br />
1 <strong>No</strong>.<br />
33 Local control Panels (13 nos. approx.)in SS enclosure 1 Set<br />
34 Junction boxes in SS enclosure 1 Set<br />
Page 29 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
35 Limit switches<br />
a)Roller lever,heavy duty type limit switches(4 nos)<br />
b)Inductive type proximity limit switches with temperature<br />
protection housing.(28 nos), (equivalent to TURCK make, type<br />
no. – Ni-35-CP40-AN6X2 with protective housing-SG40/2)<br />
c) Magnetic type proximity limit switches with temperature<br />
protection housing (8 nos). (equivalent to TIEFENBACH make,<br />
type no. – WK209/2)<br />
1 Set<br />
36 PLC system, cold standby system with redundant CPU, power<br />
supply and communication processor.<br />
The PLC shall confirm to the specification as indicated in<br />
schedule-4<br />
Ambient temperature - 60°C.<br />
Supply voltage – 24VDC.<br />
RAM memory- 1MByte (minimum) with battery backup.<br />
<strong>No</strong>n volatile memory backup.<br />
I/O handling capabilities –<br />
Discrete I/O - <strong>10</strong>000 (minimum)<br />
Analog I/O - 4000 (minimum)<br />
For other details refer PLC configuration diagram<br />
1 Set<br />
37 Foot switch for electric bell 1 <strong>No</strong>.<br />
38 Light fitting(Refer SLD) 1 Set<br />
39 HMI, 15” touch screen, minimum 3000 tags, 200 screen 1 <strong>No</strong>.<br />
40 Printer – A4 size Laser printer. 1 <strong>No</strong>.<br />
41 List of Softwares<br />
1. PLC programming software.<br />
2. HMI configuration software.<br />
3. Drive parameterisation software.<br />
1 Set<br />
42 Power cable, control cable (flexible copper cables) and all<br />
special cables for PLC, pulse encoder etc.<br />
1 Lot<br />
43 Cable accessories 1 Lot<br />
44 Erection accessories inclosing mounting channels, fasteners<br />
etc.<br />
1 Lot<br />
Page 30 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
45 Asbestos rope for braiding on the cables exposed to<br />
heat/radiation.<br />
1 Lot<br />
46 Commissioning spare (as per schedule – 1) 1 Lot<br />
47 Tools, tackles and instruments (as per schedule – 2)<br />
The minimum configuration of the Laptop shall be as given<br />
below-<br />
Core i7-2620M(2.5 GHz/1333/3 MB/35W) or higher, 8 GB RAM, 500GB<br />
HDD or higher, DVD-RW, 14.0" LED Back-Lit AntiGlare HD Display, HD<br />
Webcam, Dedicated Graphics with 1 GB GDDR5 Memory, Wireless LAN,<br />
Bluetooth, , USB 3.0, 6-in-1 Media Reader, 6 Cell Battery, MS Windows 7 Pro<br />
64 Bit .<br />
1 SET<br />
48 Documents –<br />
1 SET<br />
The laptop shall have following software loaded.<br />
1. Application software (PLC & HMI)<br />
2. Drive parameter list.<br />
3. Operation manual (Drive + PLC +HMI)<br />
4. PLC programming manual<br />
5. HMI programming manual<br />
CD<br />
49 2 years operational spare (only list to be furnished) 1 Lot<br />
List of Proximity Switches & Limit Switches mounted on various mechanism:.<br />
1. Proximity Switches (magnetic type)<br />
Long Travel Mechanism - 2 nos.<br />
Pushing Mechanism - 2 nos.<br />
Levelling Mechanism - 2 nos.<br />
Spare switches - 2 nos.<br />
Page 31 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
2. Proximity switches (non-magnetic type)<br />
Pushing Mechanism<br />
Emergency Drive - 2 nos.<br />
Levelling Mechanism<br />
Emergency Drive - 1 no.<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Leveller Door Latch engaging - 2 nos.<br />
Smoke Sleeve Travel - 2 nos.<br />
Transfer Chute Travel - 2 nos.<br />
Spillage Coal Bunker Gate - 2 nos.<br />
Door Extractor<br />
Door Lifting & Lowering - 1 no.<br />
Door Latching & Unlatching - 2 nos.<br />
Door Cleaner<br />
Travel - 2 nos.<br />
Head Lifting & Lowering - 2 nos.<br />
Frame Cleaner Head Lifting & Lowering - 2 nos.<br />
Safety Barriers - 4 nos.<br />
Spare switches - 2 nos.<br />
3. Roller Lever Operated Limit Switches<br />
Pushing Emergency Winch Drive - 1 no.<br />
Page 32 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Levelling Emergency Winch Drive - 1 no.<br />
Spare switches - 2 nos.<br />
2.5 Scope of service: -<br />
2.5.1 Erection,Testing,Commissioning & Performance Guarantee test :<br />
2.5.1.1 Erection is included in the scope of work of the tenderer.<br />
2.5.1.2 For supervision of electrical erection work, the tenderer shall employ<br />
authorised persons holding valid electrical licence for the state of<br />
West Bengal.<br />
2.5.1.3 For erection, SAIL-DSP shall provide only electric power at nearest<br />
available point. All other arrangement shall be made by the tenderer<br />
of their own at their own cost.<br />
2.5.1.4 The consumables and spares required till successful commissioning<br />
of the coke pusher shall be arranged by the tenderer.<br />
2.5.1.5 All tools & tackles including special tools shall be arranged by the<br />
tenderer.<br />
2.5.1.6 The tenderer shall depute specialists in various disciplines from his<br />
organisation for erection, testing & commissioning. Exact period/<br />
duration for deputation shall be mutually discussed and finalised.<br />
2.5.1.7 The tenderer shall commission the complete electrical system of the<br />
machine.<br />
2.5.1.8 The tenderer shall ensure that a minimum manpower is always<br />
stationed at site and additional manpower, if required shall be<br />
deployed depending on exigency of work till commissioning.<br />
2.5.1.9 The coke pusher car shall be considered as commissioned on<br />
completion of first pushing of all the ovens provided it is completed<br />
within 30 days from the date of pushing of the first oven. However in<br />
case pushing of all the ovens is not completed within 30 days of the<br />
first pushing, commissioning would be deemed to be completed. The<br />
Page 33 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
tenderer shall be responsible for proper functioning of the electrical<br />
system during this PG test.<br />
2.5.1.<strong>10</strong> The electrical system of the machine shall be guaranteed for capacity,<br />
performance and reliability for a period of twelve (12) months from the date<br />
of reaching the rated pushing level within the period of three months from<br />
the commissioning of the Battery. All equipment & component parts shall be<br />
guaranteed by the <strong>Tender</strong>er against defective or improper materials, poor<br />
workmanship and failure from normal usage for one year from date of<br />
commissioning. If any defect or mal-performance occurs during the<br />
guarantee period, the tenderer shall make all the necessary/desirable<br />
alterations, repairs and replacements as desired by the Purchaser/<br />
Purchaser’s representative without any cost to the Purchaser.<br />
2.5.1.11 The performance of individual machine shall be demonstrated for the<br />
following parameters:<br />
� Continuous and trouble free operation of the machine for 15<br />
days maximum or as decided by the Purchaser at rated capacity<br />
of 96 pushings per day. During the above period, all<br />
mechanisms shall be made functional and shall operate in the<br />
proper sequence as envisaged in the design. For non-fulfillment<br />
of above performance attributable to the electrical system of<br />
the machine, 0.1 % of the total value of electrical system<br />
package shall be deducted for shortfall of every one oven of<br />
production.<br />
2.5.1.12 Separate experts for electrical system shall be deputed during PG test.<br />
2.5.2 Responsibility matrix for free issue items :-<br />
Sl.<br />
<strong>No</strong><br />
.<br />
Equipment Equipment<br />
supply<br />
Cable<br />
Supply<br />
Installati<br />
on<br />
Commissio<br />
ning<br />
1. Air Conditioning Equipment<br />
a. A/c Unit HEC <strong>Tender</strong>er HEC HEC<br />
b. Control<br />
Panel<br />
HEC <strong>Tender</strong>er <strong>Tender</strong>e<br />
r<br />
Assistance<br />
By<br />
<strong>Tender</strong>er<br />
Page 34 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
2<br />
3<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Lubrication equipment<br />
Control<br />
panel<br />
Pushing ram winch<br />
Control<br />
panel<br />
4 Leveling ram winch<br />
Control<br />
panel<br />
HEC <strong>Tender</strong>er <strong>Tender</strong>e<br />
r<br />
HEC <strong>Tender</strong>er <strong>Tender</strong>e<br />
r<br />
HEC <strong>Tender</strong>er <strong>Tender</strong>e<br />
r<br />
Assistance<br />
By<br />
<strong>Tender</strong>er<br />
Assistance<br />
By<br />
<strong>Tender</strong>er<br />
Assistance<br />
By<br />
<strong>Tender</strong>er<br />
5 Hydraulic system<br />
6<br />
a. Hydraulic HEC<br />
Unit<br />
b. Control <strong>Tender</strong>er<br />
panel<br />
Pneumetic system<br />
<strong>Tender</strong>er<br />
<strong>Tender</strong>er<br />
HEC<br />
<strong>Tender</strong>e<br />
r<br />
HEC<br />
<strong>Tender</strong>er<br />
a.<br />
pneumetic<br />
Unit<br />
HEC <strong>Tender</strong>er HEC HEC<br />
b. Control<br />
Panel<br />
<strong>Tender</strong>er <strong>Tender</strong>er <strong>Tender</strong>e<br />
r<br />
<strong>Tender</strong>er<br />
7 Vibrator HEC <strong>Tender</strong>er HEC HEC<br />
8 Air blower HEC <strong>Tender</strong>er HEC HEC<br />
for leveller<br />
9 Water pump HEC <strong>Tender</strong>er HEC HEC<br />
2.6 Following documents to be furnished by the tenderer along with the offer:-<br />
1. Clausewise confirmation of TS.<br />
2. List of deviation (if any).<br />
3. Details of offered motor, VFD, PLC system etc.<br />
4. Offered PLC configuration diagram.<br />
5. Details of HMI, absolute encoder, proximity switches.<br />
6. List of offered softwares for PLC, HMI & VFD.<br />
Page 35 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
3.0 Climatic Conditions<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
3.1 The equipment offered shall be suitable for tropical and humid climate.<br />
However maximum temperature and <strong>10</strong>0% humidity may not occur<br />
simultaneously. The equipment shall also be suitable for elevations up to<br />
<strong>10</strong>00 meters above mean sea level.<br />
3.2 For the purpose of equipment selection and specially for de-rating the<br />
capacities of drive motors, switch gear and power cable an ambient<br />
temperature condition shall be taken as 60°C. However, AC drive (VFD)<br />
shall be selected considering 50°C and PLC shall be selected considering<br />
55°C ambient temperature.<br />
3.3 The equipment and cable on the machine shall be suitably protected<br />
against damage from radiant heat and shooting flames. All electrical<br />
equipments shall be of weather- proof and also dust and vermin proof.<br />
Unless specified otherwise, the enclosure class of the equipment shall be<br />
IP-55. Enclosure class for PLC & VFD shall be IP-42.<br />
4.0 Standards<br />
4.1 The equipment shall be selected, assembled and tested as per guide lines<br />
provided in the latest edition of "Indian Standard Specification" <strong>No</strong>.<br />
IS: 4137-1985 for class 3 & 4 duty cranes and shall be subject to any<br />
modification and requirement specified by the Purchaser. Electrical<br />
equipment shall also conform to following Inter Plant Steel Standards<br />
(IPSS) :<br />
� 1-03-003-94 : AC mill/crane duty slip ring induction motors(second<br />
revision).<br />
� 1-03-0<strong>04</strong>-95 : AC crane duty squirrel cage induction motors<br />
(second revision).<br />
� 1-03-011-92 : AC cabin fans for EOT cranes (first revision).<br />
� 1-<strong>10</strong>-002-82 : Resistance boxes for power circuits (with<br />
amendment 1).<br />
� 1-<strong>10</strong>-005-81 : Master controller.<br />
Page 36 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� 1-<strong>10</strong>-006-81 : Drum/cam controller (with amendment 1).<br />
� 1-<strong>10</strong>-0<strong>10</strong>-84 : General requirements for control panels for cranes<br />
(with amendment 1).<br />
� 1-<strong>10</strong>-011-84 : Particular requirements for control panels for AC<br />
cranes (with amendment1).<br />
4.2 The equipment shall also conform to the latest "Indian Electricity Rules and<br />
Regulations" in regard to safety requirements, earthing and other essential<br />
provisions specified there in. The equipment shall be designed and selected<br />
to facilitate inspection, cleaning, replacement and repair and for use where<br />
continuity of operation and safety are the main considerations. The<br />
<strong>Tender</strong>er shall ensure that the equipments selected and provided by him<br />
shall have sufficient internal space for accommodating robust construction<br />
and adequate rating margins which experience has shown to be<br />
necessary in steel works operation and shall be ensured throughout<br />
manufacture.<br />
4.3 All imported equipment shall be as per IPSS/IS/IEC without diluting<br />
Purchaser's TS. In case of conflict between Purchaser's TS &<br />
IPSS/IS/IEC, Purchaser's decision shall be final.<br />
5.0 Power Supply Conditions<br />
5.1 The power from trolley lines shall be available at 415 volts, 3 phase, 4<br />
wire, 50Hz. The equipment selected shall be suitable for operation with<br />
voltage variation of +<strong>10</strong>% and -15%. The frequency variation shall be<br />
+4%, -6%. The combined voltage and frequency variation shall be +/-<br />
<strong>10</strong>%.<br />
5.2 The following voltage shall be used in the oven machine:<br />
� 415 volts, 3 phase, 50Hz AC for motors.<br />
� 240 volts AC +/-<strong>10</strong>%. for control circuit.<br />
� 240 volts, single phase 50 Hz AC for lighting, air conditioning,<br />
ventilation fans.<br />
� 240 V AC for socket outlets for hand tools.<br />
Page 37 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� 220 V, D.C. for electromagnetic brakes.<br />
� 24 V, D.C. for solenoid valves and I/Os of PLC..<br />
� 240 V, AC through UPS for PLC input supply.<br />
5.3 The different voltages mentioned above other than 415 volts, 3<br />
phase, 50Hz AC shall be derived through individual separate<br />
transformer and transformer rectifier units- connected to 415 volts AC.<br />
The transformer shall have + 5% & + <strong>10</strong>% taps on the primary side. One<br />
working and one standby transformer shall be provided for 240 volts AC<br />
control circuits.<br />
5.4 The short circuit level of the system shall be considered as 50 kA for 1<br />
sec.<br />
5.5 The maximum voltage drop during starting of motor shall be limited<br />
to 15 % at the motor terminals without effecting the performance of motors.<br />
The following shall also be noted:<br />
� The voltage available at the motor terminals during starting<br />
shall be sufficient to ensure positive starting and<br />
acceleration of the motor under fully loaded condition without<br />
any damage to the motor.<br />
� The voltage drop indicated shall be calculated with starting<br />
current corresponding to the rated voltage of the motor.<br />
� For DC supply and UPS outgoing feeders, it shall be ensured<br />
that the voltage available at the equipment being fed by DC/UPS<br />
feeders shall be as per equipment design basis.<br />
6.0 Technical Specification<br />
6.1 Current Collector & Trolley Lines<br />
6.1.1 The trolley lines (4-0 Grooved Copper Conductor) 3 Ph, 4 wire for<br />
operation of Pusher car shall be supplied and erected by the purchaser.<br />
The location of trolley lines shall be indicated by the purchaser in<br />
clearance diagram of the machine so that the <strong>Tender</strong>er can arrange for<br />
Page 38 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
the main current collectors suiting these dimensions. Fourth trolley<br />
shall be provided for electronic earthing purpose. The electrical earthing<br />
of the complete machine shall be through rail.<br />
6.2 Collector Shoes<br />
The collectors shall be provided with spring loaded adjustable base<br />
along with head assembly with swiveling action current collector for all<br />
the three phases and earth in line with existing batteries. The collectors<br />
shall have adequate current carrying capacity. The design of<br />
collector shoes shall be such as to minimise the chance of bending at the<br />
hinge points due to dust or corrosion. Minimum 2 nos. current collectors<br />
per phase and earth shall be provided. Current collector for Pusher car<br />
shall be suitable for trolley line.<br />
6.3 Collector Shunts<br />
6.4 Mountings<br />
Current carrying shunts on all the collectors shall be designed so that<br />
there is no danger of contact with adjacent collectors. The shunts shall<br />
be easily replaceable.<br />
All the collectors shall be mounted on rigid steel supports and suitably<br />
insulated. Electrical clearance between live parts of adjacent shoes shall<br />
be at least 25 mm. Flexible shunts in their least favorable position shall<br />
not reduce this clearance. Collectors shall be designed for ease of<br />
maintenance and mounted suitably so that they are readily accessible<br />
for this purpose. Accordingly suitable working platform shall be<br />
provided. Further current collector to be suitably located so that spillage<br />
of coal & oil from the car does not fall on collector.<br />
7.0 Specification of Motors<br />
7.1 Except for Air Conditioning, Compressor and hydraulic drives, all<br />
motors shall be crane duty suitable for minimum 150 starts per hour,<br />
having duty cycle rating S-4, 40% C.D.F., unless specified otherwise.<br />
Motors for air Conditioning, Ventilation, Compressor and hydraulic<br />
drives shall be S1 Duty. Motor fed from VVVF drive shall be Inverter<br />
duty as per specification.<br />
Page 39 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
All motors shall be totally enclosed, fan cooled, horizontal foot mounted with<br />
IP-55 protection class. The motors shall comply to the latest Indian,<br />
International standards and IPSS. The supplier shall be responsible<br />
for selecting the ratings that shall be required for the specified duty<br />
with type of control specified. Ambient temperature correction factors<br />
depending upon ambient temperature specified shall be used to de-rate<br />
the motor. The <strong>Tender</strong>er shall clearly indicate the above de-rating<br />
factors in their design. The motor bearing shall be heavy / medium duty<br />
series.<br />
The motor shall have cylindrical shaft extension.<br />
7.2 All motors shall be squirrel cage motors. Inverter duty Squirrel cage<br />
motors with AC drive shall be provided for drives requiring speed<br />
control.<br />
7.3 The motors shall be so selected that the motor temperature rise in actual<br />
service, which may include severe repetitive duty, interval of slow speed<br />
of operation, electrical braking requirements, etc., shall not exceed the<br />
permissible limits.<br />
7.4 Horse power<br />
7.5 Torque<br />
The motor horse power shall be computed as per IS: 4137-1985. The<br />
frame size shall be selected according to `kW' mentioned against it in the<br />
relevant IPSS specification shall not be less than the designed/computed<br />
power. The calculations for selection of motors shall be submitted to<br />
consultant for approval.<br />
The pull out torque of the motors at rated voltage and frequency shall<br />
not be less than 2.75 times of nominal torque.<br />
7.6 Class of Insulation<br />
The motors shall have minimum class „F‟ insulation with temperature<br />
rise limited to class „B‟. Inverter duty motors shall have class H<br />
insulation with temperature rise limited to class F.<br />
7.7 Thermistor Protection<br />
Page 40 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
The intermittent duty motors shall be provided with thermistors to take care<br />
of thermal over stressing.<br />
7.8 Travel motors on all the oven machines shall be preferably with<br />
synchronous speed of <strong>10</strong>00 rpm.<br />
8.0 Power distribution on machines<br />
8.1 An on-load manual MCCB isolator with locking facility shall be provided<br />
immediately after current collectors on incoming line on the machines.<br />
Power from the isolator shall be taken to the moulded case circuit<br />
breaker followed by a power contactor. This circuit breaker shall be of<br />
crane duty type. The breaker shall be provided with under voltage,<br />
overload and short circuit releases. Fault level for the protective<br />
switch gear shall be 50KA (minimum). Power to utilities like<br />
illumination, fans, air conditioning etc. shall be taken after isolator.<br />
8.2 Each motor feeder shall be provided with MCCB, contactor, EMPR<br />
and auxiliary contactors as required. Each solenoid feeder shall be<br />
provided with DPMCB and contactor suitable for DC rating. All power<br />
contactors shall be suitable for AC4 duty. Rating of power contactors<br />
shall be 50% higher than motor power requirement. MCB shall have<br />
minimum 9kA short circuit capacity.<br />
9.0 Specification of Main control desk<br />
9.1 Control desk shall be completely factory wired, sheet steel (CRCA, 2 mm<br />
thick) enclosed, free standing, floor mounted, with suitable covers and<br />
doors. Enclosure class shall be IP 54. It shall be suitable for corrosive<br />
atmosphere. The top cover where equipment shall be mounted shall be of<br />
stainless steel of thickness 2mm. All the equipment shall be mounted on the<br />
top cover with suitable inscriptions.<br />
8.2 Control desk in operator's cabin shall contain:<br />
� Machine power 'ON' push button and indication lights.<br />
� Selector switches for various sequences.<br />
Page 41 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Push buttons and indicator lights required for auxiliaries<br />
control.<br />
� Master controllers (inductive type / step by step type ) shall be<br />
provided for the following:<br />
� Machine travel.<br />
� Pusher beam, leveller bar for pusher machine.<br />
� Ammeters shall be provided for the following :<br />
� Pusher Ram Drive<br />
� Leveller Drive<br />
� Touch screen Monitor of HMI system and printer.<br />
� Operator station / control desk make shall be as per preferred<br />
make list.<br />
� Particular requirement :-<br />
- All the three master controller shall be mounted on<br />
separate vertical stand.<br />
- Master controller for Long Travel mechanism shall be on<br />
LHS of operator”s chair.<br />
- Master controllers for Pushing Ram & Levelling Ram shall<br />
be on RHS of operator”s chair.<br />
- Components for frame cleaning mechanism shall be on<br />
RHS facia of control desk.<br />
- Components for door cleaning mechanism shall be on<br />
LHS facia of control desk.<br />
- Components for door extracting mechanism shall be on<br />
front facia of control desk.<br />
<strong>10</strong>.0 Specification of Control panels<br />
<strong>10</strong>.1 All MCCBs, power and auxiliary contactors, EMPR, time relays etc. shall be<br />
mounted in sheet steel cubicles with lockable hinged doors. The door<br />
hinges shall be such that during repair work inside the panel, the door can<br />
be lifted and placed away enabling better access inside the panel. All<br />
ventilating openings shall have screen protection; interior of the panel<br />
Page 42 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
should be dust and vermin proof. Control panels shall be fully weather proof.<br />
Enclosure class shall be IP-54. Thermal overload relays shall not be used.<br />
<strong>10</strong>.2 Panels shall be front wired with readily accessible terminal blocks for<br />
making connection to the external equipment. Panels shall be pre-wired up<br />
to the terminal strip.<br />
<strong>10</strong>.3 All the contactors, etc. shall be mounted in vertical arrangement with<br />
due consideration to the vibration encountered in the operation of<br />
machine.<br />
<strong>10</strong>.4 The bottom most row of equipment mounted inside the panel<br />
excepting terminal strip shall be at least 350 mm above the panel<br />
bottom cover to facilitate inspection and repair. Panel shall be<br />
mounted such a way that bottom of panel is at least 150mm above the<br />
floor. The upper most row of equipment shall be at a height of 1550<br />
mm (maximum) from the floor.<br />
<strong>10</strong>.5 The terminal strip shall be fixed on the panel boards preferably in a<br />
horizontal manner, leaving enough space for termination of cables.<br />
Power and control terminals shall be separated from each other by<br />
means of replaceable insulated spacers. Terminal blocks shall have<br />
enough clearance to avoid tracking. The minimum size of terminal<br />
block shall be suitable for <strong>10</strong> mm 2 conductor. The minimum size of<br />
control terminal block shall be suitable for 4 mm 2 conductor.<br />
<strong>10</strong>.6 All equipment on the panel board shall have permanent identification<br />
label in accordance with the circuit diagram and also the power<br />
and control terminals.<br />
<strong>10</strong>.7 Terminal blocks shall be robust and of such construction so as to<br />
preclude the possibility of cable connections getting loose due to<br />
vibration on the machine. Sheet steel used for fabrication of panel<br />
shall be CRCA having minimum thickness of 2.0 mm. Panel shall be<br />
mounted such that bottom of panel is at least 150 mm above the floor.<br />
<strong>10</strong>.8 Panels shall be suitable for operation in corrosive atmosphere.<br />
<strong>10</strong>.9 Each panel shall accommodate equipment for one motion only.<br />
However, equipment for auxiliary drives may be clubbed in one or<br />
Page 43 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
more panels. Power and control terminals shall be segregated. 20%<br />
spare control terminals shall be provided in each panel.<br />
<strong>10</strong>.<strong>10</strong> Fault indications shall be available on the doors.<br />
<strong>10</strong>.11 Panels shall be mounted on suitable shock absorber pads.<br />
<strong>10</strong>.12 Contactors<br />
<strong>10</strong>.12.1 The rating of all the contactors shall be at least 50% higher than the<br />
respective motor full load current at the specified duty cycle, it is supposed<br />
to control. The power contactors shall be of AC4 duty and the minimum<br />
rating shall be 30 A.<br />
<strong>10</strong>.13 Circuit protection switch gear<br />
<strong>10</strong>.13.1 Protection switch gear shall consist of the following:<br />
� One triple pole MCCB fitted with over load release for protection<br />
against sustained overload and magnetic type instantaneous<br />
release for protection under short circuit conditions on all the<br />
three phases. The breaker shall have adequate rupturing<br />
capacity to withstand and clear fault current of the order of 50<br />
kA.<br />
� One triple pole contactor shall be provided after MCCB.<br />
� A suitable arrangement shall be made in the system to facilitate<br />
control testing with power circuit off. This shall be done by<br />
providing disconnecting links in the power circuit. Arrangement<br />
shall be made for quick removal of links. These links shall be<br />
covered with a hinge type cover.<br />
� To indicate when power and control sources are ON, pilot<br />
indication lamps shall be provided insider the driver's cabin.<br />
<strong>10</strong>.13.2 In addition to incoming circuit breaker, the following protective equipment<br />
shall be provided inside the driver's cabin:<br />
� Double pole MCBs for isolation and protection of lighting and<br />
socket outlet circuits.<br />
Page 44 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� One double pole MCB for isolation and protection of control<br />
circuit.<br />
<strong>10</strong>.13.3 For the protection of each drive motor and the control circuit for every<br />
motion of the car, Microprocessor based overload relays and miniature<br />
circuit breakers respectively shall be provided. The overload relays shall<br />
have adjustable settings. The over load relays shall have inverse time<br />
current characteristics and shall be self resetting type. NC contacts of all the<br />
overload relays shall be connected in series and incorporated in trip circuit<br />
of incoming breakers trip off. For protection of control circuit against<br />
sustained overload and short circuit conditions, miniature circuit<br />
breakers shall be provided for control circuit and shall be housed in<br />
respective control panel. Breakers shall be of reputed make.<br />
<strong>10</strong>.14 Auxiliary switch-gear<br />
<strong>10</strong>.14.1 All fuses shall be HRC link type.<br />
<strong>10</strong>.14.2 Emergency stop push buttons (stayput type).<br />
Safety switches of sustained contact type shall be provided at the<br />
entrance to the car so that under any emergency conditions, by<br />
operating the switch, the incoming circuit breaker is tripped thus<br />
cutting off power to all the motors. A pilot lamp incorporated in<br />
control circuit shall glow-up when any of these switches are operated.<br />
Further a mush room head type, "OFF" push button should be<br />
provided in the operator‟s cabin so that the main incoming breaker<br />
can be tripped under any emergency conditions by pressing the<br />
operating head. Safety switches shall also be provided near LT Motors<br />
for Charging car and Pusher car.<br />
<strong>10</strong>.15 All outgoing feeders of MCC shall be as follows:<br />
� Motor feeders shall be provided with MCCB (suitable for motor<br />
protection) contactor & microprocessor based overload relay<br />
and required number of selector switches, control switches,<br />
auxiliary contactors, ammeters etc.<br />
Page 45 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Power supply feeders shall be provided with MCCB, ammeter &<br />
voltmeter with selector switches.<br />
� Control supply shall be protected with the help of miniature<br />
circuit breakers.<br />
� Solenoid valves & DC magnets shall be provided with<br />
MCCBs/MCBs & contactors.<br />
11.0 Control modes<br />
All the drives shall be controlled from HMI at control desk located in<br />
the operator's cabin. Following types of sequence control shall be<br />
provided.<br />
11.1 Semi-automatic operation<br />
� Different process sequence shall be automatic. Progress of a<br />
sequence shall depend on limit switches or sensors<br />
corresponding to different positions.<br />
� A sequence shall mean all the operations being performed on a<br />
mechanism at one and the same time.<br />
� Each sequence shall be controlled from control desk by push<br />
button/key board.<br />
� A sequence shall start only when all the preconditions and<br />
permanent requirements including healthiness of drives and<br />
circuit are met.<br />
� It shall be possible to switchover to interlocked step-by-step<br />
mode during the operation of the sequence.<br />
11.2 Interlocked step-by-step operation<br />
� Each sub-sequence of the main sequence shall be controlled<br />
from control desk by separate push button/key board.<br />
� The progress of sub-sequence shall depend on the limit switch<br />
position or sensors.<br />
Page 46 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Each movement shall be started only after ensuring the<br />
necessary interlocks.<br />
� The progress of each sub-sequence shall be displayed on<br />
the control desk and monitor of HMI.<br />
� It shall be possible to switchover to semi-automatic mode<br />
only after the completion of a sequence.<br />
� Provision of by passing interlock shall be provided incase of<br />
emergency. This shall be achieved by changing mode selector<br />
switch.<br />
11.3 Other features<br />
11.3.1 All control shall be through PLC operated by master controller / push<br />
buttons / key board of HMI. Further local control stations shall be provided<br />
at suitable locations of drives for local control from PLC. All indicating lamps<br />
shall be of LED type only.<br />
11.4 Annunciation and indications<br />
11.4.1 An alarm shall be available in case of any fault. An acknowledge system<br />
and the fault display shall also be provided in HMI.<br />
11.4.2 The HMI system shall indicate the movement of jack corresponding to<br />
a sequence. The monitor of HMI system shall depict the required<br />
dynamic graphics.<br />
11.4.3 Whenever the travel motion of the machines is operated an audible<br />
alarm shall be operated through the operation of foot switch in<br />
operator's cabin.<br />
11.4.4 All hooters & sirens shall be of robust industrial design. The make shall be<br />
approved by purchaser.<br />
12.0 Limit switches & Junction boxes<br />
Page 47 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
12.1 <strong>Heavy</strong> duty, roller lever, self reset type or rotary type, limit switches shall be<br />
used.<br />
12.2 Enclosure class of all limit switches and junction boxes shall be IP-65.<br />
12.3 Limit switches shall be suitable for operation in corrosive atmosphere.<br />
12.4 Roller lever type limit switches shall be provided with 2NO+2NC<br />
contacts suitable for 240V, AC, <strong>10</strong>A or 230V, DC, 2A.<br />
12.5 Rotary type limit switches shall be provided with minimum 3<br />
spare cams and contact arrangement. Contact rating shall be similar<br />
to roller lever type limit switches.<br />
12.6 <strong>No</strong>n contact type Magnetic/proximity sensors for higher temperature shall<br />
be<br />
considered for various applications as per process requirement. The<br />
proximity sensor shall have suitable protective housing to withstand long<br />
term exposure to elevated temperatures up to +170 0 C .Two nos. of LED<br />
should be provided with sensor for power indication and output indication.<br />
12.7 Enclosure material for junction boxes, Local control station and field<br />
devices<br />
13.0 Brakes<br />
shall be minimum 1.6mm thick stainless steel.<br />
All brakes shall be of DC Electromagnetic, mill duty type only.<br />
Standalone brake panel shall be provided for each application.<br />
14.0 Resistance Boxes<br />
14.1 All resistances shall conform to IPSS:1-<strong>10</strong>-002-82. Punched steel grid<br />
resistances shall be provided. Resistance material shall be non-corrodible,<br />
free from brittleness. Typical material shall be AISI Grade 406 or Fechral (<br />
Cr 12 - 15 %, Al 3.5 - 4.5 %, rest Fe ).<br />
15.0 Light Fittings<br />
Page 48 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
15.1 Lighting shall be provided in operator's cabin, panel room, platforms,<br />
walkways, stair cases, control desk, working area and any other area<br />
required for operation of machine.<br />
15.2 All DPMCBs for lighting shall be provided in lighting distribution board<br />
in operator's cabin.<br />
15.3 Fluorescent lamps shall be used for operator's cabin and panel room.<br />
Sodium vapour lamps shall be used for all other areas.<br />
15.4 Suitable number of power socket outlets and hand lamp socket outlets<br />
shall be provided. A hand lamp with a plug and sufficient length of<br />
cable shall be provided with each machine.<br />
15.5 Lighting panel shall be separately provided. Bulk-head type fittings<br />
with lamps<br />
shall be provided in platform and on the under frame of the car and<br />
high pressure sodium vapour lamps for flood lights shall be provided<br />
on the either side of the oven machines to illuminate the track and<br />
other areas. The light switches shall be provided inside the operator's<br />
cabin. Screw cap type holders and lamps shall be used for the car<br />
lighting.<br />
15.6 Minimum 2 nos. of red revolving flash lights shall be provided on the car<br />
on both sides.<br />
15.7 The lighting transformer shall have 50% reserve capacity. The lighting<br />
distribution board with metal clad switches incorporating MCBs shall<br />
be provided in the operator's cabin for the following:<br />
� Car lighting<br />
� Fans<br />
� Alarm Bell.<br />
15.8 Socket Outlet<br />
Minimum of two numbers socket outlets for hand lamps shall be provided at<br />
operator's cabin, hydraulic cabin, MCC room and electronic panel room.<br />
Hand lamps shall be operated at 230V volts AC supply. Industrial type metal<br />
clad plug and sockets shall be provided.<br />
Page 49 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
15.9 Suitable lighting transformer shall be provided for machine lighting.<br />
Minimum rating of lighting transformer shall be 7.5KVA.<br />
16.0 Specification of Cables<br />
16.1 All cables for power, control, lighting etc. shall be carried out with 1.1 KV<br />
grade heat resistant silicone rubber insulated flexible cable of copper<br />
conductor suitable for 150˚C. All power cables shall be minimum 4 mm2<br />
(copper) and the control cables shall be minimum 1.5 mm2 (copper). The<br />
wiring inside the control panel shall be with PVC insulated stranded copper<br />
conductor. All flexible cables shall be multi-stranded copper. Single strand<br />
cables shall not be used any where inside the car. All cables exposed to<br />
direct heat radiation shall be of special insulation or shall run in formed steel<br />
channels provided with heat resistant material. Cables laid on open racks<br />
shall run in formed steel channels provided with heat resistant material.<br />
Cables laid on open racks shall be adequately clamped. Cables selection<br />
and routing on the car shall from a part of the car design.<br />
16.2 GI pipes and pipe fittings if used on car for running cables, shall be of<br />
standard design and shall be supplied with complete accessories. Each<br />
motor shall be wired through separate pipe. All cables remaining live in<br />
open position of isolation shall be installed separately.<br />
17.0 Identification of Circuits, Cables etc.<br />
18.0 Earthing<br />
Adequate labels of permanent nature shall be provided as support of<br />
switches, fuses, contactors and relays etc. to facilitate identification of circuit<br />
and replacement. All panels, controller etc. are to be properly marked for<br />
each motor. All power, control, lighting and other cables are to be tagged at<br />
both ends as per cable number indicated in drawing. All equipment<br />
terminals are also to be marked like-wise. Only metal ferrules shall be used.<br />
All the electrical equipments mounted on the car shall be connected to the<br />
car structure by means of earthing links. The car structure in turn shall be<br />
made electrically continuous by providing jumpers over rivets or bolts.<br />
Equipment laid by flexible cable shall be earthed by means of spare core<br />
provided in the flexible cable. Earthing shall conform to "Indian Electricity<br />
Rules". Earthing shall be achieved through machine mass, rail and 4th earth<br />
Page 50 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
conductor. Equipotential circuit shall be maintained. Copper wire of<br />
suitable cross section shall be used for earthing. Rubber matting shall be<br />
provided in operator's cabin. Earthing of all electronic equipment shall be as<br />
per the recommendation of supplier.<br />
19.0 Air conditioning<br />
19.1 All cabins, hydraulic rooms, electrical rooms and rooms housing electronic<br />
equipment shall be provided with air-conditioning equipments. Temperature<br />
inside Operator’s cabin shall be 24±2°C, however inside the electronic &<br />
hydraulic cabins it shall be 35°C. Air conditioning equipment supply is not in<br />
the scope of the tenderer.<br />
20.0 Variable Voltage Variable Frequency (AC Drives)<br />
20.1 All drives requiring speed control shall be provided with AC drives<br />
depending on the type of motor selected. AC drives shall be provided for<br />
travel drives of oven machines, Ram beam drive and leveller drive of<br />
Pusher car etc. Pulse encoder shall be provided and hooked up with drives.<br />
20.2 AC drives shall conform to the general specifications enclosed as Annexure.<br />
20.3 The following AC drives shall be provided for each machine:<br />
� Two numbers of AC drives for travel mechanism of pusher car shall<br />
be provided each capable of driving all the travel drives. <strong>No</strong>rmally<br />
both shall be operating, driving two sets of wheel drives. Pulse<br />
encoders shall be provided on wheels. Output of pulse encoders<br />
shall be hooked up to AC drives. Generally one drive with two<br />
motor shall be suitable for machine travel operation.<br />
� Separate AC drives shall be provided for pusher beam, leveller<br />
drive for pusher car.<br />
20.4 Pulse encoders shall be provided for Ram beam drive , travel drive &<br />
Leveller<br />
drive. Analog output of pusher ram VFD panel (4-20 mA) shall be<br />
connected to PLC to monitor the pusher beam drive output control.<br />
Make of pulse encoders shall be HUBNER.<br />
20.5 Enclosure class of AC drive panel shall be IP 42.<br />
Page 51 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
20.6 All AC drives shall be provided with suitably rated reactors.<br />
20.7 Minimum rating of AC drives & reactor shall be 180 % of the full load<br />
RMS current of the motor/group of motors. This shall be considered as<br />
the continuous current for the AC drives. Over load capacity indicated<br />
in the TS shall be based on the <strong>10</strong>0% continuous current indicated<br />
above.<br />
20.8 AC drives shall be microprocessor based having communication<br />
facility with PLCs for data transfer and speed reference set point.<br />
20.9 Software of drives shall be developed in such a way that after over<br />
voltage or under voltage when the drive trips, the AC drive shall be<br />
automatically resetted without any manual intervention after<br />
normalising of the voltage.<br />
20.<strong>10</strong> The AC drive system shall be independent of trolley line design<br />
system being provided by the purchaser and shall not effect the<br />
guaranteed performance of the drive system.<br />
20.11 AC drive shall be provided with 1:<strong>10</strong>0 speed range with dynamic<br />
braking.<br />
20.12 AC drive panels shall be mounted on anti vibration pads.<br />
21.0 Programmable Logic Controller (PLC)<br />
21.1 Each oven machine shall be provided with PLC and HMI. The system shall<br />
be complete with CPU, I/O racks, memory, key board and monitor. HMI<br />
shall depict graphics of various mechanism operation and also provide<br />
alarm annunciation system. Stand by system with redundant CPU, power<br />
supply and communication processor shall be installed in the PLC panel.<br />
One PLC (co-ordinating PLC) shall be provided by purchaser at battery<br />
control room for data communication with machine PLC.<br />
21.2 Communication between PLC and AC drive shall be possible for smooth<br />
operation of the machine. PLC shall have facility to communicate with<br />
Purchaser’s RTU through serial communication.<br />
Page 52 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
21.3 PLC shall perform the following task:<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Logic interlock functions, control & supervision of drives &<br />
solenoid valves.<br />
� Automatic sequential operation of various drives/devices<br />
like door handling mechanism, cleaner, pusher, charger, leveller<br />
etc.<br />
� Status indication & signalling.<br />
� Fault monitoring & annunciation.<br />
� Diagnostic features based on logical rules to recognise and<br />
display faults.<br />
� Communication with battery control room through digital radio<br />
link. (Hardware for digital radio link is in the tenderer‟s scope of<br />
supply.)<br />
� Report generation.<br />
21.4 One number Laptop with programming software and drive<br />
parameterisation software for each machine shall be provided<br />
(included in tools and tackles – schedule 2)<br />
21.5 <strong>Tender</strong>er shall note that at every stage of design, engineering & software<br />
development purchaser & consultant shall be fully associated.<br />
21.6 Software of the PLCs shall be developed in such a way that after voltage<br />
dip when all the I/Os are disabled, the same shall be automatically<br />
resetted without any manual intervention after revival of the voltage.<br />
21.7 Enclosure class of PLC panel shall be IP42.<br />
21.8 <strong>Tender</strong>er shall provide suitably rated UPS for PLCs and its<br />
peripherals.<br />
21.9 PLC shall conform to the general specifications enclosed as Annexure.<br />
21.<strong>10</strong> PLC panels shall be mounted on anti vibration pads.<br />
Page 53 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
21.11 20 % spare I/O of each type shall be provided as spare.<br />
21.12 Input interrogation voltage of PLC shall be 24 V DC. However, mixing of<br />
voltages shall not be allowed. Cabling and schemes shall be<br />
developed accordingly.<br />
21.13 All outputs shall be relay outputs. Interposing relays shall be auxiliary<br />
contactors suitable for 240V, AC, 50 Hz, 6A. DC rating of contacts shall be<br />
2A. <strong>10</strong> % spare interposing relays shall be provided.<br />
22.0 Particular Requirements<br />
22.1 Sizing of electrical premises shall be done as per the requirements indicated<br />
by Purchaser/consultant.<br />
22.2 The <strong>Tender</strong>er shall take all the necessary steps to get the installation<br />
approved by statutory Government Authorities like Electrical Inspector,<br />
Factory Inspector, Insurance Official etc. Necessary assistance in form of<br />
application and payment of Government fees shall be rendered by<br />
Purchaser in this regard. Modification suggested by statutory<br />
authorities in equipment or installation shall be carried out by<br />
<strong>Tender</strong>er at no extra cost to the Purchaser.<br />
22.3 <strong>Tender</strong>er shall supply current collectors to be provided on the oven<br />
machines as per the design of trolley line system being provided by the<br />
Purchaser. Details of the same shall be given to the <strong>Tender</strong>er during<br />
detailed engineering. <strong>No</strong> additional claim on this account shall be<br />
entertained by the purchaser.<br />
22.4 Performance guarantee for electrical equipment shall ensure that all<br />
the electrical equipment in a subsystem/system shall be capable of<br />
performing as per the specified and approved performance parameters<br />
of subsystem/system. However every electrical equipment shall also be<br />
capable of individual performance as per design as well as name plate<br />
details. This shall be demonstrated by the <strong>Tender</strong>er to the satisfaction<br />
of the purchaser/consultant.<br />
Page 54 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
22.5 Make of equipment shall be as per TS. Prior approval of<br />
purchaser/consultant shall be taken for make of equipment not indicated<br />
in TS.<br />
22.6 Enclosure class of the equipment shall be as per TS.<br />
22.7 Training of purchaser's personnel for drives(20 mandays) & PLC(20<br />
mandays) shall be arranged at the tenderer’s desigrated premises free of<br />
charge.<br />
22.8 AC drives panels, PLCs and its peripherals, MCC, LDB, control desk<br />
shall be mounted on anti vibration pads. Any other equipment<br />
sensitive to vibrations shall also be mounted as indicated above.<br />
23.0 Tests<br />
All routine and site tests shall be carried out strictly as per Specification and<br />
IS/IPSS/International Standards. Type test certificates shall be furnished for<br />
similar equipment. In case the type test certificates are not available, the<br />
same shall be conducted in Purchaser's presence, if the Purchaser desires,<br />
at no extra cost to the Purchaser.<br />
24. Drawings & Documents<br />
24.1 Information/data/drawings to be furnished for Electrics by the <strong>Tender</strong>er for<br />
approval<br />
24.1.1 Basic engineering<br />
� Single line diagrams of MCCs, PDBs, MLDBs, LDBs etc.<br />
� Power control and regulation schemes of AC drives.<br />
� Layout of electrical rooms and control rooms including<br />
ventilation air conditioning and handling facilities.<br />
� Layout of electrical equipment in electrical premises &<br />
operator's cabin.<br />
Page 55 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Voltage drop calculations for incoming power cables & outgoing<br />
power cable for motor.<br />
� Quality Assurance plan for various equipments.<br />
� List of motors, limit switches & other field equipments.<br />
� Maximum demand calculation for each MCC, PDB, MLDB etc.<br />
� Motor rating & AC drive rating selection & calculation.<br />
� List of drawings.<br />
24.1.2 Detailed engineering<br />
� Single line diagrams with ratings for MCCs, PDBs, LDBs etc.<br />
� Bill of materials with technical specification.<br />
� General arrangement drawings with complete dimensions and<br />
list of inscriptions for all equipment.<br />
� Power and control schemes for protective panel and other<br />
drives with bill of materials, technical specification, type/make,<br />
etc.<br />
� Power, control & regulation scheme for AC drives and UPS.<br />
� Automation configuration with control philosophy write up<br />
indicating control, interlocking and automation<br />
details.Functional description of drives & interlocks.<br />
� List and details of hardware with specifications.<br />
� G.A drawings of panels.<br />
� Power supply scheme.<br />
� List of I/Os, Block Logic Diagram and BOQ of PLC<br />
� Hard copy of software.<br />
Page 56 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
24.1.3 Illumination<br />
� Layout drawings.<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Layout of electrical equipment on the oven machine.<br />
� Equipment & cable layout in electrical premises and<br />
control/operator rooms with sectional views.<br />
� Layout of cable trays/structures, GI pipe layout and cable layout<br />
on the machine with sectional views.<br />
� Battery and UPS capacity calculations.<br />
� Motors and field devices<br />
- G.A drawings.<br />
- Technical data sheet.<br />
� Cable specification.<br />
� Single line diagrams with ratings of power components for<br />
LDBs.<br />
� Bill of materials with technical specificationof<br />
equipment/component /fittings.<br />
� Illumination layout containing the type and rating of all<br />
equipment with list of the luminarie for the machines.<br />
24.2 Information/data/drawings to be furnished by the <strong>Tender</strong>er for reference<br />
� All drawings and documents approved by MECON.<br />
� Terminal plan drawing for all equipment.<br />
� Cable schedule.<br />
� Interconnection diagrams.<br />
Page 57 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Layout of earthing system for the equipment.<br />
� Technical particulars, catalogues, literature etc.<br />
� Consolidated bill of materials for erection & installation<br />
items like GI pipes & fittings, cable trays, earthing materials etc.<br />
� Spare parts list & drawings.<br />
� Instructions for storage/erection, testing &<br />
commissioning.<br />
� Operation & maintenance manuals.<br />
� Final test certificates from suppliers and site tests.<br />
� As built drawings.<br />
24.3 Information/data/drawings to be furnished by the <strong>Tender</strong>er as final<br />
technical documentation.<br />
� All drawings, documentation and calculations indicated above.<br />
� List of drawings & drawing numbering system explanation.<br />
� Motors & field devices :<br />
� Speed-torque, current vs. time, thermal withstand<br />
characteristics for motors.<br />
� List of interfaces between the <strong>Tender</strong>er‟s equipment and<br />
Purchaser's equipment.<br />
� Internal wiring diagrams of equipment.<br />
� Illumination<br />
� Schedule of equipment with their location<br />
� Connected load and maximum demand for machines.<br />
Page 58 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
� Cable schedule.<br />
� All approved drawings.<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Internal layout and wiring diagrams of all panels.<br />
� All as built drawings.<br />
� Technical specification/ data sheets of equipment and light<br />
fittings.<br />
24.4 Drawings/documents for inspection of electrical equipment<br />
� Type test certificate for identical equipment.<br />
� Sub-supplier's or vendor's catalogues, technical literature.<br />
� Test reports and internal inspection report by <strong>Tender</strong>er.<br />
� Test certificates of components/equipment.<br />
� Technical specification & data sheets of equipment.<br />
� All "Approved" drawings.<br />
25.0 Make of Electrical Equipment<br />
1. Due consideration shall be given to inventory control, interchangeability,<br />
trouble shooting etc. in design and selection of<br />
equipment and controls.<br />
2. Efforts shall be made to offer maximum indigenous electrical<br />
equipment.<br />
3. Make of all indigenous electrical equipment shall be selected<br />
out of Purchaser's "Preferred Makes of Equipment and<br />
supplies".<br />
4. Make of all imported electrical equipment shall be selected in<br />
consultation with the Purchaser.<br />
Page 59 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
5. In case make for some of the equipment/components are not<br />
indicated in the Purchaser's "Preferred Makes of Equipment and<br />
supplies" then the same shall be finalised in consultation with<br />
Purchaser/Consultant.<br />
6. In case the electrical equipments are imported, these shall be<br />
tropicalised. It shall be ensured that the components used are<br />
also available from Indian sources. Sufficient spares shall be<br />
supplied for imported equipment/ components.<br />
7. <strong>Tender</strong>er shall ensure against the OBSOLESCENCE of<br />
equipment under their scope of supply for a minimum period<br />
of <strong>10</strong> years. The <strong>Tender</strong>er shall also guarantee that<br />
discontinuity of production of any item offered as part of the<br />
system shall not affect the maintainability of the system. The<br />
<strong>Tender</strong>er shall submit an undertaking to this effect along with<br />
the offer.<br />
Page 60 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
26.0 Preferred Makes<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
a) Make of motor : ABB/KIRLOSKAR/CGL/BB/ALSTOM/<br />
SIEMENS/ BALDOR<br />
b) Make of panels : RITTAL/BCH WITH APPROVED<br />
COMPONENTS<br />
c) Brake (DCEM) : BCH<br />
d) MCCB :<br />
GEPOWER/SCHNEIDER/ABB/SIE<br />
MENS.<br />
e) Contactor : ABB/SCHNEIDER/L&T/<br />
SIEMENS/GEPOWER/BCH.<br />
f) Thermal O/L Relay : SIEMENS/BCH/SCHNEIDER/L&T/C&S/<br />
GEPOWER /ABB<br />
g) EMPR : LG/SPECHER&SCHUH/BCH/SIEMENS<br />
h) Selector switch/ : SIEMENS/BCH/GEP/KAYCEE/ABB<br />
push button<br />
indicating lamp<br />
i) Limit switches : EPCC (KAKKU) / AG MECHANICAL<br />
j) MCB : MDS/STANDARD/SCHNIDER/<br />
ABB/SIEMENS<br />
k) Meters : MECO/IMP<br />
l) Lighting : PHILIPS/ CG/BAJAJ<br />
fixtures<br />
m) HRC Fuses : GEPC/SIEMENS/L&T<br />
n) Master controller : SCHNEIDER / SIEMENS /<br />
STROMKRAFT<br />
Page 61 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
o) PLC : ROCK<br />
WELL/ABB/SCHNEIDER/SIEMENS<br />
p) AC Drives : ABB / SIEMENS / L&T / ROCKWELL<br />
AUTOMATION/ SCHEIDER / HITACHI /<br />
NELCO<br />
q) Weighing system : SCHENCK/<br />
SARTORIOUS/TRANSWEIGH<br />
r) Encoders : HUBNER<br />
s) Proximity & Photo : ROCKWELL/SCHNEIDER/SIEMENS<br />
Electric sensor<br />
Page 62 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
27.0 List of drawings.<br />
Sl.<br />
<strong>No</strong>.<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
These drawings shall be furnished by the tenderer during detail<br />
engineering. Approval of drawings from DSP/ MECON shall be responsibility of<br />
tenderer.<br />
Description Project Drg. <strong>No</strong>. Category<br />
Electrical<br />
schematic &<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/000<strong>10</strong><br />
1<br />
2<br />
BOM<br />
GA of Control<br />
Panel DSP/HEC/14/02/01/COB-<br />
43B/DE/00011<br />
3<br />
4<br />
GA of Control<br />
Desk<br />
GA of PLC panel<br />
including HMI<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00012<br />
DSP/HEC/14/02/01/COB-<br />
5<br />
6<br />
7<br />
GA of Local<br />
Control<br />
Post<br />
GA of Terminal<br />
Box<br />
Motor GA<br />
Drawing & data<br />
sheet with curve<br />
43B/DE/00013<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00014<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00015<br />
DSP/HEC/14/02/01/COB-<br />
8<br />
9<br />
DC Brake GA<br />
Drawing<br />
Brake Rectifier<br />
Panel,<br />
GA, BOM &<br />
schematic<br />
43B/DE/00016<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00<strong>017</strong><br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00018<br />
<strong>10</strong> Cable Selection<br />
Chart<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00019<br />
11<br />
12<br />
Data Sheet of all DSP/HEC/14/02/01/COBcables<br />
43B/DE/00020<br />
Data Sheet of<br />
lighting fixtures DSP/HEC/14/02/01/COB-<br />
13<br />
43B/DE/00021<br />
UPS-GA,<br />
schematic &<br />
BOM with battery DSP/HEC/14/02/01/COB-<br />
43B/DE/00022<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Approval<br />
Page 63 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
sizing<br />
14 Data Sheet of<br />
Limit<br />
Switches<br />
(Proximity<br />
switches)<br />
15 Data Sheet of<br />
Laptop<br />
& Printer<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00023<br />
16 PLC I/O List<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00024<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00030<br />
17 Equipment<br />
Layout drgs DSP/HEC/14/02/01/COB-<br />
43B/DE/00031<br />
18<br />
19<br />
20<br />
21<br />
Cable layout<br />
drgs.<br />
External<br />
connection<br />
diagram<br />
Cable Schedule<br />
Control<br />
philosophy<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00032<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00033<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00034<br />
DSP/HEC/14/02/01/COB-<br />
43B/DE/00035<br />
1.0 SCHEDULES<br />
SCHEDULE-1<br />
1.1 LIST OF COMMISSIONING SPARES<br />
Approval<br />
Approval<br />
Reference<br />
Reference<br />
Reference<br />
Reference<br />
Reference<br />
Reference<br />
SL.NO. EQUIPMENT DESCRIPTION OF SPARE QUANTITY<br />
REQUIRED REMARK<br />
S<br />
Page 64 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
1<br />
2<br />
3.<br />
4.<br />
5.<br />
6.<br />
7.<br />
Contactor Coil<br />
Push Button<br />
Bulb for signal<br />
lamp<br />
Proximity switch<br />
AC incoming<br />
fuse for VVVF<br />
drive<br />
DC Link Fuse for<br />
VVVF drive<br />
Input/Output<br />
card<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
1 no for each<br />
rating<br />
2 nos.<br />
5 nos.<br />
2 nos.<br />
1 set for each<br />
rating<br />
1 set for each<br />
rating<br />
1 set for each<br />
rating<br />
Page 65 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-2<br />
1.2 SPECIAL TOOLS, TACKLES AND INSTRUMENTS<br />
SL.NO<br />
.<br />
NAME OF<br />
EQUIPMENT<br />
DESCRIPTION OF<br />
TOOLS/TACKLES/<br />
INSTRUMENTS.<br />
QUANTITY<br />
RECOMMENDE<br />
D<br />
1 2.5 kV Hand wound megger 1 no<br />
2 3 ½” Digital Multimeter 1 no<br />
3 Laptop with latest<br />
configuration and licenced<br />
software.<br />
1 no<br />
Page 66 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com<br />
REMARK<br />
S<br />
NOTE:-<br />
The above list is indicative. The <strong>Tender</strong>er shall provide the complete list<br />
during BE/DE stage.
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-3<br />
FORMAT FOR LT MOTOR DATA SHEET<br />
1. MAKE :<br />
2. DRIVEN EQUIPMENT TAG NO. :<br />
3.<br />
4.<br />
MOTOR TAG NO.<br />
QUANTITY<br />
:<br />
:<br />
5.<br />
6.<br />
VOLTAGE WITH VARIATION :<br />
NO. OF PHASES/CONNECTION/ :<br />
NO. OF TERMINALS<br />
7.<br />
8.<br />
FREQUENCY WITH VARIATION :<br />
FAULT LEVEL (MVA) & DURATION :<br />
9.<br />
<strong>10</strong>.<br />
MOTOR TYPE & DUTY<br />
KW RATING/POLE<br />
:<br />
:<br />
* AT 40 DEG. C. :<br />
* AT SPECIFIED AMBIENT TEMP :<br />
WITH DERATING.<br />
* BHP/BKW OF DRIVEN EQPT. :<br />
AT RATED LOAD<br />
11. FRAME SIZE/MOUNTING :<br />
12. INSULATION CLASS WITH TEMP. :<br />
RISE<br />
13. ENCLOSURE TYPE :<br />
14. FULL LOAD SPEED :<br />
15. FULL LOAD TORQUE (FLT) :<br />
16. STARTING TORQUE AS % OF FLT :<br />
17. PULLOUT TORQUE AS % OF FLT :<br />
18. FULL LOAD CURRENT (FLC) :<br />
19. STARTING CURRENT AS % OF :<br />
FLC<br />
20. STARTING TIME ON RATED LOAD<br />
* AT RATED VOLTAGE :<br />
* AT 75 % OF RATED VOLTAGE :<br />
21. LOCKED ROTOR WITHSTAND<br />
TIME<br />
* COLD :<br />
Page 67 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
* HOT :<br />
22. DIRECTION OF ROTATION :<br />
23. GD SQUARE OF MOTOR :<br />
24. GD SQUARE OF DRIVEN EQPT. :<br />
25. POWER FACTOR AT<br />
* 50 % LOAD :<br />
* 75 % LOAD :<br />
* <strong>10</strong>0 % LOAD :<br />
26. EFFICIENCY AT<br />
* 50 % LOAD :<br />
* 75 % LOAD :<br />
* <strong>10</strong>0 % LOAD :<br />
27. SPACE HEATER WATTS/VOLTS :<br />
28. TERMINAL BOX TYPE & :<br />
NO. OF TERMINALS<br />
29. FOR SLIP RING MOTORS<br />
* TYPE AND NO. OF RTDs<br />
FOR WINDINGS :<br />
* STATOR/ROTOR TIME :<br />
CONSTANT<br />
* ROTOR CURRENT AT FULL :<br />
LOAD<br />
* ROTOR VOLTAGE<br />
* ROTOR RESISTANCE<br />
:<br />
:<br />
30. NO. OF STARTS PER HOUR<br />
31. COOLING<br />
:<br />
:<br />
32. APPLICABLE STANDARD :<br />
33. APPLICABLE SPECIFICATION :<br />
34. LOCATION :<br />
35. HAZARDOUS AREA :<br />
CLASSIFICATION<br />
36. BEARING TYPE NO. :<br />
37. LUBRICATION TYPE :<br />
38. CABLE SIZE :<br />
39. WEIGHT IN KG. :<br />
40. G.A., DIMENSIONS & MOUNTING : YES/NO<br />
DETAIL DRAWINGS ENCLOSED<br />
41. DETAIL DRAWINGS FOR :<br />
TERMINAL YES/NO<br />
Page 68 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
BOX<br />
42. PERFORMANCE<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
CHARACTERISTIC CURVES<br />
VIZ. SPEED V/S CURRENT &<br />
SPEED<br />
V/S TORQUE ENCLOSED<br />
: YES/NO<br />
Page 69 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-4<br />
STANDARD SPECIFICATION FOR PROGRAMMABLE LOGIC<br />
CONTROLLER<br />
PROGRAMMABLE LOGIC CONTROLLERS:<br />
Monitoring and control of Oven Machines operation shall be<br />
Programmable Logic Controller (PLC) based.<br />
The equipment shall confirm to the standards developed by the Inter<br />
plant standards for steel industry IPSS:2-07-015-93 and relevant<br />
standard of Bureau of Indian standards (BIS) as applicable. Where<br />
IPSS / BIS do not exist, the components of all equipment shall be de-<br />
signed, manufactured, assembled, tested and installed in accordance<br />
with the latest standards of IEEE/NEMA/IEC or National standards<br />
Institution of the country where they are manufactured.<br />
1.1 General Features<br />
The PLC system shall be so designed that it is completely reliable and<br />
availability of the system shall be better than <strong>99</strong>%. The PLC system shall be<br />
most versatile, expandable, rugged, microprocessor based. The hardware<br />
shall be designed using advanced technology which shall bring a high level<br />
of capability, reliability and quality in the system. The PLC system shall<br />
comprise of processor I/O unit, multiplexers, A/D converters, communication<br />
electronics, CPU, Power Supply Modules, Memories for CPU; bus system,<br />
operators’ console with peripherals, interfacing equipment, marshalling /<br />
field termination racks, desks, panels etc. The input/output channels shall<br />
be provided with isolation.<br />
On-line replacement of any module shall be possible in such a way<br />
that the removal and addition of any module shall be possible without<br />
de-energizing the system. Further there shall not be any interruption in<br />
the system while replacing a faulty module except for the<br />
inputs/outputs which are being handled by the module.<br />
Page 70 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Operation of PLC shall be completely unaffected by a momentary<br />
power loss of the order of 20 milliseconds.<br />
The system shall have extensive set of self diagnostics hardware and<br />
software features with alarm facility for easy and fast maintenance.<br />
Diagnostics shall be required at local as well as in console level for<br />
identification of fault location.<br />
1.2 Environmental Classification<br />
The equipment shall be suitable for continuous duty under the<br />
following conditions:<br />
� Temperature while operating :<br />
lower limit : 0 degree C<br />
Upper limit : 55 degree C<br />
� Temperature while not operating (storage)<br />
lower limit : 20 degree C<br />
Upper limit : 70 degree C<br />
� Relative humidity<br />
- Daily average 80 to 90% (<strong>10</strong> h) and 65 to 90% ( 16 h)<br />
- Maximum 98%, not occurring simultaneously with maximum<br />
temperature.<br />
1.3 Basic design particulars<br />
Power Supply Units<br />
� Plug in Modules as required for CPU / IO cards mounted on<br />
respective Racks<br />
� Power supply for CPU Rack<br />
� 24V Power supply Units for I/O interrogation and field instruments<br />
PLC System<br />
� Communication modules for Communication between PLCs, AC<br />
drives, DCS, Level2 system radio communication data exchange<br />
system and with field devices.<br />
Page 71 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� CPU Capable of handling PID functions and weighing and<br />
batching functions.<br />
Memory<br />
� EPROM / EEPROM<br />
� RAM with battery backup<br />
Input units<br />
- Discrete inputs<br />
- BCD inputs<br />
- Analog inputs ( configurable for mV, mA, T/C of various types,<br />
RTD)<br />
- Pulse inputs ( Incremental encoder / digital tacho)<br />
- Absolute encoder inputs ( gray code)<br />
Output units:<br />
- Discrete outputs for driving interposing output relays<br />
- BCD outputs<br />
- Analog outputs ( 4 – 20mA / 0 - 20mA)<br />
Timers From <strong>10</strong> milliseconds to few hours, Accuracy (+/-)0.1%<br />
Counters Count from 0000 to <strong>99</strong><strong>99</strong> Up / Down<br />
1.4 Power Supply System<br />
� 415 V, 3 phase, 4 wire, 50 Hz solidly earthed neutral system.<br />
� Symmetrical fault level 50 kA, rms<br />
� Voltage variation : + <strong>10</strong>% / -15%<br />
� Frequency variation: +4% / -6%<br />
1.4.1 Built-in power supply units<br />
� Suitable for the power supply system as specified above.<br />
� Insulation level 2.5 kV for 1 minute.<br />
� Protective features:<br />
� Surge voltage protection<br />
� Fuse protection in the input and output circuits<br />
� Electronic over current protection<br />
Page 72 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Thermostat protection against over temperature<br />
� Independent units for the following :-<br />
� For CPU and associated electronic units<br />
� For sensing the status of input devices<br />
� For powering field transmitters through respective input cards<br />
� For driving outputs<br />
1.5 Central Processing Unit (CPU)<br />
� Modular and plug-in type<br />
� Central processor 32 or 16 bit microprocessor based<br />
� Single / multiple processors in coordination<br />
� Shall be capable of handling 30 % additional (future) I/Os over and<br />
above 20 % spares (installed) I/Os indicated in basic configuration<br />
diagram.<br />
� PLC shall be capable of handling weighing and batching loops<br />
� Maximum CPU loading shall be limited to 60 % for the intended<br />
applications<br />
� Scan time between 2 m sec to 5 m sec per one K instructions or<br />
better<br />
� Provision to latch desired outputs<br />
1.6 Memory<br />
1.6.1 Program memory: Formatted data shall be stored in EPROM / EEPROM<br />
or battery operated backed RAM. These memories shall be backed up<br />
by floppy disks.<br />
The general technical features of the memories shall be as<br />
follows:<br />
� Modular and plug-in type<br />
� Word length 8 bit/16 bit<br />
� Expandable in blocks<br />
� Minimum size 16K<br />
� Data and application program memory sized to have at least<br />
40% free memory space.<br />
� EEPROM / RAM with battery back-up<br />
� Back-up battery shall be as follows:<br />
� Rechargeable Ni-Cd batteries with necessary charging circuit / Lithium<br />
batteries of suitable capacity.<br />
Page 73 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Able to sustain memories for a minimum of 14 days with no power<br />
applied to the controller.<br />
1.7 Process Input / Output (I/O) Units<br />
1.7.1 Input Units<br />
This unit shall provide the main interface between field devices, PLC and<br />
HMI system. This shall provide necessary slots / racks with complete wiring<br />
for installing the input / output cards for analog and logical I/Os and the<br />
controller connection. The field cables shall not be brought directly to the I/O<br />
cards. The same shall be routed through the field termination / marshalling<br />
racks. All wiring inside racks / cabinets / back of the panels shall be housed<br />
in covered nonflammable plastic raceways arranged to permit easy<br />
accessibility to various equipment for work and maintenance. The signal<br />
validity check, ambient temperature compensation for mV inputs from<br />
thermocouples and broken sensor check shall be necessarily a built-in<br />
feature for analog input cards. 20% I/O slots (installed) and 20% I/O cards<br />
(at least one card of each type minimum) shall be kept spare.<br />
Separate power supply unit shall be provided for individual I/O rack and<br />
processor. Suitable battery back-up shall be provided for volatile memory<br />
protection.<br />
Each I/O shall be electrically isolated from external control circuit by suitable<br />
means. The minimum isolation level between I/O and logic circuit shall be<br />
1500 V dc.<br />
Each I/O shall be protected against the reversal of polarity of the power<br />
supply voltage to I/O.<br />
� Modular and plug-in type<br />
� Insulation level of 1.5 kV<br />
� Individual fuse for each unit shall be provided for protection against<br />
cable fault/earth fault.<br />
� Input interrogation voltage 24V DC (built-in) preferable.<br />
� LED status indication<br />
Inputs shall be suitable for accepting the following:<br />
� Discrete input units shall have the following:<br />
Page 74 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
- Time delay of about <strong>10</strong> millisecond to filter out noise and contact<br />
bounce.<br />
- Optocoupler to galvanically isolate each input device from the<br />
decision making logic of the controller<br />
� BCD input units suitable for four digit input<br />
� Pulse inputs ( Incremental encoder / digital tacho )<br />
� Absolute / incremental encoder inputs<br />
� Analogue input units shall be as follows:<br />
- With necessary A/D converter having 12 /14 bit resolution.<br />
- Suitable for 4 - 20mA / 0 - <strong>10</strong>V DC inputs ( with 24 V dc power supply<br />
facility in each card for the field transmitters, excepting one input card<br />
where this loop power supply facility is not required)<br />
- Suitable for PT<strong>10</strong>0 2- wire / 3 wire<br />
- With insulation level of 1.5 kV<br />
- Each input shall be galvanically isolated.<br />
1.7.2 Output Units<br />
� Modular and plug-in type<br />
� Discrete output units shall be as follows:<br />
- Isolated output with two separate terminals for each output.<br />
- All outputs shall be through separate relays rated for 24V DC, 2A, 50<br />
Hz (15A for 50 milli-second to take care of the in rush current of the<br />
contactor coil).<br />
- Galvanically isolated by opto coupler<br />
- With LED status indication<br />
- With insulation level of 1.5 KV<br />
- Output relays shall have surge suppressor across them. Card mounted<br />
relays are not acceptable.<br />
� BCD output units shall be as follows:<br />
- Suitable for four digit output<br />
- Rated to drive seven segment displays used<br />
- With insulation level of 1.5 kV<br />
� Analog outputs shall be as follows:<br />
Page 75 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
- Suitable for 4 - 20mA / 0 - <strong>10</strong>V outputs<br />
- With necessary D/A converters having 12/14 bit resolution<br />
- With insulation level of 1.5 kV<br />
- Each output shall be galvanically isolated.<br />
1.8 Programming Unit<br />
� Laptop shall be provided for programming.<br />
� With facility for loading the programme developed on EPROM and CD.<br />
� Capable of ON line & OFF line programme development with<br />
necessary hardware interface and software.<br />
� Facility for simulation test and programme debugging with necessary<br />
software.<br />
1.9 Self diagnostic features<br />
� Parity errors, cycle errors and under voltage<br />
� Failure in central processor unit, memory and power supply.<br />
� Communication failures – all types<br />
� Indication of type of failure<br />
� Automatic turning OFF of all outputs or optionally holding of<br />
all outputs in their last state on failure detection.<br />
1.<strong>10</strong> Terminations<br />
� All inputs and output wired upto easily accessible terminal blocks<br />
rated for 660V.<br />
� Screened cables for milli-Volt signals from I/O rack to terminal block.<br />
� Compensating cables for thermocouple signals from I/O rack to<br />
terminal block (with copper terminals).<br />
� Suitable for terminating upto 2.5sq. mm. copper conductor industrial<br />
control cables.<br />
� Fuse terminals for all output signals.<br />
1.11 Additional Features<br />
� Fully programmed<br />
� Connection of field devices with input units through ordinary multi<br />
core copper control cables.<br />
Page 76 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Communication with computer in distributed hierarchical control<br />
system and operator consoles/display units.<br />
� Printers to get hard copy of the programme developed / process<br />
information / reports.<br />
1.12 Earthing<br />
Separate earthing bus for power / panel earthing and electronic<br />
earthing shall be provided.<br />
Electronic earthing bus shall be suitably insulated. Earthing<br />
requirements / earthing schemes for the equipment supplied shall be<br />
clearly indicated in appropriate drawings.<br />
1.13 Special Features<br />
i) The PLC system shall be immune to the following:<br />
- Radio frequency interference<br />
- Electromagnetic interference<br />
- Power system spikes<br />
The methods and standards followed for these features shall be<br />
furnished along with the tender.<br />
1.14 Other features<br />
� Test sockets on input modules for input simulation<br />
� Suitability for On-line replacement of I/O cards without switching of<br />
power supply<br />
� Switch to disable all outputs of the controller during startup/debugging<br />
� Fuse failure indication for outputs<br />
� Provision to connect VDU/Printer for alarm annunciation to accept set<br />
points, data display and logging<br />
� mA Ammeters to be mounted on the front panel for leakage current<br />
measurement during earth fault of input and output power bus .<br />
2.0 Constructional Features<br />
Page 77 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Unitised construction<br />
� Sheet steel clad<br />
� Floor mounted, free standing and indoor type<br />
� cable entry provision from bottom<br />
� Panel illumination to be provided with door interlock limit<br />
switch<br />
� Dust and vermin proof<br />
� suitable anti-vibration pads to withstand vibrations<br />
� All modules plug-in type<br />
Enclosure<br />
� Conforming to IP-42 class, for equipment located in airconditioned<br />
room.<br />
Painting<br />
The sheet metal parts shall be subjected to the following pre-treatment<br />
before final painting.<br />
� Degreasing<br />
� Pickling for complete rust removed<br />
� Phosphating<br />
� Corrosion resistant primer painting.<br />
Final coats of spray paints shall be given as per shade <strong>No</strong>.631 as per IS<br />
5, 1<strong>99</strong>5.<br />
3.0 Mounted Spares<br />
� Min of 20 % of I/O modules used with at least one module of each type<br />
for input and output shall be offered as spare for each programmable<br />
controller and the same shall be mounted and wired to the terminal<br />
block in the cubicle suitably.<br />
� Provision shall be provided with empty slots for future expansion for<br />
20% I/O modules.<br />
� Minimum 50 % spare memory capacity shall be built in the system<br />
after loading of application and system software.<br />
Page 78 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
4.0 Miscellaneous requirements for programmable controllers<br />
� Programmable controllers shall be suitable for normal industrial<br />
environment though they shall be housed in air-conditioned rooms.<br />
� Table top mounted printer shall be provided.<br />
� Separate furniture (Printer tables) shall be provided for the above<br />
printers.<br />
� Cassettes/CDs loaded with frozen program of each PLC shall also be<br />
supplied. These shall be properly identified and housed on cubicle for<br />
ready use.<br />
5.0 SOFTWARE:<br />
a) PLC Programming software – 1 no for each machine.<br />
b) HMI software – 1 no for each machine.<br />
HUMAN MACHINE INTERFACE<br />
The Human Machine Interface shall be through the touch screen. PLC<br />
will be communicating directly with HMI. All the data updating taking<br />
place in the PLC will be updated in HMI. High resolution colour touch<br />
screen monitor will be provided. Sequence of various mechanism<br />
operation will be controlled and displayed on screen including alarms.<br />
i) Printer<br />
The workstation shall be connected with laser printer.<br />
The mounting of the printer shall be on separate tables. The tables<br />
shall be supplied along with printers. The noise of printers at 1 meter<br />
distance shall be less than 65 dB.<br />
Tests<br />
The following tests shall be carried out on PLCs in the presence of purchaser / representatives:<br />
� Visual inspection test.<br />
� Over all dimensions, component, mounting, and wiring.<br />
Page 79 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Quantity checks for no. of I/O modules, peripherals etc.<br />
� Insulation test.<br />
� Temperature test (ageing test).<br />
� Mechanical vibration test.<br />
� <strong>No</strong>ise immunity test.<br />
� Bill of materials.<br />
� Functional tests :<br />
� Of CPU, programming unit, power supply, I/Os.<br />
� Test of all fault diagnostic features of PLC.<br />
� Checking of operation of each I/O port, timers.<br />
� Running of a test and actual programme, transfer of data to and<br />
from VDU key board unit and driving of printer.<br />
� Integrated functional test with all equipment and peripherals<br />
connected as per configuration diagram.<br />
Cables<br />
All necessary special cables with connectors required for<br />
interconnection of the different units of the above system shall be<br />
included in the scope of work.<br />
Page 80 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-5<br />
STANDARD SPECIFICATION FOR VARIABLE VOLTAGE VARIABLE<br />
FREQUENCY CONVERTERS (AC DRIVES)<br />
VARIABLE VOLTAGE VARIABLE FREQUENCY DRIVE<br />
1.0 BASIC DESIGN PARTICULARS<br />
All VVVF Drives shall have Digital Control Technology with Vector control.<br />
VVVF shall communicate with PLC.<br />
� Input Voltage : 415V +<strong>10</strong>% to –15% , 3 phase neutral<br />
earthed system.<br />
� Input Frequency : 50 Hz +4%, -6%<br />
� Output Voltage : 3-Phase, 415 V max. at nominal input .<br />
� Output Frequency : Can be selected to suit the motor<br />
operating frequency range for constant torque<br />
and constant power<br />
1-50 Hz (Constant torque)<br />
50-<strong>10</strong>0 Hz (Constant power)<br />
� Rated output current: Minimum 180% of full load RMS Current of<br />
motor/ group of motors for intended<br />
application<br />
1.1 Type of connections<br />
� Three phase frequency converters with rectification and inversion i.e.<br />
variable voltage and variable frequency output with current source /<br />
voltage source (PWM) inverters.<br />
� Line reactors /Isolation transformers for harmonic and noise<br />
suppression.<br />
1.2 Overload capacity<br />
� 150% of the rated inverter current for 1 minute following <strong>10</strong>0% load &<br />
to meet the drive overload capacity.<br />
1.3 Other Features<br />
Page 81 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Efficiency more than 95% at full load.<br />
� Suitable to withstand vibrations more than 0.5 g.<br />
� Ramp rate : Linear acceleration and deceleration adjustable<br />
independently.<br />
� Set point for torque adjustable independently.<br />
2.0 Power components:<br />
The main power components of the VVVF equipment shall have the<br />
following equipment on incoming AC side:<br />
� Matching reactor.<br />
� AC line surge suppression network.<br />
� ACB/MCCB<br />
� Input contactors<br />
� Line contactors<br />
2.1 Load side<br />
� Filter network<br />
� Output side reactor.<br />
� Isolator and over-load relay for each motor.<br />
3.0 Principle Controls – Minimum Requirements :<br />
� IGBT Power Technology<br />
� PWM with Programmable career frequency<br />
� Reference speeds setter (SW selectable)<br />
� Torque / Power mode<br />
� Slip compensation control<br />
� V/f control<br />
� Speed feed back, as required<br />
� Current feed back<br />
� Dynamic current control<br />
� Programmable proactive current limit<br />
� Independently programmable acceleration & deceleration times (<br />
Minimum 2 each)<br />
� Independently programmable Torque set points.<br />
� Zero speed / over speed monitor as applicable<br />
� Dynamic braking Chopper unit with resistance.<br />
Page 82 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Facility to accept speed reference and other control from<br />
programmable controller through communication network.<br />
4.0 Protective features<br />
� AC line surge suppression network<br />
� Under voltage in supply network<br />
� Phase sequence protection and monitoring<br />
� Under voltage in DC link<br />
� Over voltage in DC link<br />
� Over speed monitor<br />
� Overload<br />
� Earth fault<br />
� Instantaneous over current<br />
� Transformer faults<br />
� Cooling fan failure<br />
� Stall monitor for motor<br />
� AC mains failure<br />
5.0 INPUTS<br />
ANALOG INPUTS<br />
(a) Frequency Setting 0-<strong>10</strong> V DC ; 4 - 20 mA<br />
(b) Position feedback<br />
DIGITAL INPUTS<br />
(a) Reset : For fault reset & instantaneous<br />
output cutoff ( <strong>No</strong>rmally Closed )<br />
(b) Forward / Reverse run : Selectable individually.<br />
(c) Multistage speed / Torque : Four kinds of speed settings<br />
including main speed setting shall<br />
be selectable.<br />
(d) Jogging Operation : Selectable from 0 to 9.9 Hz Mode<br />
selection by digital input<br />
(e) Stop : Coast to zero command<br />
(f) Pulse inputs : From digital tacho / BCD from<br />
position encoder / Encoders<br />
(Incremental & absolute)<br />
6.0 OUTPUTS :-<br />
Page 83 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
ANALOG OUTPUT<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
(a) Frequency monitor : 0-<strong>10</strong> V DC signal proportional to<br />
output frequency for driving analog<br />
meter.<br />
DIGITAL OUTPUTS<br />
(a) Fault alarm relay : Relay with change over contact<br />
available for annunciating inverter<br />
fault.<br />
(b) Drive running signal : output (24V DC) for driving<br />
externally connected relays.<br />
(c) Frequency arrival signal : Output (24V DC) for driving<br />
externally connected relays.<br />
(d) Annunciator outputs : Contact outputs for annunciating<br />
various inverter panel faults in<br />
lighted windows.<br />
7.0 Constructional Features<br />
� Floor mounted, free standing<br />
� Dust and vermin proof<br />
� Sheet steel clad<br />
- Minimum 2.5 mm thick for panels.<br />
- Minimum 2.0 mm thick for doors and side covers<br />
� ISMC 75 base channel at the bottom.<br />
� Suitable to withstand vibrations to be encountered in steel plant<br />
applications.<br />
� Provided with anti vibration Pads<br />
� Cubicles with illumination lamps, door switches, space heaters and<br />
adequate sockets for connecting instrument, soldering iron etc.<br />
� All control blocks plug-in-type with necessary test sockets.<br />
� Units shall be self contained and serviceable.<br />
8.0 Enclosure and Ventilation<br />
� Enclosure conforming to IP-42.<br />
� Units shall be provided with cooling fans and louvers at the bottom<br />
sides. All louvres shall have fine mesh behind them.<br />
Page 84 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
9.0 Test<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Ventilation through individual ventilation ducts, from bottom not<br />
acceptable.<br />
� Ambient temperature shall be 55ºC .<br />
a) The following tests shall be carried out at works in the presence of<br />
purchaser's representative:<br />
� Visual inspection<br />
� Insulation test<br />
� High voltage test<br />
� Functional test<br />
� Light load test<br />
� Full load and temperature rise test<br />
b) The following tests shall be performed at site :<br />
� Visual inspection<br />
� Insulation test<br />
� Functional test<br />
� Light load test<br />
Page 85 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-6<br />
STANDARD SPECIFICATION FOR L T INVERTER DUTY MOTOR<br />
Sl.<strong>No</strong>. Parameters Description<br />
1.0 Type - AC Squirrel cage induction motor.<br />
- Inverter Duty<br />
2.0 Standard - IPSS 1-03-001/ IS 325<br />
- NEMA Standard MG1-1<strong>99</strong>3 Part 31, or<br />
the latest revision in so far as it is<br />
applicable.<br />
3.0 Constructional Features<br />
A Frame size & rating - As per IS 325<br />
- <strong>10</strong>:1 constant torque speed range<br />
motors may exceed frame standard<br />
by one frame rating.<br />
B Motor body Grey iron casting as per IS:2<strong>10</strong>-1978<br />
C Motor Feet Integrally cast with the stator<br />
D Body Design - Prevent breakage or other failures<br />
due to vibrations normally<br />
encountered in heavy industries .<br />
- Motors shall be of weather proof<br />
construction.<br />
- Designed to operate in the humid air<br />
E Protection for Motor &<br />
Bearing<br />
stream .<br />
IP - 55<br />
(with canopy for motor)<br />
F Motor Shaft Shall be provided with an external<br />
recessed slinger at the drive end of the<br />
motor to provide additional (minimum<br />
Page 86 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
IP-54) protection from moisture and<br />
foreign material.<br />
G Shaft ends & Extension - Cylindrical as per requirement<br />
- Shaft shall be extended for encoder /<br />
tacho. mounting, accordingly<br />
suitable hole shall be drilled and<br />
tapped .<br />
H Internal Encoder Motors with speed variation of <strong>10</strong>00:1 at<br />
constant torque shall have internal built<br />
in encoder for speed feedback.<br />
I Bearing - Roller type bearing upto 5 kW .<br />
- Ball Bearing at NDE end for above 5<br />
kW.<br />
- All motors shall have fully regreasable,<br />
anti-friction bearings.<br />
- All motors shall have cast iron inner<br />
bearing caps.<br />
- Bearings shall be oversized .<br />
- All motors shall have a charged<br />
lubrication system to inhibit moisture<br />
condensation.<br />
- Standard motors shall have extended<br />
grease fittings on the opposite driveend<br />
to facilitate re-lubrication. Grease<br />
ports shall be located on the<br />
periphery of the motor end shield.<br />
- Motor shall be fitted with a shaft<br />
slinger or V ring seal on the drive end<br />
for a minimum of IP-54 protection (to<br />
help protection of bearing from<br />
ingress of dust, dirt or fluids)<br />
Page 87 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
J Hazardous Area safety<br />
design<br />
4.0 Terminal box<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
As per process requirement<br />
A Location RHS viewed from DE / On top<br />
B Suitability - 4 Core Aluminium Cable<br />
- The terminal box shall be oversize as<br />
compared to NEMA requirements.<br />
C Rotation 4 X 90 deg.<br />
D Earthing stud Inside Terminal Block<br />
E Miscellaneous - Shall be gasketed between the<br />
terminal box halves.<br />
- The conduit box shall be field<br />
convertible to cast iron.<br />
- External screws and bolts shall be<br />
grade five, hex heads and be plated to<br />
resist corrosion.<br />
5.0 Cooling - TEFC, Effective bi-directional<br />
- Motor with <strong>10</strong>00:1 speed range and<br />
constant torque shall have external<br />
fan.<br />
- External fan motor shall be 3 phase ,<br />
440 V AC<br />
- Thermistors shall be provided in the<br />
windings.<br />
6.0 Quality of operation<br />
A Vibration intensity - Shall be limited as per IS 12075-1986.<br />
- Shall not exceed .08 inches / second<br />
velocity.<br />
B <strong>No</strong>ise level As per IS: 12065-1987<br />
Page 88 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
7.0 Electrical design<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
A Power Supply 415 V +<strong>10</strong>% / -15%, 3-phase, 50 Hz + 4%/-<br />
6% ,<br />
4-wire AC, 50 kA for 1 second, solidly<br />
earthed.<br />
B Starting Variable Frequency Drive<br />
C Service factor - 1.0 for VFD power .<br />
- 1.15 for sine wave power .<br />
D Peak transient voltage 1500 V<br />
E Minimum rise time 0.1 microsecond<br />
F Starting Torque 200 % rated torque for 1 minute below<br />
base speed<br />
G Constant horsepower<br />
operation<br />
1.5 times base speed .<br />
H Duty Application dependent<br />
I Max speed<br />
permissible<br />
150 % rated for 2 minutes<br />
J Derating for VFD As per above mentioned standard<br />
K Insulation - Minimum Class H<br />
- Insulation materials with additional<br />
phase insulating material, extra endturn<br />
bracing and Class H spike<br />
resistant wire.<br />
L Load Type Constant Torque / Variable Torque<br />
(As per application)<br />
M Space Heater - Out door motors above 45 kW<br />
- Indoor Motor above 1<strong>10</strong> kW<br />
Page 89 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
N Temperature Rise Limited to Class F<br />
O <strong>No</strong>. of Poles 6 / 8<br />
8.0 Operating Characteristics<br />
A Operation with variation<br />
in the voltage or the<br />
frequency<br />
Motors shall operate successfully<br />
under running conditions at rated load<br />
with variation in the voltage or the<br />
frequency not exceeding the following<br />
conditions:<br />
+/-<strong>10</strong>% rated voltage at rated constant<br />
V/f ratio except for specific torque<br />
boost situations.<br />
Motors shall operate successfully<br />
under running conditions at rated load<br />
and V/f ratio when the voltage<br />
unbalance at the motor terminals does<br />
not exceed one percent.<br />
B Torques Motors shall meet or exceed the<br />
minimum locked rotor (starting) and<br />
breakdown torques specified in NEMA<br />
Standard MG1 Part 12 for Design B for<br />
the rating specified when on sine wave<br />
power.<br />
C Operating speed range - Zero to base speed in case of VT.<br />
- <strong>10</strong>00: 1 for CT (with blower cooling)<br />
D Locked rotor (starting)<br />
currents<br />
- <strong>10</strong>:1 , 6:1 , 4:1 for CT .<br />
Shall not exceed NEMA Design B values<br />
for the specified rating on 5:1 constant<br />
torque or less and variable torque<br />
motors. NEMA Design A values are<br />
allowed for 6:1 constant torque or<br />
Page 90 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
higher value constant torque rated<br />
motors.<br />
Motors shall be capable of a 20 second<br />
stall at six times full load current<br />
without injurious heating to motor<br />
components.<br />
E Efficiency - Shall have a nameplate minimum and<br />
nominal full load efficiency for motors<br />
when tested in accordance with<br />
NEMA standard MG1 Part 12, IEEE<br />
Test Procedure 112 Method B, using<br />
accuracy improvement by segregated<br />
loss determination including stray<br />
load loss measurements.<br />
9.0 Motor location Outdoor / indoor installation.<br />
<strong>10</strong>.0 Painting For indoor motors:<br />
- Surface preparation shall be made by<br />
sand blasting or shot blasting to near<br />
white metal<br />
- After surface preparation two coats of<br />
air drying epoxy based red oxide zinc<br />
phosphate primer shall be applied.<br />
Dry film thickness of each coat shall<br />
be 30 microns minimum.<br />
- After primer has dried two coats of air<br />
drying epoxy based enamel paint<br />
shall be applied. Dry film thickness of<br />
each coat shall be 40 microns<br />
minimum.<br />
- The total thickness of painting shall<br />
thus be 140 microns.<br />
Page 91 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
For outdoor motors:<br />
- Surface preparation shall be made by<br />
sand blasting or shot blasting to near<br />
white metal.<br />
- After surface preparation two coats of<br />
air drying epoxy based red oxide zinc<br />
phosphate primer shall be applied.<br />
Dry film thickness of each coat shall<br />
be 30 microns minimum.<br />
- One coat of air drying epoxy resin<br />
based intermediate paint shall be<br />
applied after primer. Dry film<br />
thickness of intermediate paint shall<br />
be <strong>10</strong>0 microns minimum.<br />
- After intermediate paint has dried two<br />
coats of air drying epoxy based<br />
enamel paint shall be applied. Dry<br />
film thickness of each coat shall be 40<br />
microns minimum.<br />
The total thickness of painting shall<br />
thus be 240 microns.<br />
11.0 Nameplate - Shall be of stainless steel and<br />
stamped per NEMA Standard MG1<br />
Part <strong>10</strong> and Part 31.<br />
- Nameplate information shall include<br />
as a minimum, the nominal efficiency<br />
value per NEMA Standard MG1 Part<br />
12, the bearing identification<br />
numbers, power factor, Torque values<br />
with speed range and amps for that<br />
torque value.<br />
- Nameplate also shall include Full<br />
Page 92 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Load Slip RPM, Magnetizing amps<br />
and (if included) encoder PPR and<br />
Voltage rating.<br />
Page 93 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
1.1 GENERAL<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
SCHEDULE-7<br />
STANDARD SPECIFICATION FOR UNINTERRUPTED POWER SUPPLY<br />
SYSTEM<br />
Technical parameters for design<br />
Power supply system : 440 V, 50 Hz, 3 phase, 4 wire<br />
System neutral : Earthed<br />
Insulation level : 2.5 kV<br />
System short circuit level : 50 kA for 1 second<br />
Output Voltage : 240V, AC, 50 Hz.<br />
UPS system shall be of adequate capacity to cater for power<br />
requirement of the entire automation system.<br />
This shall include PLC panels, I/O Panels, Workstations, etc., located in<br />
operator’s room and various electrical rooms.<br />
This shall also include power supply for I/O interrogation, transmitter<br />
power supply (24V DC) for field instruments connected to PLC<br />
wherever applicable, etc.<br />
1.2 Basic particulars for design:<br />
Basic details:<br />
� Features and performance in line with IEEE 446 and configuration as<br />
per fig 45 of IEEE 446.<br />
� 125% of the rated output for 15 minutes<br />
� Suitable for connecting to a 415 V, 3 phase, 50 Hz, 4 wire, grounded<br />
neutral system with a symmetrical fault level of 50 kA rms.<br />
� Three / Single phase voltage and frequency controlled output, as<br />
required.<br />
� With isolating transformer, rectifier, inverter unit and necessary DC<br />
batteries.<br />
� Dual redundant system with automatic static bypass and common DC<br />
battery.<br />
Page 94 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� DC battery shall be sealed maintenance free Lead acid with plate cells<br />
type.<br />
� Battery shall be suitable to maintain the power supply for at least 30<br />
minutes in the event of mains failure.<br />
� 25% overload condition to be considered for battery sizing.<br />
� Electronic bypass switch to connect the system to the mains supply<br />
without interruption to the load in the event of inverter failure.<br />
� Necessary distribution board in different areas for distribution of<br />
power from UPS output to individual consumers.<br />
Permissible variations:<br />
Mains power supply system<br />
� Voltage : ± <strong>10</strong> %<br />
� Frequency : ± 5%<br />
Output of the uninterrupted power supply system while<br />
delivering a load of its rated capacity<br />
� Voltage : (+/-) 3 %<br />
� Frequency : (+/-) 0.1 %<br />
� Harmonic distortion: Max. 2 %<br />
Transformer<br />
� Rating suitable for the application<br />
� Dry type , with class H insulation<br />
� + 2.5% with tappings on primary<br />
Rectifier<br />
� Dual rectifier with each unit rated for supplying both inverter load<br />
and battery charger load.<br />
� Rectifier unit shall consist of minimum six pulse bridge<br />
connection<br />
� With necessary smoothing reactor and filters<br />
� Automatic boost and float charging control<br />
Protective features:<br />
� Maximum current limiting<br />
Page 95 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Automatic reduction of current limit in the event of cooling fan<br />
failure<br />
� Boost charging and float charging current limiting<br />
� Earth fault monitoring and protection<br />
� Thermal overload protection<br />
Indications:<br />
� Rectifier ON<br />
� Battery run out timer/counter<br />
� Low battery voltage or blown battery fuse<br />
� High battery voltage<br />
� Charging failure<br />
� Failure in line voltage or auxiliary supply<br />
� Blown fuse, single phasing or over current<br />
� Fan failure<br />
� Battery on float charge /boost charge.<br />
� Inverter On<br />
� Inverter reserve synchronised<br />
Batteries:<br />
Batteries for UPS shall be lead acid sealed maintenance free type. The<br />
Ampere Hour rating of the battery shall be adequate to supply the<br />
inverters on full load for 30 minutes back up. Batteries shall be<br />
installed in suitable metallic enclosure and located near UPS.<br />
Inverter & Controls:<br />
Construction details:<br />
� Unitised construction<br />
� Free standing, floor mounted and indoor type<br />
� Provided with anti vibration Pads<br />
� Dust and vermin proof<br />
� Sheet steel clad , Min 2.0 mm thick for panels & : Min 1.6 mm<br />
thick for doors and side covers<br />
� With illumination lamps, door switches, space heaters and<br />
sockets for soldering<br />
� All control block plug-in type with test sockets<br />
� Units shall be self contained and serviceable<br />
Page 96 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
Basic Features:<br />
� IGBT Based.<br />
� With input circuit consisting of battery contactor, filter and<br />
smoothing reactor<br />
� Dc/dc converter for voltage control<br />
� Inverter proper and control electronics<br />
� Series reactor and parallel filter<br />
� Output transformer.<br />
� Static by-pass<br />
� Switch load automatically to the reserve power supply on<br />
fault<br />
� Fast acting inverter contactor to connect the inverter output<br />
to the load.<br />
� High speed fuses<br />
� The changeover within 20 ms.<br />
Indication<br />
� Load on inverter<br />
� Load on By-pass<br />
� Reserve within limits<br />
Meters<br />
� Output voltage - Phase-neutral & between phases<br />
� Output frequency<br />
� Ammeter in each phase<br />
� Battery current and voltage with indication of status in charge or<br />
discharge<br />
Alarms<br />
� Reserve out of limits<br />
� Load on reserve<br />
� Static switch off<br />
Protection against the following:<br />
� Abnormal output voltage<br />
� Abnormal link voltage<br />
� Over current on output<br />
� Over current on input or commutating failure<br />
� Low battery voltage<br />
� High transformer temperature<br />
Page 97 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
� Auxiliary supply failure<br />
� Fan failure<br />
� Logic failure<br />
� Clock failure<br />
1.3 Enclosure and ventilation<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
� Enclosure conforming to IP-41 class<br />
� Units shall be provided with cooling fans and louvers at the<br />
bottom sides.<br />
� Individual ventilation ducts for each unit shall be provided.<br />
1.4 UPS DISTRIBUTION BOARD<br />
Suitable UPS distribution board with sufficient feeders to supply<br />
individual PLC panels, I/O Panels, Workstations etc.<br />
20% spare supply feeders shall be considered for future use.<br />
Page 98 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com
ISO 9001 Company<br />
SCHEDULE-8<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
8.4 LIST OF RECOMMENDED SPARES FOR TWO YEARS OPERATION &<br />
MAINTENANCE<br />
SL.NO<br />
.<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
7<br />
8<br />
9<br />
<strong>10</strong><br />
11<br />
EQUIPMENT DESCRIPTION OF<br />
SPARE<br />
ELECTRICAL<br />
Contactor Coil<br />
Push Button<br />
Bulb for signal<br />
lamp<br />
Proximity switch<br />
Limit Switches<br />
AC incoming fuse<br />
for VVVF drive<br />
Control cards for<br />
VVVF drive<br />
Digital input<br />
module<br />
Digital output<br />
module<br />
Analog output<br />
module<br />
DC Link Fuse for<br />
QUANTIT<br />
Y<br />
INSTALLE<br />
D<br />
QUANTIT<br />
Y<br />
RECOMM<br />
ENDED<br />
2 nos. for<br />
each rating<br />
4 nos.<br />
<strong>10</strong> nos.<br />
4 nos.<br />
1 no. of<br />
each type<br />
1 set for<br />
each rating<br />
1 set<br />
1no.<br />
1no.<br />
1no.<br />
2 sets for<br />
each rating<br />
Page <strong>99</strong> of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />
VVVF drive<br />
HEAVY ENGINEERING CORPORATION LIMITED, DHURWA, RANCHI - 8340<strong>04</strong><br />
PHONE: 0651 2401278, FAX: 0651 2401166, EMAIL: pksingh@hecltd.com<br />
REMARKS
ISO 9001 Company<br />
<strong>Heavy</strong> Engineering Corporation Limited<br />
(A Govt. of India Enterprise)<br />
<strong>Heavy</strong> Machine Building Plant<br />
(Purchase Department/ MM Division)<br />
NOTE:-<br />
The above list is indicative. The <strong>Tender</strong>er shall provide the complete<br />
list during BE/DE stage.<br />
Page <strong>10</strong>0 of <strong>10</strong>0<br />
-----------------------------------------------------------------------------------------------------------------<br />