<strong>Dia</strong> <strong>Bras</strong> 2009 Challenges & Priorities<br />

Bolivar<br />

■ Raise financing for construction of a mill near the Bolivar Mine (US$6.5 M)<br />

� Process at Malpaso Mill 200 tpd high-grade material from Bolivar and<br />

generate positive cash flow at forecasted metal prices<br />

� <strong>Exploration</strong> program to expand and upgrade resources<br />

� Further reduction of direct operating costs<br />

Cusi<br />

� Metallurgical testing has been completed showing silver recovery of 85%<br />

by combined flotation and cyanidation methods<br />

� Start Cusi operations in August 2009 at 6,000 tpm with the flotation<br />

circuit and in parallel build the cyanidation system (US$1.5 M)<br />

� <strong>Exploration</strong> program to expand and upgrade resources<br />

� Expand production to 15,000 tpm by late 2010 by mining high grade silver<br />

from Promontorio<br />

Position the Company for the commodity markets recovery and pursue<br />

M&A activities to enhance the value of the Company<br />