ESA Document - Emits - ESA
ESA Document - Emits - ESA ESA Document - Emits - ESA
s HMM Assessment Study Report: CDF-20(A) February 2004 page 82 of 422 and further apoapsis lowering manoeuvres at the next pericentre pass. Alternatively, it might be an option to force a low-velocity escape. Failure before reaching a bound orbit: The manoeuvre fails while the spacecraft is still in a hyperbolic orbit with respect to Mars. In the case regarded in section 2.7.12.1, only the case of a complete failure was regarded. A partial failure would result in a trajectory closer to the orbit of Mars. • Incomplete execution of TEI: Here the case distinction made above also applies. 2.7.12.3 Conclusions An abort cannot be always guaranteed with no further consequences: • During the MOI and TEI manoeuvres abort is not possible • During the first part of the transfer to Mars, abort is always possible without mission mass increase • During the second part of the transfer to Mars, abort is always possible but mission mass increase is needed (either propulsion system or ERC) • From low Mars orbit, there are two possibilities: return via Venus swing-by but mass increase is needed or waiting for next return window 2.7.13 Aerobraking Aerobraking is a proven technique to remove energy from an orbit, e.g., when transferring from a highly eccentric orbit to one of low eccentricity, with minimal propellant consumption. Aerobraking involves lowering the pericentre of the initial orbit so that it grazes the upper atmosphere. At every perigee pass, the spacecraft loses some orbital energy to atmospheric friction. This lowers the apocentre radius. After a number of passes, during which the pericentre altitude must be observed and repeatedly corrected so that it does not descend too deeply into the atmosphere, the apocentre will have reached the required altitude. Then, a manoeuvre at the apocentre raises the pericentre and the aerobraking phase is terminated. The use of aerobraking rather than propulsive manoeuvres for final orbit acquisition can lead theoretically to significant savings in propellant mass. (see Mission architecture) For this reason, a preliminary estimation was performed in this study. 2.7.13.1 Requirements and design drivers Aerobraking is a lengthy process but it is relatively safe. The structural and thermal loads imposed on spacecraft components are low compared to other techniques involving atmospheric flight such as aerocapture and entry/landing. However, with the present spacecraft there were design concerns for some of the subsystems, in particular the solar arrays. If left deployed during aerobraking, they would provide the large surface area required to maximize the deceleration and minimise the manoeuvre duration but they would also be particularly vulnerable to the increased structural and thermal loads. Therefore it was necessary to perform a trade-off between the manoeuvre duration and the solar array restrictions. The constraints are summarized in Table 2-29:
s Maximum manoeuvre duration 6 months (about 180 days) Maximum dynamic pressure • Solar arrays facing flow • Solar arrays parallel to flow Maximum heat flux (Q) • Solar arrays facing flow • Solar arrays parallel to flow 0.2 N/m 2 13 N/m 2 10 kW/m 2 Uncertain Table 2-29: Aerobraking constraints HMM Assessment Study Report: CDF-20(A) February 2004 page 83 of 422 The dynamic pressure constraint comes from the structural limitations of the solar array structure. For the hinge the maximum allowable bending moment is 185 Nm and the maximum allowable shear load is 25 N and for the support beam the maximum allowable bending moment is 300 Nm (from the solar array design specifications). The force acting on the panels was evaluated from the dynamic pressure as: F = 1 PdynC D S 2 where CD is the drag coefficient of the structure (assumed to be that for a flat plate for which CD=2.0) and S is the surface area facing the flow. For a solar array area of 95 m 2 and a thickness of 0.1 m (including the thickness of the support beam), the maximum allowable dynamic pressure loads given above were derived. 2.7.13.2 Assumptions and trade-offs A trade-off was required between the aerobraking manoeuvre duration and the structural and thermal loads on the solar arrays. Three solar array configurations were considered in the tradeoff: 1. Solar arrays facing flow. 2. Solar arrays turned parallel to flow (to avoid stowage requirements). 3. Solar arrays stowed. The results of the various analyses are summarized in Table 3-31 below. The highlighted areas show values that violated the constraints outlined above. Option Qmax [kW/m 2 ] Pdyn,max [N/m 2 ] Duration Operational Issues 1 Solar arrays deployed 45.0 11.0 3 months facing flow 2 Solar arrays deployed 23.0 5.5 6 months facing flow 3 Solar arrays deployed low 0.2 about 8 yrs facing flow 4 Solar arrays deployed 60.0 13.0 About 16 Turning of arrays parallel to flow months 5 Solar arrays stowed 630.0 145.0 3 months Retraction deployment of arrays and 6 Solar arrays stowed 315.0 72.0 6 months Retraction deployment of arrays and Table 2-30: Results of aerobraking analyses
- Page 31 and 32: s HMM Assessment Study Report: CDF-
- Page 33 and 34: s Figure 2-10: Trajectory Overview
- Page 35 and 36: s 2.4.3.5 TEI and planetary protect
- Page 37 and 38: s HMM Assessment Study Report: CDF-
- Page 39 and 40: s HMM Assessment Study Report: CDF-
- Page 41 and 42: s HMM Assessment Study Report: CDF-
- Page 43 and 44: s HMM Assessment Study Report: CDF-
- Page 45 and 46: s Mars Excursion Vehicle Transfer H
- Page 47 and 48: s 2.7.5.1 Mission elements dry mass
- Page 49 and 50: s 2.7.5.8 MEV release The MEV is re
- Page 51 and 52: s Total mission time (days) 1200 10
- Page 53 and 54: s HMM Assessment Study Report: CDF-
- Page 55 and 56: s HMM Assessment Study Report: CDF-
- Page 57 and 58: s stack 9 Propellant mass of the ne
- Page 59 and 60: s HMM Assessment Study Report: CDF-
- Page 61 and 62: s HMM Assessment Study Report: CDF-
- Page 63 and 64: s HMM Assessment Study Report: CDF-
- Page 65 and 66: s The core supporting structure has
- Page 67 and 68: s 2.7.7.1.3 Mars excursion module S
- Page 69 and 70: s 2.7.7.1.4 Earth return capsule HM
- Page 71 and 72: s Mission Phase Description Event s
- Page 73 and 74: s Mission Phase Description Event s
- Page 75 and 76: s 2.7.10 Mission performance Table
- Page 77 and 78: s Days on Martian surface 450 400 3
- Page 79 and 80: s HMM Assessment Study Report: CDF-
- Page 81: s HMM Assessment Study Report: CDF-
- Page 85 and 86: s % of loss from baseline 20 18 16
- Page 87 and 88: s 2.7.15 Sensitivity analysis HMM A
- Page 89 and 90: s 2.7.15.4 Influence of the mass of
- Page 91 and 92: s HMM Assessment Study Report: CDF-
- Page 93 and 94: s Parameters used: • No Shuttle
- Page 95 and 96: s 2.8.3.3 Launch 3- Front node Figu
- Page 97 and 98: s HMM Assessment Study Report: CDF-
- Page 99 and 100: s HMM Assessment Study Report: CDF-
- Page 101 and 102: s HMM Assessment Study Report: CDF-
- Page 103 and 104: s HMM Assessment Study Report: CDF-
- Page 105 and 106: s HMM Assessment Study Report: CDF-
- Page 107 and 108: s HMM Assessment Study Report: CDF-
- Page 109 and 110: s 2.10.1.4 Communications HMM Asses
- Page 111 and 112: s HMM Assessment Study Report: CDF-
- Page 113 and 114: s 2.10.2.2.2 LEO assembly HMM Asses
- Page 115 and 116: s HMM Assessment Study Report: CDF-
- Page 117 and 118: s Basic RF link Four 70-m Ka-band s
- Page 119 and 120: s HMM Assessment Study Report: CDF-
- Page 121 and 122: s HMM Assessment Study Report: CDF-
- Page 123 and 124: s HMM Assessment Study Report: CDF-
- Page 125 and 126: s 3 TRANSFER VEHICLE 3.1 Systems…
- Page 127 and 128: s Operational Requirements It shall
- Page 129 and 130: s Trans Mars Injection Module Mars
- Page 131 and 132: s Figure 3-2: Parallel configuratio
s<br />
Maximum manoeuvre duration 6 months (about 180 days)<br />
Maximum dynamic pressure<br />
• Solar arrays facing flow<br />
• Solar arrays parallel to flow<br />
Maximum heat flux (Q)<br />
• Solar arrays facing flow<br />
• Solar arrays parallel to flow<br />
0.2 N/m 2<br />
13 N/m 2<br />
10 kW/m 2<br />
Uncertain<br />
Table 2-29: Aerobraking constraints<br />
HMM<br />
Assessment Study<br />
Report: CDF-20(A)<br />
February 2004<br />
page 83 of 422<br />
The dynamic pressure constraint comes from the structural limitations of the solar array<br />
structure. For the hinge the maximum allowable bending moment is 185 Nm and the maximum<br />
allowable shear load is 25 N and for the support beam the maximum allowable bending moment<br />
is 300 Nm (from the solar array design specifications). The force acting on the panels was<br />
evaluated from the dynamic pressure as:<br />
F = 1 PdynC<br />
D S<br />
2<br />
where CD is the drag coefficient of the structure (assumed to be that for a flat plate for which<br />
CD=2.0) and S is the surface area facing the flow. For a solar array area of 95 m 2 and a thickness<br />
of 0.1 m (including the thickness of the support beam), the maximum allowable dynamic<br />
pressure loads given above were derived.<br />
2.7.13.2 Assumptions and trade-offs<br />
A trade-off was required between the aerobraking manoeuvre duration and the structural and<br />
thermal loads on the solar arrays. Three solar array configurations were considered in the tradeoff:<br />
1. Solar arrays facing flow.<br />
2. Solar arrays turned parallel to flow (to avoid stowage requirements).<br />
3. Solar arrays stowed.<br />
The results of the various analyses are summarized in Table 3-31 below. The highlighted areas<br />
show values that violated the constraints outlined above.<br />
Option Qmax<br />
[kW/m 2 ]<br />
Pdyn,max<br />
[N/m 2 ]<br />
Duration Operational Issues<br />
1 Solar arrays deployed 45.0 11.0 3 months<br />
facing flow<br />
2 Solar arrays deployed 23.0 5.5 6 months<br />
facing flow<br />
3 Solar arrays deployed low 0.2 about 8 yrs<br />
facing flow<br />
4 Solar arrays deployed 60.0 13.0 About 16 Turning of arrays<br />
parallel to flow<br />
months<br />
5 Solar arrays stowed 630.0 145.0 3 months Retraction<br />
deployment of arrays<br />
and<br />
6 Solar arrays stowed 315.0 72.0 6 months Retraction<br />
deployment of arrays<br />
and<br />
Table 2-30: Results of aerobraking analyses