s<br />

2.10.2.2.2 LEO assembly<br />

HMM<br />

Assessment Study<br />

Report: CDF-20(A)<br />

February 2004<br />

page 113 of 422<br />

The LEO Assembly task is in charge of all operations of the spacecraft composite until end of<br />

assembly/start of commissioning.<br />

The LEO assembly is concerned with integrating a new element into the transfer spacecraft<br />

composite structure every 50 days over a timespan of 3.5 years. Each type of composite<br />

component needs its dedicated team of specialists to look after. In addition there are highly<br />

complex robotic operations to be conducted with the service platforms. To be able to do the<br />

assembly in a minimum time, shift work is assumed during the commissioning periods.<br />

The spacecraft composite does not support an early manned capability. The early EVAs (when<br />

needed) are performed by the visiting Shuttle crew. The responsibility for these EVAs is<br />

assumed to rest with the Shuttle operator.<br />

The concept is to establish a dedicated operations infrastructure specialized in the assembly of<br />

the transfer spacecraft. A hierarchical control infrastructure is proposed for the overall spacecraft<br />

and the composite components geared to the changing characteristics of the built-up spacecraft<br />

composite.<br />

Operations Architecture:<br />

LEO Assembly Flight Operations Team, consisting of:<br />

• System Team<br />

• Mission Planning Team (in control of launches and resources)<br />

• Component Operations Teams (one team for each type of component)<br />

• Workbench Operations Team<br />

Industrial Support Team for LEO Assembly with system and subsystem experts (DHS, thermal,<br />

power, mechanisms, AOCS etc.), responsible for the following teams:<br />

• System Team<br />

• Propulsion Stages MOI<br />

• Propulsion Stages TMI<br />

• Service platforms<br />

• SM<br />

• Airlock and Cupola<br />

• PM Central Structure Items<br />

• Habitation Module<br />

• Launcher Interface<br />

Mission Control System, consisting of:<br />

• System mission control system<br />

• Component mission control systems<br />

Simulators, consisting of:<br />

• System simulator (being able to represent the different stages of assembly)