In 2006, the soil investigations and basic engineering for the project were carried out and the design basis was finalised by the owner’s engineer (JV Technum-Tractebel, ELSAM, SOGREAH) and certified by DNV. DEME was selected as the marine contractor responsible for all offshore construction works, such as the dredging works for the foundations, the construction and lifting of the gravity-based foundations, the cable-laying works and the installation works of the turbines. The detailed design is ongoing by the marine contractor’s engineer, COWI. Meanwhile, based on the obtained best and final offers, the negotiation process with contractors is ongoing, and will lead to the start of the execution works at the beginning of the second quarter of 2007. The planning is split into three phases, taking into account the obligation outlined in the building and environmental permit, to first develop a demonstration stage of 6 tur- bines. Following the preparatory onshore works for phase 1 in 2007, the offshore works will be executed in the good weather season (May-September) of 2008, assuring the first offshore energy production of the Belgian coast by October 1 st 2008. C F E A N N U A L R E P O R T 2 0 0 6 I 1 2 6 e c o r p o r a t e f i n a n c i a l y e a r Rock placement services in the North Sea by the D.P. “Rollingstone”. 7 5

7 6 Financial report Corporate governance Management report Consolidated financial statements Statutory financial statements

In <strong>2006</strong>, the soil investigations and basic engineering for<br />

the project were carried out and the design basis was<br />

finalised by the owner’s engineer (JV Technum-Tractebel,<br />

ELSAM, SOGREAH) and certified by DNV. DEME was<br />

selected as the marine contractor responsible for all<br />

offshore construction works, such as the dredging works<br />

for the foundations, the construction and lifting of the<br />

gravity-based foundations, the cable-laying works and<br />

the installation works of the turbines. The detailed design<br />

is ongoing by the marine contractor’s engineer, COWI.<br />

Meanwhile, based on the obtained best and final offers, the<br />

negotiation process with contractors is ongoing, and will<br />

lead to the start of the execution works at the beginning of<br />

the second quarter of 2007.<br />

The planning is split into three phases, taking into account<br />

the obligation outlined in the building and environmental<br />

permit, to first develop a demonstration stage of 6 tur-<br />

bines. Following the preparatory onshore works for phase<br />

1 in 2007, the offshore works will be executed in the good<br />

weather season (May-September) of 2008, assuring the<br />

first offshore energy production of the Belgian coast by<br />

October 1 st 2008.<br />

C F E A N N U A L R E P O R T 2 0 0 6 I 1 2 6 e c o r p o r a t e f i n a n c i a l y e a r<br />

Rock placement services<br />

in the North Sea by the<br />

D.P. “Rollingstone”.<br />

7 5