3. Replace Astro Turf external court surface with a 3G rubber crumb.<br />

It is proposed to remove existing astro turf surface from one external court and<br />

replace with 3G rubber crumb surface similar to existing surface on the other<br />

external court. There are two external courts,1 of which is an astro turf surface and<br />

the other is state of the art 3G Rubber crumb. These surfaces were both laid in 2007<br />

and it was decided then to install astro turf on one as it offered the potential for a<br />

range of sports such as tennis , netball etc. In practice these games have never<br />

been taken up and the court is underutilised as customers playing 5-a-side football<br />

have a strong preference for the 3G surface.<br />

Reasons<br />

• 3G Surface out sells astro 2 to 1 and many court hires are lost.<br />

• Tennis, netball and multi sports have not taken off and with 5 a side now being as<br />

popular as it is there is a potential to increase sales of court time on another 3G<br />

surface<br />

• There is now the opportunity for multi sports to be played on 3G.<br />

• The existing maintenance programme would be amended and less equipment<br />

required - reducing costs.<br />

• There is an opportunity to increase footfall and secondary income generation.<br />

Financial<br />

The capital cost of the work is estimated to be £22,000<br />

Assuming the resurfaced court is used as often as the existing 3G court an additional<br />

£5,000 income pa would be realised.<br />

Payback on investment on this basis alone would therefore be achieved in under 5<br />

years.<br />

Potential Barriers<br />

• None identified<br />

Update<br />

This work was completed on budget (£22,000) and has increased income above<br />

projections by £2,000 in the first year.<br />