29.01.2013 Views

REC- 1-51.p65 - Rural Electrification Corporation Ltd.

REC- 1-51.p65 - Rural Electrification Corporation Ltd.

REC- 1-51.p65 - Rural Electrification Corporation Ltd.

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

RURAL ELECTRIFICATION CORPORATION LIMITED<br />

1. INDUSTRY STRUCTURE<br />

MANAGEMENT DISCUSSION AND ANALYSIS REPORT<br />

[Pursuant to Clause 49 (IV) (F) of the Listing Agreement]<br />

During the fiscal 2010 a total of 9585 MW of generation<br />

capacity was added. The country’s power deficit was<br />

marginally lower than that of previous year at 10.1 per cent<br />

of the total demand. The peak power deficit during the fiscal<br />

year was, however, marginally higher than previous year at<br />

12.7% of the peak demand.<br />

So far during the first three years of the 11th five year plan,<br />

the installed generation capacity has grown from 132.33 GW<br />

at the end of fiscal 2007 to 159.4 GW at the end of fiscal<br />

2010 representing an addition of 27068 MW. The target<br />

capacity addition during the 11th plan has been kept at 78700<br />

MW. According to the Report of the Working Group on Power<br />

for Eleventh Plan of the GoI (fiscal 2008 to fiscal 2012), the<br />

overall requirement of funds for the power sector has been<br />

estimated at Rs. 10,316,000 million. For the Twelfth Plan<br />

period, CEA estimates that in order to meet the projected<br />

demand requirement by 2017, capacity addition of 100,000<br />

MW would be required; and including additions required<br />

in expanding transmission and distribution systems, the total<br />

fund requirement for the plan period would be about<br />

Rs. 11,000,000 million.<br />

Generation<br />

The installed generation capacity increased by 9585 MW<br />

during fiscal 2010 with 2180 MW added in the Central sector,<br />

3118 MW added in the State sector and 4287 MW added in<br />

the Private sector. The total installed generation capacity<br />

was 159398 MW at the end of March 2010.<br />

(Units in MW)<br />

Sector Installed Installed Increase in Target<br />

Capacity Capacity Installed Capacity<br />

at the end of as on Capacity Addition<br />

10th Plan 31.10.2010 so far in during<br />

(2007) 11th plan 11th Plan<br />

(2012)<br />

State 70096 79392 9296 26783<br />

Central 45121 50992 5871 36874<br />

Private 17113 29014 11901 15043<br />

Total 132330 159398 27068 78700<br />

*Source CEA report<br />

In addition to the above there is a captive generating capacity<br />

of 19509 MW, connected to the grid.<br />

Transmission<br />

About 15583 ckm of transmission lines were added in the<br />

fiscal 2010 in the country with total length aggregating about<br />

2.36 lakh ckm at the end of fiscal 2010. The installed length<br />

of transmission lines at the end of 10th plan i.e. fiscal 2007<br />

was about 1.98 lakh ckt kms. The substation transformation<br />

capacity at 400 kV and 220 kV level aggregated 3.06 lakh<br />

MVA excluding 4500 MVA of 765kV transformation capacity,<br />

at the end of fiscal 2010.<br />

Investments for transmission system development and<br />

related schemes during the Eleventh Plan period is estimated<br />

at Rs. 1,400,000 million, with Rs. 750,000 million being<br />

required for the central sector and Rs. 650,000 million being<br />

required for the state sector. Further, CEA estimates that in<br />

the 12 th plan the funds requirement for transmission sector<br />

would be about Rs. 2,400,000 million, with Rs. 1,400,000<br />

million being required for the central sector and Rs. 1,000,000<br />

million being required for the state sector.<br />

The focus of transmission system development is to provide<br />

adequate inter-regional and intra-regional transmission<br />

capacity so as to consolidate and strengthen the national<br />

grid network towards a strong all-India grid. GoI’s<br />

transmission perspective plans focus on the creation of a<br />

national grid in a phased manner by adding over 60,000 ckm<br />

of transmission network by 2012.<br />

Distribution<br />

ANNEXURE-I<br />

The total fund requirement for sub-transmission and<br />

distribution system development for urban and rural areas,<br />

during the eleventh Plan period is estimated at Rs. 2,870,000<br />

million inclusive of APDRP and RGGVY schemes. Further,<br />

CEA estimates that for the 12 th five year plan period, the<br />

total fund requirement for the Distribution sector, would be<br />

about Rs.3,710,000 million.<br />

The R-APDRP scheme (Restructured APDRP) seeks to<br />

address the issue of limited resources with the SEBs and<br />

State Public Utilities and their resultant inability to upgrade<br />

the distribution network. R-APDRP focuses on actual,<br />

demonstrable performance in terms of sustained loss<br />

reduction and proposes to cover urban areas - towns and<br />

cities with population of more than 30,000 (10,000 in case<br />

of special category states). In addition, in certain high-load<br />

density rural areas with significant loads, works of separation<br />

of agricultural feeders from domestic and industrial ones,<br />

and of High Voltage Distribution System (11kV) will also be<br />

taken up. The Part-A of R-APDRP aims at preparation of<br />

Base-line data for the project area covering Consumer<br />

Indexing, GIS Mapping, Metering of Distribution<br />

Transformers and Feeders, and Automatic Data Logging for<br />

all Distribution Transformers and Feeders and SCADA / DMS<br />

system etc. Part-B aims at renovation, modernization and<br />

strengthening of 11 kV level Substations, Transformers/<br />

Transformer Centers, Re-conductoring of lines at 11kV level<br />

and below and upgradation of the entire last mile distribution<br />

infrastructure.<br />

GoI provides 100% Loan for part-A of the R-APDRP schemes<br />

and upto 25% (90% for special category States) Loan for<br />

part-B of the R-APDRP schemes for which funds would be<br />

channelized through PFC / <strong>REC</strong>. The entire amount of GoI<br />

loan for part-A of the project is converted into grant after<br />

establishment of the required base-line data system within<br />

a stipulated time frame and duly verified by third party<br />

inspection agencies. Part-B loans to the extent of 50% (90%<br />

for special category States) are converted into grant in five<br />

equal tranches on achieving 15% AT&C loss in the project<br />

area duly verified by third party inspection agencies, on a<br />

sustainable basis for a period of five years.<br />

39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!