Connecting External Sources SMA Solar Technology AG<br />
The generator is disconnected by the <strong>Sun</strong>ny Island after the GENRDY signal has been withdrawn by<br />
the GenMan.<br />
NOTICE!<br />
Occurrence of unpredictable operating states.<br />
• Never carry out a manual start directly at the generator.<br />
• Observe the indications in the GenMan manual.<br />
14.1.3 Generator Operation<br />
The <strong>Sun</strong>ny Island allows automatic operation (depending on state of charge or load)<br />
(see 14.1.5 ”Automatic Generator Operation” (page 114)). In addition, manual operation is also<br />
possible.<br />
14.1.4 Manual Generator Operation<br />
The manual operating modes for the generator management are tripped using the<br />
"540.01 GnManStr" parameter. Here, a distinction is made between the following operating modes:<br />
Auto: In this operating mode, the generator is automatically started due to the settings.<br />
This includes the start via the state of charge or the consumer power or by the<br />
request for a manual equalization charge.<br />
("520.01 ChrgSelMan" = Start).<br />
Stop: The generator is manually stopped. The current generator request is canceled –<br />
immediate disconnection from generator and change to lock state. Once the lockout<br />
time has ended, the generator switches into automatic operation.<br />
Start: Manual generator start – the generator runs "continuously" until stopped.<br />
The generator can only be manually stopped.<br />
Run1h: Operation for one hour. Once the lockout time has expired, the transition back into<br />
automatic mode follows.<br />
An equalization charge can be manually started using the "520.01 ChrgSelMan" parameter.<br />
This sets the battery management (see 13 ”Battery Management” (page 97)) in the equalization<br />
charge state and the generator is requested. This request persists until equalization charge has been<br />
completed.<br />
The following process diagrams provide an overview of the start/stop behavior of the <strong>Sun</strong>ny Island<br />
during manual generator operation:<br />
112 SI<strong>5048</strong>-TB-TEN110340 <strong>Technical</strong> <strong>Description</strong>