APPENDIX B3G: COSTING FOR NORTH GRID PROJECTS<br />
Grid Project Cost R’ mil Grid Total<br />
Acornhoek Upgrade 2x 125MVA 275/132kV transformers<br />
17<br />
Brits 400kV Reinforcement<br />
949<br />
Coal 3 Phase 1 - 765kV<br />
0*<br />
Coal 3 Phase 2 - 800kV HVDC<br />
12,000<br />
Dwaalboom 132kV switching station<br />
45<br />
Foskor 275/132kV transformation upgrade<br />
1,096<br />
Foskor 275kV Reinforcement<br />
0**<br />
Medupi Integration (Alpha) Phase 1A: Spitskop and Dinaledi<br />
10,140<br />
Northern<br />
Medupi Integration (Charlie) Phase 2A: Mogwase<br />
Medupi Integration (Charlie) Phase 2B: Mokopane<br />
647<br />
647<br />
33,777<br />
Medupi Integration (Charlie) Phase 2C: Epsilon and Delta<br />
4,599<br />
Nzhelele 400kV reinforcement<br />
2,387<br />
Pelly 132/22kV transformation upgrade<br />
28<br />
Rustenburg Transformation Reinforcement<br />
194<br />
Spitskop 400/132kV Transformation<br />
221<br />
Tabor and Spencer Reinforcement - Phase 1<br />
185<br />
Tabor and Spencer Reinforcement - Phase 2<br />
622<br />
Medupi Integration (Alpha) Phase 1B: Marang<br />
0***<br />
* Cost is included in Coal 3 Phase 2 - 800kV HVDC (also includes HVDC costs in the Central and East Grids)<br />
**Costs included in Foskor 275/132kV transformation upgrade<br />
***Costs in Medupi Integration (Alpha) Phase 1A: Spitskop and Dinaledi<br />
Please note that the amounts in the tables represents cash flows in the <strong>Ten</strong>-year plan periods, any cash flows not falling<br />
within this period have not been added, consequently the total cost of the plan may be higher that reflected here. Excludes<br />
Customer Project and includes <strong>Eskom</strong> Generation Projects.<br />