APPENDIX B3A: COSTING FOR CENTRAL GRID PROJECTS<br />
Grid Project Cost R’ mil Grid Total<br />
Benburg Ext 3rd 250MVA 275/132kV<br />
145<br />
Croydon Ext 3rd 250MVA 275/132kV transformer<br />
144<br />
Demeter 400kV Integration<br />
1,115<br />
Eiger Ext 3rd 80MVA 88/33kV transformer<br />
30<br />
Johannesburg Reactive Power Project<br />
50<br />
Johannesburg East Strengthening - Phase 1<br />
460<br />
Johannesburg East Strengthening - Phase 2<br />
615<br />
Johannesburg East Strengthening- Phase 3 A-D<br />
2,165<br />
Johannesburg East Strengthening - Phase 3 E-F<br />
1,928<br />
Johannesburg North - Phase 2a<br />
208<br />
Johannesburg North - Phase 2b<br />
83<br />
Johannesburg Strengthening<br />
2,437<br />
Kookfontein Phase 1<br />
17<br />
Kookfontein Phase 2<br />
132<br />
Central Kyalami Integration<br />
1,775 17,856<br />
Siluma 275/88kV MTS<br />
821<br />
Simmerpan 275/132kV substation<br />
396<br />
Simmerpan 275/88kV substation<br />
497<br />
Snowdon transformer upgrade<br />
116<br />
Vaal Strengthening Phase 1: Glockner 400/275kV Trfr<br />
509<br />
& Hera-Bernina<br />
.<br />
Vaal Strengthening Phase 2<br />
317<br />
West Rand Strengthening - Phase: Etna 400kV<br />
590<br />
Soweto Strengthening Phase 2 - 275/132kV<br />
563<br />
Soweto Strengthening Phase 1 - 275kV<br />
616<br />
West Rand Strengthening - Phase: Glockner and Hera 400kV<br />
326<br />
Coal 3 Phase 2 - 800kV HVDC<br />
0*<br />
West Rand Strengthening - Phase: Westgate B and<br />
Taunus 400kV<br />
1801<br />
* Cost included in Coal 3 Phase 2 - 800kV HVDC (Northern Region)<br />
Please note that the amounts in the tables represents cash flows in the <strong>Ten</strong>-year plan periods, any cash flows not falling<br />
within this period have not been added, consequently the total cost of the plan may be higher that reflected here. Excludes<br />
Customer Project and includes <strong>Eskom</strong> Generation Projects.<br />
© <strong>Eskom</strong> <strong>2011</strong> 53