Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Type Total R’mil<br />
Customer 6,100<br />
Generation 31,200<br />
Reliability 127,000<br />
Grand Total 164,300<br />
Table 7.2: Capital expenditure per project type<br />
Please note that the amounts in the tables represents cash flows in the <strong>Ten</strong>-year plan periods, any cash flows not falling<br />
within this period have not been added, consequently the total cost of the plan may be higher than reflected here. The total<br />
excludes Scope Definition Costs.<br />
The details of costing per Grid and Project type are shown in Appendix B. For purposes of confidentiality the planned<br />
or exact costs per project of Customer Projects have been excluded from the table, however the total sum of all<br />
customer projects are indicated in Table 7.2 above.<br />
8. Concluding Remarks<br />
The most visible difference between this TDP and the previous year’s TDP is the phasing and spread of the projects<br />
over the planning period. There has been some re-phasing of the existing projects, using more realistic completion<br />
dates based on execution timelines, as well as to address financial constraints resulting from the current shortage of<br />
capital.<br />
There have been a number of additional projects included in the middle part of the planning period mainly due to new<br />
substation injection points and existing substation transformer expansion. This is mainly due to a better positioning of<br />
loads due to spatial load forecasting techniques applied.<br />
There has been a reduction in the transformation capacity requirements ( by 4) over the new TDP period compared<br />
to the previous TDP which is mainly due to an increase in the number of transformers expected to be commissioned<br />
in the year 2010 (by 8) which is outside of the new TDP window.<br />
The total kilometres of additional lines has reduced from the previous TDP (by approx a total of 1100km) mainly due<br />
to lines commissioned in 2010 (approx 550km) and the re-phasing of existing projects beyond the <strong>2020</strong>.<br />
The resultant is an improved and more realistic or achievable spread of the transmission line projects and transformer<br />
installations. The result of the slower rate of completion of the transmission lines and new transformers is the<br />
increase of the risk to the network overall. This can be seen by the number of N-1 unfirm substations which take a<br />
longer period to be resolved as opposed to the previous TDP. However this risk can be managed as the N-1 unfirm<br />
refers to the strict deterministic level which assumes that the N-1 event will happen at the time of the loading peak.<br />
In reality there is a limited chance of this happening and operational mitigation plans will cater for most of the events<br />
until the required projects are completed.<br />
© <strong>Eskom</strong> <strong>2011</strong> 49