48<br />
7. Capital Expenditure <strong>Plan</strong><br />
The total capital expenditure including expansion, refurbishment, facilities, production equipment, and land acquisition<br />
project costs amount to R 204.2 billion. This summary is shown in Table 7.1 and Figure 7.1 below. It is clear that<br />
the majority of the cost will be expansion related as this relates directly to the strengthening of the network to<br />
accommodate new customers as well as new generation.<br />
Table 7.1: Capital Expenditure per year for different categories of projects<br />
Figure 7.1: Summary of Capital Expenditure in the <strong>Transmission</strong> Division<br />
Refurbishment and land acquisition projects are the second and third-most expensive items in the capital expenditure,<br />
respectively. Refurbishment is required to prolong the life of assets and land acquisition projects are required to<br />
purchase the land in which to build the expansion assets.<br />
The summary of expansion capital expenditure per project type required to realise this ten-year plan is shown in<br />
Table 7.2. The total expenditure is expected to be approximately of R 166 billion, this is approximately R 21 billion<br />
higher than the previous ten-year plan.<br />
The main reasons for this variance are because:<br />
• A provision was added covering the <strong>2020</strong> (a new year in the planning window) year list of projects.<br />
• Of project cost escalations due to re-phasing.<br />
• Of new projects added.<br />
<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong>