Cape Corridor 765kV – Phase 4<br />

• Construct the second Zeus-Perseus-Gamma-Omega 765kV line 2017<br />

If there is no nuclear generation in the Cape then the Main Cape Corridor will have to be reinforced again around<br />

<strong>2020</strong>. The reinforcement may be HVDC, in light with the current strategic grid plan.<br />

6.7.2 CAPE PENINSULA CLN<br />

The 400kV in-feeds into Muldersvlei, Stikland and Acacia nodes provide N-1 redundancy but the Acacia-Philippi infeed<br />

will reach capacity in 2012. The proposed 2nd Koeberg-Acacia 400kV line will ensure continued N-1 redundancy<br />

for Acacia beyond 2012. Firgrove substation will be needed to supply Somerset West and surrounding areas.<br />

To address the Philippi transformation capacity problem, it is proposed to establish a new 400/132kV substation in the<br />

Mitchells Plain area to relieve the loading at Philippi by constructing two 400kV lines from either Stikland or Firgrove<br />

substation. There is a proposal to convert units at Ankerlig from OCGT to CCGT, starting in <strong>2020</strong>. This would require<br />

an Ankerlig-Omega 400kV line to meet Grid Code requirements. It has been omitted from the TDP due to the<br />

uncertainties regarding the project.<br />

The projects within the Cape peninsula CLN are as follows:<br />

• Acacia 3rd 500MVA 400/132kV transformer 2010<br />

• Philippi 3rd 500MVA 400/132kV transformer (spare) 2013<br />

• Koeberg off-site Supply relocate & Associated work 2012<br />

• Firgrove 400/132kV substation 2014<br />

• Muldersvlei 3rd 500MVA transformer & Series Reactor 2013<br />

• Mitchells Plain 400/132kV substation 2016<br />

6.7.3 WEST COAST CLN<br />

The West Coast, Namaqualand, and parts of the Peninsula CLN are supplied via the Hydra-Aries-Aurora power<br />

corridor. It is proposed to create a new Ferrum-Aries 400kV power corridor once both the Mercury-Ferrum and<br />

Epsilon-Ferrum 400kV corridors have been established.<br />

Sishen-Saldanha traction upgrade<br />

In addition to the strengthening projects, the Sishen-Saldanha traction upgrade project would result in the establishment<br />

of four new 400kV traction substations, one new 275kV substation, two SVCs, and the Aries-Nieuwehoop 400kV line.<br />

Although the 275kV infrastructure will be in the Kimberley CLN, it is listed here because it is an integral part of the<br />

Sishen-Saldanha traction upgrade scheme.<br />

The strengthening projects within the West Coast CLN are as follows:<br />

• Construct the Aries SVC 2016<br />

• Construct Sishen Saldanha Phase 1 (1x275/50kV s/s + Garona SVC) 2012<br />

• Construct Sishen Saldanha Phase 2 (4x400/50kV s/s + Aries-Nieuwehoop line) 2014/2015<br />

• Construct the Ferrum-Nieuwehoop 400kV line 2016/2017<br />

• Upgrade Juno to 2x80MVA, 132/66/22kV transformers 2016/2017<br />

© <strong>Eskom</strong> <strong>2011</strong> 45