38<br />

6.6 SOUTH GRID<br />

The South Grid consists of the area to the south-eastern side of Hydra substation, which predominantly falls within<br />

the Eastern Cape Province boundary. It comprises three Customer Load Networks (CLNs), namely: Port Elizabeth,<br />

East London, and Karoo. The current transmission network and CLNs are shown in Figure 6.11 below.<br />

Figure 6.11: Current South Grid network and CLNs<br />

The high forecasted average growth rate for Port Elizabeth CLN is mainly attributed to the new Industrial <strong>Development</strong><br />

Zone (IDZ) at Coega near Port Elizabeth. The expected peak demands by 2016 and <strong>2020</strong> as well as the average<br />

percentage load increase for the period, for each CLN are given in Table 6.11 below.<br />

CLN<br />

Peak Load<br />

(MW) 2009<br />

<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong><br />

Forecasted Load (MW)<br />

2016 <strong>2020</strong><br />

Ave. Annual % Load<br />

Increase<br />

Karoo 234 256 273 1.41%<br />

East London 507 827 924 6.04%<br />

Port Elizabeth 813 1784 2772 12.59%<br />

Table 6.11: South Grid CLN load forecast and percentage load increases