The next stage of the reinforcement of the Main Cape Corridor, if required in 2019, will pass through the North West<br />

grid, linking Selemo (Epsilon) 765kV to Gamma 765kV via Perseus 765kV. The total length of this 765kV line project<br />

has been allocated to this grid.<br />

The increase in transmission assets by end 2015 and end <strong>2020</strong> and the cumulative total are shown in Table 6.10.<br />

<strong>Transmission</strong> Assets<br />

for North-West Grid<br />

New Assets expected in<br />

<strong>2011</strong> - 2015<br />

Table 6.10: Cumulative assets for North West grid<br />

New Assets expected<br />

in 2016 - <strong>2020</strong><br />

Total New<br />

Assets expected<br />

Total kms of line 1,345 2,349 3,694<br />

765kV Lines (km)<br />

400kV Lines (km)<br />

275kV Lines (km)<br />

Total installed<br />

Transformer MVA<br />

955<br />

390<br />

0<br />

1,600<br />

639<br />

110<br />

2,555<br />

1,029<br />

110<br />

4,250 1,750 6,000<br />

Transformers (no. of) 8 5 13<br />

Capacitors (no. of) 9 0 9<br />

Reactors (no. of) 7 10 17<br />

6.5.1 CARLETONVILLE CLN<br />

The North-West Grid is composed of four CLNs namely Bloemfontein, Carletonville, Kimberley, and Welkom.<br />

The current transmission network and CLNs are shown in Figure 6.9 below.<br />

The new Watershed B 400/132kV substation west of Watershed is proposed; it is intended to de-load and<br />

provide support to Watershed via the 132kV network by 2017. Load growth in the area is driven by the cement<br />

industry and mining activity. Platinum and ferrochrome mining and processing activity is expected to materialise north<br />

of Watershed.<br />

The project will comprise the following:<br />

7 Build a 400kV line from Selemo (Epsilon) to Watershed B substation 2017<br />

8 Establish 400/132kV transformation at Watershed B 2017<br />

© <strong>Eskom</strong> <strong>2011</strong> 35