The next stage of the reinforcement of the Main Cape Corridor, if required in 2019, will pass through the North West<br />
grid, linking Selemo (Epsilon) 765kV to Gamma 765kV via Perseus 765kV. The total length of this 765kV line project<br />
has been allocated to this grid.<br />
The increase in transmission assets by end 2015 and end <strong>2020</strong> and the cumulative total are shown in Table 6.10.<br />
<strong>Transmission</strong> Assets<br />
for North-West Grid<br />
New Assets expected in<br />
<strong>2011</strong> - 2015<br />
Table 6.10: Cumulative assets for North West grid<br />
New Assets expected<br />
in 2016 - <strong>2020</strong><br />
Total New<br />
Assets expected<br />
Total kms of line 1,345 2,349 3,694<br />
765kV Lines (km)<br />
400kV Lines (km)<br />
275kV Lines (km)<br />
Total installed<br />
Transformer MVA<br />
955<br />
390<br />
0<br />
1,600<br />
639<br />
110<br />
2,555<br />
1,029<br />
110<br />
4,250 1,750 6,000<br />
Transformers (no. of) 8 5 13<br />
Capacitors (no. of) 9 0 9<br />
Reactors (no. of) 7 10 17<br />
6.5.1 CARLETONVILLE CLN<br />
The North-West Grid is composed of four CLNs namely Bloemfontein, Carletonville, Kimberley, and Welkom.<br />
The current transmission network and CLNs are shown in Figure 6.9 below.<br />
The new Watershed B 400/132kV substation west of Watershed is proposed; it is intended to de-load and<br />
provide support to Watershed via the 132kV network by 2017. Load growth in the area is driven by the cement<br />
industry and mining activity. Platinum and ferrochrome mining and processing activity is expected to materialise north<br />
of Watershed.<br />
The project will comprise the following:<br />
7 Build a 400kV line from Selemo (Epsilon) to Watershed B substation 2017<br />
8 Establish 400/132kV transformation at Watershed B 2017<br />
© <strong>Eskom</strong> <strong>2011</strong> 35