6.2.2 EMPANGENI CLN<br />

The Empangeni CLN consists mainly of industrial load. The load profile for this area is fairly flat. There are four 400kV<br />

lines that supply power into this network, with 275kV lines linking this CLN to the Pinetown CLN via Impala substation.<br />

The following strengthening is proposed:<br />

Empangeni Strengthening Phase 1 (under construction)<br />

• Completion of the Majuba-Umfolozi 765kV line operated at 400kV 2010<br />

Empangeni Strengthening Phase 2<br />

• Establish Theta 400kV switching station 2013<br />

• Construct Umfolozi-Theta 765kV line to be operated at 400kV 2013<br />

• Loop Umfolozi-Athene 400kV line into Theta 2013<br />

• Loop Umfolozi-Invubu 400kV line into Theta 2013<br />

• Construct Theta-Invubu 400kV line 2013<br />

Empangeni Strengthening Phase 3 2015<br />

• Establish Lambda 400/765kV substation next to Majuba Power Station<br />

• Establish 765/400kV at Mbewu (Theta)<br />

• Convert Majuba - Umfolozi – Mbewu (Theta) line to Lamda – Mbewu (Theta) and operate at 765kV<br />

Pinetown-Empangeni Interconnection (previously Pinetown Phase 3)<br />

• Construct Sigma–Theta 400kV first and second Lines (double circuit) 2015<br />

Empangeni Strengthening Phase 4 2016<br />

• Establish 400/765kV at Camden<br />

• Construct Camden – Mbewu (Theta) 765kV line to be operated at 765kV<br />

• Install 2nd 765/400kV Transformer at Mbewu (Theta)<br />

6.2.3 PINETOWN CLN<br />

The Pinetown load is mostly residential and commercial in nature. There are four 400kV and two 275kV lines that<br />

supply power into this network. As mentioned under Empangeni CLN, the Pinetown and Empangeni CLNs are linked<br />

with a 275kV line via Avon substation. The following major projects are planned:<br />

Pinetown Strengthening Phase 1<br />

• Establish Sigma 400kV switching station 2013<br />

• Construct Majuba-Sigma 765kV (via Venus) line operated at 400kV 2013<br />

• Construct new Sigma-Hector 2x 400kV lines. 2013<br />

Pinetown Strengthening Phase 1B<br />

• Recycle Venus –Georgedale line into second Venus–Ariadne 400kV line<br />

Pinetown Strengthening Phase 2 2015<br />

• Establish 765/400kV at Sigma 2015<br />

• Convert Majuba-Sigma line to Zeus-Sigma and operate at 765kV 2015<br />

A geographical network diagram indicating the major projects in the East Grid for the ten-year period is shown<br />

in Figure 6.4.<br />

<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong>