Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
20<br />
6.2 EAST GRID<br />
The East Grid consists of four CLNs namely, Ladysmith, Newcastle, Empangeni and Pinetown. The current transmission<br />
network and CLNs are shown in Figure 6.3 below.<br />
Figure 6.3: Current East Grid network and CLNs<br />
The expected area peak demands by <strong>2011</strong>, 2015 and <strong>2020</strong> and the average percentage load increase for the period<br />
for each CLN are given in Table 6 3 below.<br />
CLN<br />
Table 6.3: East Grid CLN load forecast and percentage load increase<br />
<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong><br />
Forecasted Load (MW) Ave. Annual %<br />
Load Increase<br />
<strong>2011</strong> 2016 <strong>2020</strong><br />
Ladysmith and Newcastle 1292 1390 1590 2.3 %<br />
Empangeni 2227 2308 2638 2.7%<br />
Pinetown 3515 3777 4490 3%<br />
The TDP scheme projects for the East Grid consist primarily of the strengthening of the 400kV networks that<br />
transmits power into Empangeni and Pinetown CLNs and the introduction of 765kV. In addition to the above<br />
TDP scheme projects, there are other projects that are listed in the project summary list which are required to<br />
strengthen the network.