6.1.4 VAAL CN<br />

This CLN consists of seven transmission substations and one power station supplying both residential and heavy<br />

industrial loads. The anticipated high load growth nodes are at Makalu and at Kookfontein MTS. The main projects in<br />

the Vaal CLN are as follows:<br />

Vaal Strengthening Phase 1 (Closing of the Hera-Bernina 275kV link)<br />

• Uprating of terminal equipment at Hera, Bernina,Taunus, Princess,Westgate, Glockner, Kookfontein,Verdun and<br />

Scafell S/S<br />

• Bernina S/S refurbishment<br />

• Glockner 3rd 400/275kV 800MVA transformer<br />

• Glockner 275kV Busbar replacement to tubular <strong>2011</strong><br />

Vaal Strengthening Phase 2 (Glockner-Etna 2x400kV lines operated at 275kV)<br />

• Glockner-Etna 1&2 400kV lines operated at 275kV<br />

• 2x 275kV lines bays at Glockner S/S<br />

• 2x 275kV lines bays at Etna S/S <strong>2011</strong><br />

Kookfontein Transformation Phase 1 strengthening involves the addition of 2 x 88kV 48 MVAR<br />

capacitor banks at Kookfontein substation. <strong>2011</strong><br />

Kookfontein Transformation Phase 2 strengthening involves the 3rd 275/88kV 315MVA transformer and<br />

3rd Glockner Kookfontein 275kV line (Customer dependent) 2015<br />

A network diagram showing the major projects in the Central Grid is shown in Figure 6.2 below:<br />

Figure 6.2: Central Grid network diagram<br />

© <strong>Eskom</strong> <strong>2011</strong> 19