Johannesburg East Strengthening continued<br />

• Phase 3 A-D: Jupiter B MTS Integration<br />

o Matla- Jupiter B 1&2 400kV (150km) operated at 275kV.<br />

o New Jupiter B MTS with 10x 275kV line bays and 275kV busbar (New 400/275kV MTS site<br />

required to contain 4x 400/275kV transformers)<br />

o Turn the Matla - Esselen 275kV line and Matla – Benburg 275kV line into Nevis MTS and<br />

disconnect section of Matla Nevis section of the Matla - Benburg and Matla - Esselen 275kV Line<br />

o Apollo - Esselen 3 400kV (12km) operated at 275kV.<br />

2014<br />

• Phase 3 E-F: Sebenza Integration 2017<br />

o New 400kV Sebenza MTS operated at 275kV.<br />

o Loop-in the Sebneza -Prospect 1 and 2 275kV line (loop-in built at 400kV) and Jupiter - Fordsburg<br />

275kV and Jupiter – Prospect 275kV line into Jupiter B MTS.<br />

o Construct 2x 400kV lines from North Rand to Sebenza MTS.<br />

Soweto Strengthening Phase 1 (built at 400kV, operated at 275kV)<br />

• Establish new Quattro MTS 275kV *busbar 2014<br />

• Build 2x 275kV Quattro-Etna 15km *lines 2014<br />

Soweto Strengthening Phase 2 (built at 400kV, operated at 275kV)<br />

• Establish Quattro 132kV yard with 2x500MVA 275/132kV transformers 2016<br />

Simmerpan MTS Strengthening – Phase 1(built at 400kV, operated at 275kV)<br />

• Construct 400kV Busbar operated at 275kV at new Simmerpan MTS 2015<br />

• Operate Jupiter –Simmerpan 1&2 88kV line at 275kV and connect 1st and<br />

2nd 275/88kV 160MVA 2015<br />

Simmerpan Strengthening – Phase 2 (built at 400kV, operated at 275kV)<br />

• Establish Simmerpan 132kV yard with 2x250MVA 275/132kV transformers 2016<br />

Kyalami 400kV Strengthening<br />

• Construct Kyalami 400/132kV GIS MTS 2014<br />

• Loop Kusile - Lulamisa 400kV line into Kyalami MTS<br />

(This is dependent on Kusile Integration)<br />

2014<br />

HVDC Terminal B<br />

• Establish an HVDC converter station close to Jupiter B MTS 2017<br />

• Build an 800kV HVDC line from Terminal B to Coal 3 via Selemo (Epsilon) 2017<br />

© <strong>Eskom</strong> <strong>2011</strong> 17