14<br />

6. Breakdown of the TDP Projects by Grid<br />

6.1 CENTRAL GRID<br />

The Central Grid consists of four customer load<br />

networks (CLNs), namely; Johannesburg, Vaal Triangle,<br />

West Rand and Nigel. The current transmission<br />

network and CLNs are shown in Figure 6 1 below.<br />

Figure 6.1: Current Central Grid network and CLNs<br />

Table 6.1: Current Central Grid network and CLNs<br />

<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong><br />

The expected peak CLN demands by <strong>2020</strong> and<br />

the average percentage load increase for the period<br />

for each CLN are given in Table 6.1 on the following<br />

page.