horizon of the TDP up until 2030. The objective of this<br />

strategic study was to align the transmission network<br />

with the requirements of the generation future options<br />

and the growing and future load centres. This Strategic<br />

Grid Study has enabled the 10- year TDP to be aligned<br />

with the future long-term development of the whole<br />

<strong>Eskom</strong> system.<br />

The addition of over 72 000 MVA of transformer capacity<br />

to the transmission system is an indication of both the<br />

increasing load demand and the increasing firm capacity<br />

requirements of the customers. Approximately 2 800 MVars<br />

of capacitive support are required to support areas<br />

of the network under contingency conditions to<br />

ensure that the required voltage levels are maintained.<br />

They also improve system efficiency by reducing<br />

network losses.<br />

Approximately 14 900 MVArs of reactors are a direct<br />

result of the long lengths of both 765kV and 400kV<br />

transmission lines that will be constructed over this<br />

period. There are also a number of series compensation<br />

projects required on the 765kV and 400kV lines<br />

required to improve the power transfer capability of<br />

the Cape power corridors.<br />

Two new SVCs are proposed to support the<br />

Northern Cape (West Grid) and the proposed Sishen-<br />

Saldanha Spoornet expansion, namely a +200/-100<br />

MVAr SVC at Aries and a smaller one of +45/-100<br />

MVars at Garona.<br />

Some projects have associated distribution projects to<br />

enable customers to benefit from them. For example,<br />

a new MTS substation may require distribution<br />

infrastructure to link it to the existing distribution<br />

network or to connect new bulk loads. Distribution<br />

infrastructure and individual feeder bays to connect<br />

distribution infrastructure or bulk loads are not<br />

reported on individually in this report.<br />