horizon of the TDP up until 2030. The objective of this<br />
strategic study was to align the transmission network<br />
with the requirements of the generation future options<br />
and the growing and future load centres. This Strategic<br />
Grid Study has enabled the 10- year TDP to be aligned<br />
with the future long-term development of the whole<br />
<strong>Eskom</strong> system.<br />
The addition of over 72 000 MVA of transformer capacity<br />
to the transmission system is an indication of both the<br />
increasing load demand and the increasing firm capacity<br />
requirements of the customers. Approximately 2 800 MVars<br />
of capacitive support are required to support areas<br />
of the network under contingency conditions to<br />
ensure that the required voltage levels are maintained.<br />
They also improve system efficiency by reducing<br />
network losses.<br />
Approximately 14 900 MVArs of reactors are a direct<br />
result of the long lengths of both 765kV and 400kV<br />
transmission lines that will be constructed over this<br />
period. There are also a number of series compensation<br />
projects required on the 765kV and 400kV lines<br />
required to improve the power transfer capability of<br />
the Cape power corridors.<br />
Two new SVCs are proposed to support the<br />
Northern Cape (West Grid) and the proposed Sishen-<br />
Saldanha Spoornet expansion, namely a +200/-100<br />
MVAr SVC at Aries and a smaller one of +45/-100<br />
MVars at Garona.<br />
Some projects have associated distribution projects to<br />
enable customers to benefit from them. For example,<br />
a new MTS substation may require distribution<br />
infrastructure to link it to the existing distribution<br />
network or to connect new bulk loads. Distribution<br />
infrastructure and individual feeder bays to connect<br />
distribution infrastructure or bulk loads are not<br />
reported on individually in this report.<br />