12<br />

A significant amount of new transmission lines is being<br />

added to the system with over 6,000 km of 765kV<br />

and over 8 000 km of 400kV lines either approved or<br />

proposed over the 10-year TDP period. This is mainly<br />

due to the major network reinforcements required for<br />

the supply to the Cape (South and West Grids) and<br />

Kwa Zulu Natal (East Grid). The integration of new<br />

power stations in the developing Limpopo West Power<br />

Pool (Medupi and Coal 3 close to Matimba and the IPP<br />

Mmamabula in Botswana) also require significant lengths<br />

of transmission line as they are very remote from the<br />

main load centres. New HVDC lines are required to<br />

export the excess power from Coal 3 in the Waterberg<br />

directly to load centres in Gauteng and Kwa Zulu Natal<br />

(Central and East Grids) requiring 1 700km of 800kV<br />

constructed HVDC lines.<br />

The large amount of 400kV transmission line is also as<br />

a result of a more meshed transmission 400kV network<br />

<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong><br />

TDP New Assets Total<br />

HVDC Lines (km)<br />

765kV Lines (km)<br />

400kV Lines (km)<br />

275kV Lines (km)<br />

Transformers 250MVA+<br />

Transformers