3.2 GENERATION ASSUMPTIONS<br />
The major change in the generation assumptions from<br />
the previous TDP is the inclusion of Wind Generation.<br />
The Coal 3 generation is still assumed to be in the<br />
Waterberg area, close to Medupi and in line with the<br />
current project development with the target date for<br />
the first units in 2016. The integration of the first units at<br />
Coal 3 will utilise the new Delta 765/400kV substation<br />
and the Delta-Epsilon lines will be energised at 765kV.<br />
4. Completed Projects Since Last TDP<br />
This chapter contains a list of projects completed<br />
since the last TDP. A project may consist of a number<br />
of sub-projects, which may be placed into commercial<br />
operation before the entire project is completed. This is<br />
done to ensure that the network and customers enjoy<br />
the benefits of the new assets as soon as practicable.<br />
4.1 COMPLETED GENERATION INTEGRATION<br />
PROJECTS<br />
According to the <strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> 2010-<br />
2019, some RTS power stations were anticipated to<br />
be completed in 2010. Parts of some of these projects<br />
have since been completed, and the resultant benefits<br />
are being realised. The completion status of the projects<br />
is as follows:<br />
Grootvlei RTS: generator bays 5 and 6 are still<br />
outstanding and completion is anticipated in the<br />
<strong>2011</strong>/12 financial year.<br />
Komati RTS: generator bays 4, 5, 6, 7, 8 and 9 are<br />
still outstanding, and completion is anticipated in the<br />
<strong>2011</strong>/12 financial year. Unit 3 was commissioned.<br />
4.2 UPDATE ON TRANSMISSION RELIABILITY<br />
This section discusses all the projects that were<br />
reflected in the <strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> 2010 2019<br />
It is proposed to implement two HVDC schemes with<br />
a HVDC converter station in the vicinity of Coal 3 to<br />
cater for the final configuration of six 750MW units.<br />
Coal 4 is assumed to be out of this TDP period.<br />
The HVDC lines will connect to HVDC rectifier terminal<br />
stations in Gauteng and Kwa Zulu Natal (Central and<br />
East Grids).<br />
Nuclear 1 is considered, as in the previous TDP, to be<br />
located at the Thuyspunt site.<br />
for commissioning in FY2010/11. Over and above that,<br />
there are other projects that were not mentioned<br />
in that plan (due to the fact that they were near<br />
completion) that have since been concluded.<br />
Central Grid<br />
The installation of the 3rd and 4th transformers at<br />
Lepini substation is completed.<br />
The transformers that were planned to be commissioned<br />
in 2010 were at Croydon, Eiger and Esselen substations.<br />
Esselen has been completed. Croydon and Eiger are<br />
outstanding.<br />
Western Grid<br />
There were no projects planned to be commissioned<br />
in 2010/11.<br />
East Grid<br />
The construction of the Majuba Umfolozi 400 kV (765<br />
kV design) is completed.<br />
The transformers that were planned to be commissioned<br />
in 2010 were at Hector and Eros substations. Both<br />
these projects have been completed.<br />
North East Grid<br />
The projects for the installation of additional<br />
© <strong>Eskom</strong> <strong>2011</strong> 9