3.2 GENERATION ASSUMPTIONS<br />

The major change in the generation assumptions from<br />

the previous TDP is the inclusion of Wind Generation.<br />

The Coal 3 generation is still assumed to be in the<br />

Waterberg area, close to Medupi and in line with the<br />

current project development with the target date for<br />

the first units in 2016. The integration of the first units at<br />

Coal 3 will utilise the new Delta 765/400kV substation<br />

and the Delta-Epsilon lines will be energised at 765kV.<br />

4. Completed Projects Since Last TDP<br />

This chapter contains a list of projects completed<br />

since the last TDP. A project may consist of a number<br />

of sub-projects, which may be placed into commercial<br />

operation before the entire project is completed. This is<br />

done to ensure that the network and customers enjoy<br />

the benefits of the new assets as soon as practicable.<br />

4.1 COMPLETED GENERATION INTEGRATION<br />

PROJECTS<br />

According to the <strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> 2010-<br />

2019, some RTS power stations were anticipated to<br />

be completed in 2010. Parts of some of these projects<br />

have since been completed, and the resultant benefits<br />

are being realised. The completion status of the projects<br />

is as follows:<br />

Grootvlei RTS: generator bays 5 and 6 are still<br />

outstanding and completion is anticipated in the<br />

<strong>2011</strong>/12 financial year.<br />

Komati RTS: generator bays 4, 5, 6, 7, 8 and 9 are<br />

still outstanding, and completion is anticipated in the<br />

<strong>2011</strong>/12 financial year. Unit 3 was commissioned.<br />

4.2 UPDATE ON TRANSMISSION RELIABILITY<br />

This section discusses all the projects that were<br />

reflected in the <strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> 2010 2019<br />

It is proposed to implement two HVDC schemes with<br />

a HVDC converter station in the vicinity of Coal 3 to<br />

cater for the final configuration of six 750MW units.<br />

Coal 4 is assumed to be out of this TDP period.<br />

The HVDC lines will connect to HVDC rectifier terminal<br />

stations in Gauteng and Kwa Zulu Natal (Central and<br />

East Grids).<br />

Nuclear 1 is considered, as in the previous TDP, to be<br />

located at the Thuyspunt site.<br />

for commissioning in FY2010/11. Over and above that,<br />

there are other projects that were not mentioned<br />

in that plan (due to the fact that they were near<br />

completion) that have since been concluded.<br />

Central Grid<br />

The installation of the 3rd and 4th transformers at<br />

Lepini substation is completed.<br />

The transformers that were planned to be commissioned<br />

in 2010 were at Croydon, Eiger and Esselen substations.<br />

Esselen has been completed. Croydon and Eiger are<br />

outstanding.<br />

Western Grid<br />

There were no projects planned to be commissioned<br />

in 2010/11.<br />

East Grid<br />

The construction of the Majuba Umfolozi 400 kV (765<br />

kV design) is completed.<br />

The transformers that were planned to be commissioned<br />

in 2010 were at Hector and Eros substations. Both<br />

these projects have been completed.<br />

North East Grid<br />

The projects for the installation of additional<br />

© <strong>Eskom</strong> <strong>2011</strong> 9