Potential imported power projects were treated as<br />

separate sensitivity analysis studies in the 20 year<br />

transmission strategic grid studies.<br />

Any promising imported power projects can then<br />

be included and incorporated in future TDP updates<br />

once a sufficient level of confidence in the timing and<br />

implementation is attained.<br />

Figure 2.2: Power station capacity introduction by year<br />

The proposed OCGT IPP plants to be provided by<br />

the Department of Energy (DOE) are not specifically<br />

included in the studies. However, the two known sites<br />

in the East and South Grids have been studied, and<br />

effectively, only the feeder bays at the relevant <strong>Eskom</strong><br />

MTS substations are required to integrate them into<br />

the network.<br />

These plants are designed for operation only during<br />

Assumed New Generation Capacity<br />

2010 TDP-<strong>Plan</strong><br />

New Generation summary<br />

A summary of the new plant and the year that the<br />

last unit at the power station becomes commercially<br />

available is given in Appendix A. These generation units<br />

were assumed to be in service at the expected dates.<br />

This is graphically illustrated in Figure 2 2 below and<br />

Figure 2 3 on the next page.<br />

peak load periods or during emergencies, making<br />

it necessary to plan the network to meet local load<br />

without them being available for use.<br />

It is also acknowledged that the Tubatse (or Lima)<br />

pumped-storage scheme project near Steelpoort has<br />

been put on hold, but most of the infrastructure will still<br />

be required for system reliability purposes in order to<br />

meet the needs of local loads.<br />