Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
Transmission Ten-Year Development Plan 2011-2020 - Eskom
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
of 100MW which represent a cumulative total of<br />
generation at that point. They are connected directly to<br />
the 132kV busbars of existing MTS substations.<br />
The four MTS substations are:<br />
• Juno (<strong>2011</strong>)<br />
• Proteus (<strong>2011</strong>)<br />
• Aurora (2012)<br />
• Bacchus (2012)<br />
In addition, it is assumed that the <strong>Eskom</strong> 100MW<br />
wind farm at Sere will also be established in <strong>2011</strong> and<br />
integrated as per the study proposal.<br />
Since these are intermittent sources of generation in<br />
the TDP studies, they are studied under two conditions,<br />
namely:<br />
• Zero output at system peak<br />
• Full output at system peak<br />
This is to determine the capacity and potential weakness<br />
under both generation conditions.<br />
It is acknowledged that significantly more wind<br />
generation may be connected to the network before<br />
<strong>2020</strong>. However, it is difficult to determine the exact<br />
transmission requirements for the TDP without the<br />
actual location and size of the wind farms. Taking into<br />
account that the normal average load factor of wind<br />
farms is of the order of 35%, this means that they will<br />
not have a significant impact on the capacity design of<br />
the network. The applications for wind farms will be<br />
handled on a case by case basis, but only the above<br />
allocated 500MW of wind generation has been included<br />
in the TDP studies.<br />
Moamba OCGT Generation<br />
The Moamba project is a proposed OCGT power<br />
station in Mozambique, situated approximately 30km<br />
from the South African border near Komatipoort.<br />
The power station will be integrated by looping in the<br />
existing 275kV line to the site. In addition, a new 60km<br />
400kV line energised at 275kV will be constructed from<br />
the Moamba site directly to the 400/275kV substation<br />
in Maputo. A new 275kV line (60km) between the<br />
Moamba site and the Infulene substation in Maputo is<br />
also proposed.<br />
The Moamba total capacity is 664MW, modelled as two<br />
332MW units. This will be a base load power station<br />
which will be run during system peak, but can be scaled<br />
down during low load conditions if required.<br />
Ingula pumped storage<br />
The Ingula pumped storage power station is an<br />
approved project which is assumed to have units 1 and<br />
2 completed in 2013 and units 3 and 4 completed in<br />
<strong>2011</strong> as per the project schedule.<br />
Base Load Coal<br />
The Base Load Coal power stations at Medupi and<br />
Kusile are approved projects; the new units of which<br />
are assumed to be completed between 2012 and 2017<br />
as per the project schedules and in line with the IRP.<br />
An additional base load coal power station is required,<br />
which is assumed to be the proposed Coal 3 power<br />
station at Lephalale, close to the Medupi site. The first<br />
unit will come on line in 2017 with an additional unit<br />
each year until there are 4 units by <strong>2020</strong>. This is in line<br />
with the IRP. The assumed size is 750MW units with a<br />
projected sent out power of 714MW per unit.<br />
Nuclear 1 Generation<br />
The Nuclear 1 site, selected for the purposes of the<br />
TDP, is the Thuyspunt site near Port Elizabeth. Although<br />
it is acknowledged that the site selection has not been<br />
completed, the Thuyspunt site is the preferred site from<br />
a transmission aspect. The initial unit size is assumed<br />
to be a 1500MW unit for the purposes of the TDP<br />
studies in line with the IRP assumption. Obviously, the<br />
integration requirements will change if a different site is<br />
selected, and may change if the size or the number of<br />
units change.<br />
© <strong>Eskom</strong> <strong>2011</strong> 5