20.01.2013 Views

Transmission Ten-Year Development Plan 2011-2020 - Eskom

Transmission Ten-Year Development Plan 2011-2020 - Eskom

Transmission Ten-Year Development Plan 2011-2020 - Eskom

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

of 100MW which represent a cumulative total of<br />

generation at that point. They are connected directly to<br />

the 132kV busbars of existing MTS substations.<br />

The four MTS substations are:<br />

• Juno (<strong>2011</strong>)<br />

• Proteus (<strong>2011</strong>)<br />

• Aurora (2012)<br />

• Bacchus (2012)<br />

In addition, it is assumed that the <strong>Eskom</strong> 100MW<br />

wind farm at Sere will also be established in <strong>2011</strong> and<br />

integrated as per the study proposal.<br />

Since these are intermittent sources of generation in<br />

the TDP studies, they are studied under two conditions,<br />

namely:<br />

• Zero output at system peak<br />

• Full output at system peak<br />

This is to determine the capacity and potential weakness<br />

under both generation conditions.<br />

It is acknowledged that significantly more wind<br />

generation may be connected to the network before<br />

<strong>2020</strong>. However, it is difficult to determine the exact<br />

transmission requirements for the TDP without the<br />

actual location and size of the wind farms. Taking into<br />

account that the normal average load factor of wind<br />

farms is of the order of 35%, this means that they will<br />

not have a significant impact on the capacity design of<br />

the network. The applications for wind farms will be<br />

handled on a case by case basis, but only the above<br />

allocated 500MW of wind generation has been included<br />

in the TDP studies.<br />

Moamba OCGT Generation<br />

The Moamba project is a proposed OCGT power<br />

station in Mozambique, situated approximately 30km<br />

from the South African border near Komatipoort.<br />

The power station will be integrated by looping in the<br />

existing 275kV line to the site. In addition, a new 60km<br />

400kV line energised at 275kV will be constructed from<br />

the Moamba site directly to the 400/275kV substation<br />

in Maputo. A new 275kV line (60km) between the<br />

Moamba site and the Infulene substation in Maputo is<br />

also proposed.<br />

The Moamba total capacity is 664MW, modelled as two<br />

332MW units. This will be a base load power station<br />

which will be run during system peak, but can be scaled<br />

down during low load conditions if required.<br />

Ingula pumped storage<br />

The Ingula pumped storage power station is an<br />

approved project which is assumed to have units 1 and<br />

2 completed in 2013 and units 3 and 4 completed in<br />

<strong>2011</strong> as per the project schedule.<br />

Base Load Coal<br />

The Base Load Coal power stations at Medupi and<br />

Kusile are approved projects; the new units of which<br />

are assumed to be completed between 2012 and 2017<br />

as per the project schedules and in line with the IRP.<br />

An additional base load coal power station is required,<br />

which is assumed to be the proposed Coal 3 power<br />

station at Lephalale, close to the Medupi site. The first<br />

unit will come on line in 2017 with an additional unit<br />

each year until there are 4 units by <strong>2020</strong>. This is in line<br />

with the IRP. The assumed size is 750MW units with a<br />

projected sent out power of 714MW per unit.<br />

Nuclear 1 Generation<br />

The Nuclear 1 site, selected for the purposes of the<br />

TDP, is the Thuyspunt site near Port Elizabeth. Although<br />

it is acknowledged that the site selection has not been<br />

completed, the Thuyspunt site is the preferred site from<br />

a transmission aspect. The initial unit size is assumed<br />

to be a 1500MW unit for the purposes of the TDP<br />

studies in line with the IRP assumption. Obviously, the<br />

integration requirements will change if a different site is<br />

selected, and may change if the size or the number of<br />

units change.<br />

© <strong>Eskom</strong> <strong>2011</strong> 5

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!