Chapter 5 deals with the national overview, which gives<br />
a high level explanation of the planned transmission<br />
infrastructure. This is intended to give a snapshot of the<br />
major projects that are planned for the entire <strong>Ten</strong>-year<br />
plan period and a high-level summary of the installed<br />
transmission infrastructure.<br />
Chapter 6 focuses on planned projects in detail and<br />
the impact they will have on the network. Generation<br />
integration and reliability projects are discussed per<br />
Grid. In both instances, sites and servitudes are required<br />
<strong>Transmission</strong> <strong>Ten</strong>-<strong>Year</strong> <strong>Plan</strong> <strong>2011</strong>-<strong>2020</strong><br />
to accommodate substations and lines respectively. In<br />
either case, the Environmental Protection Act requires<br />
<strong>Eskom</strong> to conduct an Environmental Impact Assessment<br />
(EIA) and obtain environmental approval, which includes<br />
consultation with affected stakeholders, prior to construction.<br />
Chapter 7 deals with the capital expenditure of the<br />
ten-year plan.<br />
Chapter 8 deals with various conclusions based on the<br />
content of this document.<br />
2. Load Demand Forecast and Generation Scenarios<br />
2.1 LOAD FORECAST<br />
Load forecasting is a fundamental requirement for a<br />
<strong>Transmission</strong> planning cycle. Availability of sufficient<br />
transmission network capacity in any country is<br />
important for economic growth. Grid <strong>Plan</strong>ning, in<br />
consultation with the relevant Distribution regions,<br />
compiles a forecast per point of supply for the network<br />
computer model.<br />
The geographically differentiated loads indicate that<br />
the growth rates and load profiles differ substantially<br />
from one substation or area to another. The forecast<br />
that was used for the <strong>2011</strong> – <strong>2020</strong> TDP (2010 TDP)<br />
was developed using the 2009 July System peak load.<br />
The effects of the economic crisis have resulted in a<br />
significant impact on the demand in late 2008 and early<br />
2009. Hence the load forecast presented in this report<br />
indicates relatively smaller system load demand as<br />
compared to the load forecast used in the 2010 – 2019<br />
TDP (2009 TDP). See Figure 2-1, on the next page, that<br />
illustrates the difference.<br />
Due to the long lead times and EIA requirements, the<br />
transmission planning studies were based on this load<br />
forecast to provide enough time to initiate the necessary<br />
transmission infrastructure projects. The forecasted<br />
system peak demand for each year is given in Figure 2<br />
1 on the next page including the percentage growth for<br />
each year for the latest forecast:.