6.10 Network development – summary of investment proposals and principal schemes (enhancement expenditure 1999/2000–2008/09)<br />
TYPE OF SCHEME ESTIMATED CAPITAL COST (£M)*<br />
In last year’s NMS<br />
Thameslink 2000 800<br />
WCRM PUG 1 and PUG 2 675<br />
Paddington Station enhancements 80<br />
Waterloo Station enhancements 22<br />
Freight enhancements 16<br />
Edinburgh Station enhancements 16<br />
London Victoria Station enhancements 11<br />
Luton Parkway new station 8<br />
Dartford resignalling 7<br />
Cardiff Central Station enhancements 5<br />
Other 127<br />
TOTAL 1767<br />
Commercial<br />
East Coast Main Line upgrade 750<br />
London–Stansted upgrade 130<br />
Southern link to Heathrow 100<br />
Manchester to Crewe capacity 100<br />
Virgin Trains CrossCountry journey-time and capacity 80<br />
Waterloo to Fawkham Junction enhancements for CTRL 65<br />
Manchester Piccadilly Station enhancements 21<br />
Freight routeing:Settle–Carlisle 15<br />
New freight depot Aberdeen (Raithes Farm) 8<br />
Midland Main Line journey-time improvements Phase 1 5<br />
Other 134<br />
TOTAL 1408<br />
*<strong>The</strong>se cost estimates vary in accuracy from firm prices through detailed design estimates to indicative<br />
feasibility assessments.<strong>The</strong> cost of each scheme will be refined as it is progressed.Total enhancement spend<br />
is based on a top-down estimate of the investment required to deliver 30% growth in passenger miles and<br />
a tripling of freight traffic by 2008/09.<strong>The</strong> schemes identified are those currently envisaged to deliver the<br />
majority of that growth.However, we would not expect the inclusion or exclusion of a specific scheme to<br />
affect the total enhancement required.<br />
TYPE OF SCHEME ESTIMATED CAPITAL COST (£M)*<br />
Partnership<br />
Northern access to Heathrow 450<br />
Freight routeing strategy 400<br />
East West Rail Link 240<br />
London commuter area capacity 200<br />
Freight gauging improvements 200<br />
Coventry–Birmingham capacity 200<br />
Brighton Main Line capacity 160<br />
Oldham Loop LRT 120<br />
Sheffield area capacity 100<br />
Central Manchester capacity 100<br />
Nuneaton–Walsall/Birmingham electrification 100<br />
Great Western Main Line journey-time improvements 70<br />
Glasgow Airport rail link 50<br />
North Trans-Pennine capacity 40<br />
ScotRail Express journey-time improvements 37<br />
Walsall–Rugeley electrification 35<br />
Tyne & Wear Metro extension to Sunderland 31<br />
West of England journey-time improvements 25<br />
Larkhall–Milngavie new service 24<br />
Manchester Airport capacity and interchange 23<br />
Merseyside electrification extension 15<br />
Rhymney Valley capacity 12<br />
Barmouth Viaduct weight limits 10<br />
Other 914<br />
TOTAL 3556<br />
Contractor<br />
Modern Facilities at Stations 1300<br />
Platform-stepping distance 900<br />
Disabled access improvements 300<br />
West Midlands reopening closed routes 75<br />
Colnbrook Euroterminal 22<br />
Merseyrail underground stations 19<br />
Old Oak Common depot enhancements 19<br />
Barrhead–Kilmarnock capacity 7<br />
Other 82<br />
TOTAL 2724<br />
Feasibility 100<br />
Third-party and unspecified or minor schemes 1145<br />
TOTAL 10700