6.10 Network development – summary of investment proposals and principal schemes (enhancement expenditure 1999/2000–2008/09)<br />

TYPE OF SCHEME ESTIMATED CAPITAL COST (£M)*<br />

In last year’s NMS<br />

Thameslink 2000 800<br />

WCRM PUG 1 and PUG 2 675<br />

Paddington Station enhancements 80<br />

Waterloo Station enhancements 22<br />

Freight enhancements 16<br />

Edinburgh Station enhancements 16<br />

London Victoria Station enhancements 11<br />

Luton Parkway new station 8<br />

Dartford resignalling 7<br />

Cardiff Central Station enhancements 5<br />

Other 127<br />

TOTAL 1767<br />

Commercial<br />

East Coast Main Line upgrade 750<br />

London–Stansted upgrade 130<br />

Southern link to Heathrow 100<br />

Manchester to Crewe capacity 100<br />

Virgin Trains CrossCountry journey-time and capacity 80<br />

Waterloo to Fawkham Junction enhancements for CTRL 65<br />

Manchester Piccadilly Station enhancements 21<br />

Freight routeing:Settle–Carlisle 15<br />

New freight depot Aberdeen (Raithes Farm) 8<br />

Midland Main Line journey-time improvements Phase 1 5<br />

Other 134<br />

TOTAL 1408<br />

*<strong>The</strong>se cost estimates vary in accuracy from firm prices through detailed design estimates to indicative<br />

feasibility assessments.<strong>The</strong> cost of each scheme will be refined as it is progressed.Total enhancement spend<br />

is based on a top-down estimate of the investment required to deliver 30% growth in passenger miles and<br />

a tripling of freight traffic by 2008/09.<strong>The</strong> schemes identified are those currently envisaged to deliver the<br />

majority of that growth.However, we would not expect the inclusion or exclusion of a specific scheme to<br />

affect the total enhancement required.<br />

TYPE OF SCHEME ESTIMATED CAPITAL COST (£M)*<br />

Partnership<br />

Northern access to Heathrow 450<br />

Freight routeing strategy 400<br />

East West Rail Link 240<br />

London commuter area capacity 200<br />

Freight gauging improvements 200<br />

Coventry–Birmingham capacity 200<br />

Brighton Main Line capacity 160<br />

Oldham Loop LRT 120<br />

Sheffield area capacity 100<br />

Central Manchester capacity 100<br />

Nuneaton–Walsall/Birmingham electrification 100<br />

Great Western Main Line journey-time improvements 70<br />

Glasgow Airport rail link 50<br />

North Trans-Pennine capacity 40<br />

ScotRail Express journey-time improvements 37<br />

Walsall–Rugeley electrification 35<br />

Tyne & Wear Metro extension to Sunderland 31<br />

West of England journey-time improvements 25<br />

Larkhall–Milngavie new service 24<br />

Manchester Airport capacity and interchange 23<br />

Merseyside electrification extension 15<br />

Rhymney Valley capacity 12<br />

Barmouth Viaduct weight limits 10<br />

Other 914<br />

TOTAL 3556<br />

Contractor<br />

Modern Facilities at Stations 1300<br />

Platform-stepping distance 900<br />

Disabled access improvements 300<br />

West Midlands reopening closed routes 75<br />

Colnbrook Euroterminal 22<br />

Merseyrail underground stations 19<br />

Old Oak Common depot enhancements 19<br />

Barrhead–Kilmarnock capacity 7<br />

Other 82<br />

TOTAL 2724<br />

Feasibility 100<br />

Third-party and unspecified or minor schemes 1145<br />

TOTAL 10700