Table A Enhancement expenditure (£M – 1998/99 prices)<br />

TYPE OF ASSET 1998/99 1999/2000 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09<br />

Track 40 70 150 510 360 420 260 180 180 170 120<br />

Structures 30 40 50 260 460 390 180 130 180 160 130<br />

Signalling 30 45 80 230 350 290 240 180 150 130 140<br />

Electrification 10 60 60 120 120 130 80 25 20 35 55<br />

Plant & Machinery 5 20 10 10 10 10 10 0 0 0 0<br />

Telecoms 10 10 5 0 10 10 0 0 0 0 0<br />

Stations 160 170 135 390 420 440 380 525 425 320 320<br />

Depots 20 20 5 10 15 0 0 0 0 0 0<br />

Other 5 5 5 10 15 20 10 0 0 5 5<br />

TOTAL 310 440 500 1540 1760 1710 1160 1040 955 820 770<br />

1998 NMS 130 220 530 430 530 420 320 180 210 220 n/a<br />

Table B Network development packages (1999/2000–2008/09)<br />

F e a s i b i l i t y, third-party and other unspecified or minor schemes<br />

Package 3 – Contractor<br />

<strong>The</strong>se schemes are generally unsuitable for us to take any demand risk,<br />

although we would take appropriate construction risk.Many of these<br />

projects are station schemes .<br />

Package 2 – Partnership<br />

<strong>The</strong>se are also schemes where we wish to take demand risk but they<br />

require agreement with a funder for ‘pump priming’investment before they<br />

can proceed.<br />

Package 1 – Commercial<br />

<strong>The</strong>se are schemes that do not require public sector funding and in which we<br />

have sufficient control of the outputs to be able to take long-term demand<br />

risk.<strong>The</strong>y require no up-front agreement with any public sector body – other<br />

than understanding of their treatment for regulatory purposes .<br />

Committed in last year’s NMS<br />

<strong>The</strong>se are schemes that have yet to be completed but which were firmly<br />

committed in last year’s NMS.<br />

Renewals expenditure<br />

Maintenance expenditure<br />

£6.3bn £10.1bn £1.8bn £1.4bn £3.6bn £2.7bn £1.2bn TOTAL £27.1bn (at 1998/99 prices)<br />

75