Renewals expenditure to deliver the programme of route improvements (£M – 1998/99 prices)<br />

PROGRAMME OF WORK 1998/99 1999/2000 2000/01 2001/02–2005/06 REF<br />

Track 1.8 1.4 1.1 9.2<br />

Signalling 0.2 0.7 0.2 4.3<br />

Plant & Machinery 0.0 0.0 0.0 2.5<br />

Telecoms 0.0 0.2 0.2 5.3<br />

Stations 0.0 4.2 4.2 1.6<br />

Depots 0.0 0.0 0.0 0.8<br />

TOTAL EXPENDITURE 2.0 6.5 5.7 23.7<br />

Enhancement expenditure on schemes to achieve the route vision (£M – 1998/99 prices)<br />

PROGRAMME OF WORK COMPLETION 1998/99 1999/2000 2000/01 2001/02–2005/06 CRR REF<br />

COMMITTED<br />

Station enhancements 2001 0.0 0.4 0.4 0.1<br />

CONTR<strong>AC</strong>TOR<br />

Mallaig turntable 2000 0.0 0.3 0.1 0.0 1<br />

Fort William turntable 2000 0.0 0.1 0.0 0.0<br />

THIRD PARTY<br />

Beauly Station reopening 2000 0.0 0.1 0.0 0.0 1<br />

Other schemes Various 0.0 0.0 0.0 0.4<br />

TOTAL RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 0.0 0.4 0.4 0.5 2<br />

TOTAL NON-RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 0.0 0.5 0.1 0.0<br />

Other route developments<br />

LOCATION PROPOSEDSOLUTION YEAR REF<br />

New station at Beauly Upgrade to the disused station providing facilities to meet a specific need 1999<br />

Improved carriage washing at Inverness New washing plant 2001/02<br />

Improved security and safety at specific stations – Upgrade lighting 2000/01<br />

Mallaig, Oban, Kyle of Lochalsh, Thurso and Wick Enhance customer-information systems<br />

Improved station facilities at stations detailed above Improvements to waiting rooms and toilet facilities 2000/01<br />

Progress on the 1998 NMS<br />

SIGNALLING Signalling equipment at Georgemas Junction has been installed,<br />

enabling the train driver to operate the equipment. This has efficiency benefits<br />

and reduces the journey time to Thurso and Wick.<br />

PLANT AND ELECTRICAL New and improved points heaters have been<br />

installed at junctions and loops, giving improved reliability and performance during<br />

periods of cold weather.<br />

STRUCTURES <strong>The</strong> route has a higher-than-average number of structures often<br />

built to support the railway through difficult terrain. Much regular and routine<br />

work has taken place over the year including waterproofing of bridges over<br />

Altnafael River and the Corriemollie Burn. In addition, linings to Leachabudhe<br />

Tunnel were renewed, together with the portals.<br />

STATIONS <strong>The</strong> SRP has continued with 49 stations completed by the end of<br />

March. Regeneration work has been carried out by Railtrack, but only after full<br />

consultation and agreement over the scope of work, with ScotRail and the<br />

relevant local authority. Agreement has recently been reached to open a new<br />

station at Beauly in the next 12 months. ScotRail has, in addition, taken the<br />

opportunity to carry out additional work at its own cost at the same time.<br />

Working in partnership has minimised the extent of disruption to the travelling<br />

public.<br />

FREIGHT A new siding has been constructed and brought into use at Kyle of<br />

Lochalsh. Other mothballed facilities have been brought back into use. Lineside<br />

loading facilities for timber traffic have been introduced.<br />

Two temporary Rail Development Officers’ posts have been created by the<br />

local authority, jointly funded by local government and the rail industry covering<br />

the West Highlands and the North Highlands, respectively.<br />

A<br />

A<br />

B<br />

B<br />

C<br />

327