20.01.2013 Views

R A I LT R AC K - The Railways Archive

R A I LT R AC K - The Railways Archive

R A I LT R AC K - The Railways Archive

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Examples of significant work<br />

Woking–Surbiton area resignalling. Work on renewal of signalling equipment and track-layout changes will be completed during 1999.<br />

Manchester Victoria. <strong>The</strong> renewal of infrastructure at Manchester Victoria,including state-of-the-art signalling,remodelling of the track layout and reconstruction works on five bridge<br />

structures,was completed during 1998.<strong>The</strong> modernisation of the layout has significantly improved the operational efficiency of the Manchester north network.<br />

<strong>LT</strong>S route overhead-line renewal. <strong>The</strong> refurbishment of the overhead-line equipment on the <strong>LT</strong>S route was completed during 1998.New engineering solutions were introduced in the<br />

project which reduced the time required to undertake the work.<br />

Yorkshire signalling renewals. Work was completed in 1998 on this project of signalling rationalisation to increase signal-box efficiency by concentrating activities in fewer upgraded<br />

locations.<br />

Forth Bridge. We remain committed to the significant maintenance required to this historic bridge. We have greatly increased the volume of repairs and painting work to bring the bridge up<br />

to a condition that will allow a more efficient steady-state maintenance regime to be carried out thereafter.<br />

Stations completed<br />

Aberdeen. Roof repairs at Aberdeen have now been completed.<br />

Folkestone Central. A major programme of station refurbishment,track and platform rationalisation was completed in 1998.<br />

Stirling. Work was completed on installing lifts to improve station access.<strong>The</strong> station received an Ian Allan Heritage Highly Recommended Award.<br />

Manchester Oxford Road. Regeneration work at this station has recently been completed.<br />

Stations in progress<br />

Brighton. <strong>The</strong> three-year multimillion pound programme to refurbish this station is proceeding according to plan.<br />

Newcastle. Work is well progressed to refurbish the station roof and buildings.<br />

Birmingham New Street. <strong>The</strong> £19M package of station improvements,including enhanced platform ambience, disabled access and fire and safety precautions is progressing according to plan.<br />

Manchester Piccadilly. Work is ongoing on the £27M project to enhance the lighting and reroof the main trainshed.<br />

Schemes completed<br />

Chiltern Route improvements. <strong>The</strong> double track between Princes Risborough and Bicester has now been reinstated which has enabled Chiltern Trains to expand its timetable .<br />

Robin Hood Line Phase 3. Work is complete and services started in June 1998.<br />

Track layout at Manchester Piccadilly. Remodelling work completed at Christmas/New Year has increased to 12 the number of operational platforms in the main part of the station.<br />

Leeds–area infrastructure. Ahead of the major resignalling and capacity enhancements set out in this NMS,a new platform has been constructed to increase capacity.<br />

Merseyrail stations. Two new stations sponsored by Merseytravel have opened at Conway Park,an underground station serving an area of urban renewal in Birkenhead and Brunswick.<br />

Taff Vale resignalling. Phases 1 and 2 are complete . Renewal of signalling between Radyr and Pontypridd has delivered capacity and linespeed improvements.A turnback facility at Taff Wells<br />

has been completed.<br />

Schemes in progress<br />

West Coast Main Line Route modernisation. An ongoing programme to deliver the core investment plan,and the enhancements required for the passenger service upgrades<br />

(PUG 1 and 2) is now under way.<br />

Thameslink 2000. Preparatory statutory planning and development of commercial arrangements have been undertaken.<br />

Dartford resignalling. Signalling renewal and track-layout changes to facilitate eventual operation of 12-vehicle trains is being undertaken.<strong>The</strong> scheme will be substantially complete in 2001.<br />

Guildford resignalling. Work continues to renew the signalling equipment, rationalise control and improve the track layout.<strong>The</strong> scheme is due to be completed later this year.<br />

Scottish signalling renewals. This is driven by the need to renew signalling equipment and enhance capacity covering Glasgow Queen Street–Greenhill via Lenzie and Cumbernauld and<br />

Cowlairs–Maryhill.Completion is planned for this summer.<br />

Ipswich–Felixstowe. An upgrade of route capacity to handle more frequent train movements is under way and will be completed in 1999.<br />

Luton Airport Station. A major new station also creating a park-and-ride facility within 2km of the M1 is nearing completion.<br />

31

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!