Renewals expenditure to deliver the programme of route improvements (£M – 1998/99 prices)<br />

PROGRAMME OF WORK 1998/99 1999/2000 2000/01 2001/02–2005/06 REF<br />

Track 6.3 6.9 5.5 23.5<br />

Structures 3.5 1.0 1.7 12.2<br />

Signalling 15.3 1.2 1.6 16.5<br />

Electrification 0.0 0.1 0.0 0.0<br />

Plant & Machinery 0.4 0.0 0.0 0.0<br />

Telecoms 0.1 0.2 0.0 2.6<br />

Stations 0.0 6.6 4.2 0.0<br />

Other 0.1 0.1 0.0 0.0<br />

TOTAL EXPENDITURE 25.7 16.1 13.0 54.8<br />

Enhancement expenditure on schemes to achieve the route vision (£M – 1998/99 prices)<br />

PROGRAMME OF WORK COMPLETION 1998/99 1999/2000 2000/01 2001/02–2005/06 CRR REF<br />

COMMITTED<br />

MVAIR 1998 14.6 0.0 0.0 0.0<br />

Station enhancements 2001 0.0 2.7 1.2 0.0<br />

PARTNERSHIP<br />

North Trans-Pennine gauge enhancement 2005 0.0 0.0 0.0 3.1 1<br />

Oldham Loop LRT conversion 2000 0.0 0.3 0.0 0.0 1<br />

CONTR<strong>AC</strong>TOR<br />

Car parks at various locations 2009 0.1 0.1 0.1 0.5 1<br />

THIRD PARTY<br />

New stations & major refurbishments 2001 2.9 0.0 0.0 0.0 1<br />

Other schemes Various 0.0 0.0 0.1 0.7 10<br />

TOTAL RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 14.7 2.8 1.3 0.8 14<br />

TOTAL NON-RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 2.9 0.3 0.1 3.5<br />

Progress on the 1998 NMS<br />

MANCHESTER VICTORIA AREA INFRASTRUCTURE RENEWALS <strong>The</strong><br />

£50M scheme to improve the track layout and signalling was commissioned in<br />

summer 1998. During the works, up to 250 personnel were involved on site<br />

each day, tackling the closure of ten signal boxes and creating a new replacement<br />

signalling centre at Salford Crescent. Additional improvements included the<br />

installation of new telecommunications for faster signalling information, the<br />

remodelling of track layouts to improve operational flexibility and train regulation,<br />

continuously welded rail for improved ride quality and reduced maintenance, and<br />

£500,000 of new palisade fencing, helping to protect the railway from trespass<br />

and vandalism.<br />

S TATION REGENERATION Southport Station Phase 1 is complete. Further<br />

work, on the station roof, is being evaluated.<br />

Works have also been completed at Blackpool North, Bolton and Rochdale,<br />

together with several smaller stations, including improvements made to stations<br />

on the Glossop Line.<br />

H O RWICH PA R K WAY Work is on site with an anticipated opening in May this<br />

year. This is a new park-and-ride facility adjacent to the M61 and is linked to the<br />

adjacent retail park and sports stadium.<br />