Renewals expenditure to deliver the programme of route improvements (£M – 1998/99 prices)<br />

PROGRAMME OF WORK 1998/99 1999/2000 2000/01 2001/02–2005/06 REF<br />

Track 3.5 0.6 0.4 2.0<br />

Structures 1.2 1.5 1.1 7.7<br />

Signalling 0.9 0.6 0.4 2.7<br />

Plant & Machinery 0.0 0.0 0.1 0.2<br />

Telecoms 0.1 0.0 0.0 0.5<br />

Stations 2.9 0.5 0.2 4.2<br />

Depots 0.0 0.0 0.0 0.0<br />

TOTAL EXPENDITURE 8.6 3.4 2.2 17.3<br />

Enhancement expenditure on schemes to achieve the route vision (£M – 1998/99 prices)<br />

PROGRAMME OF WORK COMPLETION 1998/99 1999/2000 2000/01 2001/02–2005/06 CRR REF<br />

COMMITTED<br />

Taff Vale resignalling enhancements 1999 4.1 0.0 0.0 0.0<br />

Station enhancements 2001 0.0 0.0 0.0 0.0<br />

PARTNERSHIP<br />

Rhymney Valley modernisation 2002 0.0 0.0 0.0 12.0<br />

Cardiff Valley Queen Street – central corridor upgrade (E) 2003 0.0 0.0 1.0 8.0<br />

Taff Vale North modernisation 2002 0.0 0.0 0.2 0.6<br />

CONTR<strong>AC</strong>TOR<br />

Mountain Ash diversion – land reclamation and new loop (E) 2002 0.0 0.3 1.0 1.8<br />

Cardiff CIS 2001 0.0 0.1 0.9 0.0<br />

THIRD PARTY<br />

Improved station facilities 2004 0.0 0.0 0.0 1.2<br />

Other schemes Various 0.2 1.1 0.0 1.7 66<br />

TOTAL RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 0.0 0.2 1.0 0.1 66<br />

TOTAL NON-RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 4.3 1.3 2.1 25.2<br />

Progress on the 1998 NMS<br />

SIGNALLING We completed work on Radyr, Pontypridd and Porth track, and<br />

signalling renewals (Taff Vale Phase 2) in October 1998.<br />

We are completing a feasibility study on Pontypridd–Aberdare–Merthyr<br />

Tydfil resignalling by March 2000.<br />

To improve reliability, we have equipped 22 point-ends with new electri c<br />

h e a t e rs, and conve rted heaters on four point-ends from gas to electric opera t i o n .<br />

STATIONS We have completed 46 stations under the SRP. We have improved<br />

disabled access at Porth and will install improved facilities to ensure security of<br />

passengers in many Valleys stations during 1999/2000. We will complete a major<br />

refurbishment of Pontypridd Station and improvements to the station forecourt<br />

to enhance interchange facilities this year.<br />

RHYMNEY VALLEY We have completed the feasibility study into Rhymney<br />

Valley improvements, and SWIFT has applied for funding for the full scheme.<br />

CARDIFF QUEEN STREET–CARDIFF CENTRAL We are due to complete a<br />

study into options for increasing capacity between Cardiff Queen Street and<br />

Cardiff Central by March this year.<br />

LRT We will consider options to accommodate a possible light rapid transit<br />

system.<br />

A<br />

D E<br />

B<br />

C<br />

F<br />