Renewals expenditure to deliver the programme of route improvements (£M – 1998/99 prices)<br />

PROGRAMME OF WORK 1998/99 1999/2000 2000/01 2001/02–2005/06 REF<br />

Track 10.1 11.6 7.1 54.9<br />

Structures 6.8 5.2 5.9 40.7<br />

Signalling 22.3 6.5 14.7 54.2<br />

Electrification 2.5 1.0 1.0 16.8<br />

Plant & Machinery 1.1 0.3 0.2 1.0<br />

Telecoms 1.3 4.5 5.4 8.7<br />

Stations 11.7 11.5 7.1 44.5<br />

Depots 0.7 1.8 2.2 10.0<br />

Other 0.4 0.2 0.2 1.1<br />

TOTAL EXPENDITURE 56.9 42.6 43.8 231.9<br />

Enhancement expenditure on schemes to achieve the route vision (£M – 1998/99 prices)<br />

PROGRAMME OF WORK COMPLETION 1998/99 1999/2000 2000/01 2001/02–2005/06 CRR REF<br />

COMMITTED<br />

Waterloo Station enhancements 2007 0.0 1.5 1.0 14.2<br />

Station and depot enhancements 2001 3.0 0.7 5.3 0.0<br />

SWT CD/RA indicators 1999 0.8 0.0 0.0 0.0<br />

Thameslink 2000 2006 0.0 0.0 0.0 0.1<br />

COMMERCIAL<br />

Suburban capacity improvements 2001 0.0 0.0 0.0 5.5 2<br />

Waterloo Station retail reconfiguration 2000 0.0 1.7 0.0 0.0<br />

CONTR<strong>AC</strong>TOR<br />

Waterloo Station automatic ticket gates 2000 0.0 1.5 0.0 0.0 1<br />

SWT car-park enhancements 2000 0.5 1.0 0.0 0.0 1<br />

CIS enhancements 2001 0.0 0.0 0.0 1.0 2<br />

Wimbledon Depot Class 458 enhancements 2000 0.5 0.4 0.0 0.0<br />

THIRD PARTY<br />

Dibden Bay development 2004 0.0 0.0 0.0 0.5<br />

Other schemes Various 0.6 0.6 0.2 3.3 9<br />

TOTAL RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 5.4 7.3 6.5 23.8 15<br />

TOTAL NON-RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 0.0 0.1 0.0 0.8<br />

Progress on the 1998 NMS<br />

SIGNALLING <strong>The</strong> signalling renewal scheme in the Guildford area was<br />

substantially completed in December 1998.<br />

Reassessment of the condition of the signalling equipment in the<br />

Portsmouth, Havant, Basingstoke and Farnborough areas has concluded that<br />

resignalling is unnecessary until after 2004. Some investment in life extension of<br />

the existing systems will be undertaken in the short term.<br />

Development of the scheme to renew signalling in the Bournemouth area is<br />

continuing. Work will begin in 1999, with completion due in 2001.<br />

FREIGHT We are is actively supporting Associated British Ports with its<br />

proposed development of a deep-water port at Dibden Bay, which will be linked<br />

with the rail network.<br />

STATIONS A complete refurbishment of Surbiton Station is under way, which is<br />

restoring this station to its former glory. This has led to this station being<br />

awarded Station Regeneration of the Year by the Railway Heritage Trust.<br />

At Clapham Junction, Phase 1 SRP work on the canopies and platforms has<br />

been completed. Phase 2 works, which are due to start in 2000, involve<br />

refurbishment or replacement of the station footbridge.<br />

Work has just begun at Bournemouth Station, where up to £7M will be<br />

spent on the provision on a new station roof to replace the existing badly<br />

damaged structure. <strong>The</strong> new roof is based on the original William Jacumb design,<br />

amended to comply with modern safety requirements. This work is scheduled for<br />

completion in 2000.<br />