Renewals expenditure to deliver the programme of route improvements (£M – 1998/99 prices)<br />

PROGRAMME OF WORK 1998/99 1999/2000 2000/01 2001/02–2005/06 REF<br />

Track 6.6 1.1 1.1 17.2<br />

Structures 6.1 2.1 3.1 14.0<br />

Signalling 10.5 19.3 6.0 47.4<br />

Electrification 1.7 3.2 1.9 10.1<br />

Plant & Machinery 0.3 0.3 0.1 0.8<br />

Telecoms 1.7 1.8 1.0 6.0<br />

Stations 2.4 4.1 2.9 10.0<br />

Depots 0.1 3.7 0.5 10.0<br />

Other 0.1 0.1 0.2 0.8<br />

TOTAL EXPENDITURE 29.5 35.7 16.8 116.3<br />

Enhancement expenditure on schemes to achieve the route vision (£M – 1998/99 prices)<br />

PROGRAMME OF WORK COMPLETION 1998/99 1999/2000 2000/01 2001/02–2005/06 CRR REF<br />

COMMITTED<br />

Dartford resignalling enhancements 2001 2.7 4.4 0.9 1.8 1<br />

Station and depot enhancements 2001 0.4 1.3 1.4 0.0<br />

COMMERCIAL<br />

Waterloo–Fawkham Junction enhancements for CTRL 2003 0.7 5.5 10.5 13.0 3<br />

PARTNERSHIP<br />

Charlton millennium works 1999 0.0 1.0 0.0 0.0 1<br />

CONTR<strong>AC</strong>TOR<br />

Greenhithe Station development 1999 0.0 0.8 0.0 0.0 1<br />

THIRD PARTY<br />

Holborough reinstated connection 2002 0.0 0.0 1.5 1.5<br />

Northfleet freight siding 2004 0.0 0.0 0.0 0.5<br />

Other schemes Various 0.2 0.0 0.0 1.6 4<br />

TOTAL RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 4.0 13.0 12.8 14.9 10<br />

TOTAL NON-RAI<strong>LT</strong>R<strong>AC</strong>K EXPENDITURE 0.0 0.0 1.5 3.5<br />

Progress on the 1998 NMS<br />

DARTFORD-AREA SIGNALLING RENEWAL Work is progressing with<br />

completion scheduled for 2001.<br />

KINGSFERRY BRIDGE Strengthening and refurbishment works have been<br />

completed.<br />

LINESPEED IMPROVEMENTS We are undertaking a number of studies<br />

examining the feasibility of linespeed improvements between Swanley and<br />

Ramsgate via Faversham.<br />

STATIONS Station regeneration works have been completed at Crayford,<br />

Belvedere, Chatham, Dartford, Canterbury East, Dover Priory and Ramsgate.<br />

Customer-information systems at all Connex franchised stations are being<br />

improved through a Railtrack and Connex partnership scheme.<br />

MILLENNIUM DOME <strong>AC</strong>CESS Major works are planned to enhance station<br />

facilities at Charlton, which is the chosen railhead for the Millennium Dome.<br />

This station will provide an interchange for bus services to the site.<br />

EAST KENT & MEDWAY VALLEY SIGNALLING RENEWAL Reassessment of the<br />

condition of the signalling equipment in the East Kent & Medway Valley areas has<br />

concluded that life-extension works will enable resignalling to be postponed<br />

beyond 2004.<br />

ANGERSTEIN & HITHER GREEN RESIGNALLING We have carried out detailed<br />

condition assessments in the Angerstein & Hither Green areas and have<br />

concluded that renewal work will need to be undertaken in the Hither Green<br />

area by 2001. Replacement of the signalling interlocking at Angerstein is also<br />

scheduled for 2001.<br />