Progress on the 1998 NMS<br />

RELIABILITY AND OPERABILITY Equipment reliability and minor signalling<br />

enhancements between Paddington and Airport Junction, and in the Bristol area<br />

have started and will continue through 1999/2000. Relaying track and structural<br />

repairs in the Severn Tunnel started in 1998/99 and will continue in 1999/2000.<br />

STATION REFURBISHMENT Cardiff Central is undergoing major refurbishment,<br />

due for completion in1999/2000. Improvements at Paddington, including<br />

extensive rebuilding of the main concourse area are due for completion in late<br />

1999, with improved vehicle access due to follow in 2002/03. Hayes Station will<br />

be developed as a major interchange for Heathrow Airport. In partnership with<br />

Reading Council and our customers, a feasibility study has been commissioned to<br />

evaluate commercial development of Reading Station with improved transport<br />

interchange. Swindon Station redesign is planned for completion in 2001/02,<br />

subject to a partnership package. A scheme for the complete rebuilding of Bristol<br />

Parkway in 2000 is currently at feasibility stage. A partnership development will<br />

significantly improve facilities at Bristol Temple Meads. Installation of improved<br />

customer access and customer-information systems continues at many stations, in<br />

partnership with train operators. <strong>The</strong> Station Regeneration Programme is<br />

scheduled for completion in 1999/2000. A new London–Penzance motorail<br />

service will come into operation from summer this year, following completion of<br />

works at Paddington.<br />

FREIGHT AND MAIL DEPOTS A new freight terminal at South Marston is due<br />

for completion in 1999/2000, and the Royal Mail Depot at Bristol Parkway and<br />

European railfreight terminals at Wentloog and Avonmouth are due to be<br />

completed in 2000/01. We are assessing the feasibility of clearing the route from<br />

Willesden Junction to Cardiff to W10 by 2003/04, subject to funding.<br />

LAYOUT A<strong>LT</strong>ERATIONS are under way at Reading, and Phase 1 is due for<br />

completion April 1999. Phase 2 work is being developed and will include<br />

expansion of platform capacity and remodelling at Reading to improve access<br />

from the west. Swindon and Bristol Temple Meads remodelling has been<br />

deferred until 2002/03. Newport layout alterations have been deferred pending<br />

major resignalling.<br />

NEW STATIONS A new parkway station at Reading called Thames Valley Park is<br />

now planned for 2000/01. External funding for a new station at Grove near<br />

Didcot has not been forthcoming. A new station at Magor will be evaluated once<br />

development of the theme park is clear.<br />

165