West Coast Main Line: London to Glasgow and Edinburgh continued<br />
Our WCML upgrade scheme<br />
ISSUE LOCATION COMMENTS CHANGES TO SCHEME SINCE 1998 NMS<br />
Layout remodelling Euston–Camden Work has started on site <strong>The</strong> grade-separated junction at<br />
Renewal of track and signalling Camden Junction is not required<br />
Upgrading of low-level goods lines to passenger status and provide Willesden area Detailed design now starting<br />
turnback facility. New crossovers on low-level lines to slow lines at<br />
Brent Junction<br />
New crossovers providing direct access from the WCML to and Willesden–Brent Outline design complete <strong>The</strong> installation of the new crossovers<br />
from Acton Canal Wharf Junction has been deferred until we have an agreed<br />
understanding with customers on the<br />
services which would use this junction<br />
Replacement of the double junction with a single lead junction Willesden North Junction Junction has just been renewed We have concluded that this was the most<br />
like-for-like appropriate option<br />
Track remodelling Watford Junction Feasibility study started Change to the service specification has<br />
removed the need for a passing loop on<br />
the slow line<br />
Remove junctions at Hemel Hempstead and Tring South Bourne End Feasibility study started New replacement junction now required<br />
Remodelling to introduce a centre turnback siding Tring Feasibility study started Change to the service specification has<br />
removed the need for a passing loop on<br />
the slow line<br />
Removal of junction Ledburn Junction Feasibility study started N ow to be retained as a high-speed junction<br />
Remodelling of the sidings and freight loops Bletchley Feasibility study started<br />
at the south junction with a single ladder<br />
Remodelling to introduce a centre turnback facility Milton Keynes Central Feasibility study started<br />
Provide additional platforms and facilities Rugby Feasibility study started<br />
Provide new down slow Rugby–Brinklow Feasibility study started<br />
Provide grade-separated junctions Nuneaton Feasibility study started Several options are under development<br />
New slow lines to Armitage, reordering thence Lichfield–Colwich Feasibility study started<br />
Track layout changes Crewe Feasibility study started<br />
Two freight loops Rugby–Coventry Feasibility study started<br />
Remodel junction to improve capacity and reliability Proof House Junction Detailed design work<br />
now starting<br />
Resignalling & remodelling Cheadle Hulme– Feasibility study under way<br />
Slade Lane Junction<br />
Remodelling connections to platforms 9, 10, 11 & 12 Manchester Piccadilly Scheme completed<br />
Resignalling replacing worn out equipment, and signals Meaford Crossing– Feasibility study under way<br />
respaced for 125mph running Macclesfield<br />
Introduction of Network Management Centres Defined sections Software design & development<br />
contract let<br />
Renewal of overhead-line equipment Defined sections Tender evaluation under way<br />
Power supplies renewal Whole route Feasibility study under way<br />
Abolition of foot and level crossings Whole route Feasibility study under way Solutions include diversion,<br />
closure or bridges<br />
Automatic half-barrier level crossings upgraded to CCTV operation Whole route Work has started at a number of<br />
sites and feasibility studies are<br />
ongoing for remaining sites<br />
Bridge repairs & replacements for condition or to permit higher speeds Whole route Will be undertaken as required<br />
Replacement of electrification control equipment Whole route Contract let<br />
Renewal of signalling equipment Glasgow Central Feasibility study under way<br />
Train Control System Defined sections Feasibility study under way<br />
W10 Willesden Ju n c t i o n – C o a t b r i d g eScheme authorised and<br />
and Liverpool work under way<br />
W10 Other route sections Feasibility study under way<br />
W11 Willesden Ju n c t i o n – C o a t b r i d g e, Feasibility study complete We do not currently consider that<br />
Manchester and Liverpool this scheme offers value for money<br />
During 1998, a number of additional feasibility schemes were commissioned. Some of these deal with longer-term aspirations; others either enhance existing proposals or are in connection<br />
with infrastructure to support reliability, perturbation management and maintenance issues. Further details will be provided as the studies progress in future Statements.