19.01.2013 Views

pa1778data.pdf

pa1778data.pdf

pa1778data.pdf

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

U.S. STEEL DUQUESNE WORKS<br />

HAER No. PA-115<br />

(Page 73)<br />

Although immediately successful, men were still required to dig a<br />

starting point from which the machine unloader could work until,<br />

through a bit of improvisation, a quarter section of a scrap<br />

ingot mold was placed in one end of each car just before casting.<br />

Removal of the section after solidification provided the<br />

necessary starting point for the unloader. The addition of a<br />

make-shift raised platform supported by scrap ingot molds and<br />

straddling the casting car unloading track refined the operation<br />

because it allowed the excavator to unload directly into trucks<br />

or rail cars for shipment on one side of the platform or to a<br />

stockpile on the other side. Eventually a permanent raised<br />

platform was constructed in conjunction with the installation of<br />

a new crushing, screening, and storage system in 1955.<br />

The new system, which capped the modernization of the<br />

plant's ferromanganese facilities, was the result of an extensive<br />

study to identify consumer needs taken on by the company after it<br />

was decided to centralize production at Duquesne. Determination<br />

of a product size suitable for furnace and ladle additions at<br />

consumer facilities was of particular interest. To this end, it<br />

was decided to install a crushing, screening, and storage system<br />

which was interlocked by two sloped conveyors, 50 and 250 feet in<br />

length respectively. Laid out in the shape of an L, the process<br />

began at ground level with the excavator feeding the large chunks<br />

of "ferro" from the casting car to a crusher capable of<br />

processing 125 tons per hour. After crushing, the material was<br />

conveyed to an elevated screening station where it was separated<br />

by size as it passed over three grids of a shaker screen.<br />

Depending upon its size, the material was dropped through a duct<br />

to one of three 150-ton storage bins, each of which was equipped<br />

with a retractable chute for gravity loading onto railroad cars<br />

or trucks. In 1965 a parallel crusher and conveyor was added to<br />

the system along with a ground level storage building constructed<br />

off the side of the car preparation building. 5<br />

During the late 1950s and early 1960s significant changes<br />

were made to the plant's iron production and delivery facilities<br />

beginning with the dismantling of blast furnaces numbers five and<br />

six and their replacement by Dorothy Six. Possessing a working<br />

volume (49,568 cu. ft.) which surpassed the combined working<br />

volume of the two furnaces (49,540 cu. ft.) it replaced, the<br />

108 f -0" high x 28 , -0" hearth diameter furnace also exhibited<br />

notable recording features and casting facilities. A total of<br />

ten probes were placed in an horizontal position at three<br />

different heights along the furnace stack in order to give<br />

furnace operators information about the composition of gases and<br />

temperatures throughout the furnace. The power driven probes<br />

burrowed their way to the middle of the burden before they were<br />

withdrawn. As the probes exited the furnace, they were stopped

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!