U.S. STEEL DUQUESNE WORKS<br />
HAER No. PA-115<br />
(Page 151)<br />
supported by notably less reinforcement than the hoist bucket.<br />
Additionally, a new skip pit was constructed in the stockhouse to<br />
accommodate the skip cars, new equipment was installed at the<br />
furnace top in order to facilitate charging, and an extension to<br />
the hoist house was built for the addition of two hydraulic<br />
cylinders which operated the newly installed bells at the top of<br />
the furnace.<br />
The McKee process was adapted to the existing stockhouse<br />
system of bins and scale cars which filled alternating skip cars<br />
with raw materials while they were in the number 4 skip pit.<br />
After filling, the skip cars were hoisted by a new dual drive 200<br />
hp motor/drive/winch drum assembly, manufactured by the Superior<br />
- Lidgerwood - Mundy Company and located in the hoist house, to<br />
the top of the furnace where the raw materials were deposited<br />
into a receiving hopper which delivered them, by gravity, to the<br />
hopper containing the revolving distributor. The bell shaped<br />
distributor sat directly on top of the small bell. Upon its<br />
rotation, compressed air was introduced into the small bell's<br />
hydraulic cylinder thereby beginning the reaction which<br />
simultaneously raised the cylinder and lowered the lever arm<br />
connected to the small bell at the top of the furnace. As the<br />
small bell was lowered the desegregated material dropped onto the<br />
large bell. The small bell was raised back up to its gas seal<br />
position by withdrawing the compressed air from its cylinder,<br />
after which the process was repeated with respect to the large<br />
bell's raising and lowering apparatus in order to drop the<br />
materials into the furnace proper. As one skip car was dropping<br />
its contents into the charging equipment at the furnace top the<br />
other was being filled with materials in the skip pit.<br />
The adaptation of the raw materials delivery system to the<br />
McKee arrangement at blast furnace number 3 involved only the<br />
replacement of the 250 cu. ft. hoist bucket with one 267 cu. ft.<br />
skip car. Additional increases of the capacity of blast furnace<br />
number 3 were impractical because of the character of its<br />
production. During this time the furnace only produced ferro-<br />
manganese, a product which melted at such high temperatures that<br />
a constant vigilance was required in order to prevent it from<br />
burning through the furnace lining and shell. 9<br />
The construction of Dorothy 6 between i960 - 1962 was<br />
undertaken to replace dismantled blast furnaces numbers 5 and 6.<br />
Designed and built by John Mohr and Sons of Chicago, Illinois,<br />
the furnace produced more than twice the iron generated by the<br />
dismantled furnaces together. It did so because of its large<br />
hearth diameter (28'-0"), its large working volume (58,340 cu.<br />
ft.) and because of the installation of the most modern raw<br />
materials delivery system for its time. Novel features of the