U.S. STEEL DUQUESNE WORKS<br />
HAER No. PA-115<br />
(Page 105)<br />
took the ostensibly clarified water back to the river while the<br />
sludge was pumped to the settling basins where it was removed by<br />
grab bucket after drying. 6<br />
Major construction projects involving blast furnaces number<br />
four and six between 1959 and 1962 significantly altered the<br />
make-up of the combustion air production and delivery system. As<br />
part of a major rebuild of blast furnace number four in 1959, new<br />
21'-0" diameter x 121'-0" high hot blast stoves were installed by<br />
the William M. Bailey Company. The 150,428 square feet of<br />
heating capacity in each stove was by far the largest heating<br />
area among existing hot blast stoves in the blast furnace plant.<br />
This record, however, was quickly surpassed by the construction<br />
of the hot blast stoves associated with the Dorothy six complex<br />
in 1962. Designed and installed by John Mohr and Sons Inc., each<br />
of the three 32'-0" diameter x 130'-0" high stoves contained a<br />
total heating surface of 450,781 square feet. Other important<br />
equipment relating to the combustion air production and delivery<br />
system which were part of the construction of Dorothy Six<br />
included the installation of an axial turbo-blower, a new gas<br />
cleaning apparatus, and a continuous process for dewatering blast<br />
furnace sludge.<br />
The axial turbo-blower, designed and built by the Elliott<br />
Company of Jeannette, Pennsylvania, had the capability of<br />
delivering 155,000 cfm of air at 55 psi to Dorothy Six. The<br />
first axial machine in the United States to go into service in<br />
the active production of iron, the adjustable blades at the<br />
compressor end of the turbo-blower allowed for the delivery of<br />
different volumes of air to the furnace. This made it possible<br />
to produce, in a controlled manner, different types of pig iron.<br />
The gas cleaning equipment at Dorothy Six, consisting of a<br />
dust catcher, a 190,000 scfm venturi type primary gas washer and<br />
a 190,000 scfm gas cooling tower linked together in series. It<br />
represented a first step away from the plant's traditionally<br />
centralized gas cleaning operation. Gas flowing from the top of<br />
the furnace was first passed through the dust catcher where the<br />
large entrained particulate were removed from it in the usual<br />
manner before it was taken to the top of the venturi type<br />
primary gas washer. The gas washer consisted of a venturi shaped<br />
unit connected to a 21'-0" diameter x 49*-6" high tile lined<br />
hollow cylinder. Gas entering the top of the venturi unit was<br />
forced through its narrow throat where it was sprayed at a rate<br />
of 2400 gpm with water by low and high pressure nozzles set at<br />
different angles. Upon spraying, the gas, containing .01 grains<br />
of flue dust per cubic foot, was led out of the washer through a<br />
84" i.d. connection located near the top of the cylindrical<br />
structure set below the venturi unit to the gas cooling tower.