Tanzania Portland Cement Company Ltd, <strong>Annual</strong> <strong>Report</strong> 2008<br />

The expansion project<br />

Status as of December 2008:<br />

The 108 million USD expansion project is now nearing its<br />

completion. The project received fi nal approval in early<br />

2007 and a turn-key contract was signed on 14 March<br />

2007 between <strong>TPCC</strong> and CBMI. CBMI is a well known<br />

supplier of turn-key cement factories and is a subsidiary of<br />

the Chinese industrial conglomerate SINOMA Group.<br />

The expansion project consists of a full production line<br />

with a screener/crusher of raw materials, limestone stor-<br />

age, raw meal mill and silo, a 5-stage cyclone pre-heater<br />

rotary kiln, cement mill and silo, a packing and dispatch<br />

facility, as well as a dedicated 132 kV power line.<br />

Site activities started in June 2007, and in October 2008<br />

the Company took over the fi rst section of the project;<br />

the cement grinding and packing plant. This doubled<br />

10<br />

Pacing plant<br />

2 x 90 tons/hour<br />

Cement mill<br />

85 tons/hour<br />

Cement silo<br />

7,500 tons<br />

<strong>TPCC</strong>’s cement grinding capacity from around 700,000<br />

tons to 1,400,000 tons of cement annually.<br />

The clinker production line is now under commissioning.<br />

The fi rst clinker produced from the new kiln saw the light<br />

of day on 1 March this year (2009). About 25,000 tons<br />

of high quality clinker (on a test basis) were produced by<br />

the new clinker line in March. Final take-over is scheduled<br />

for June 2009. <strong>TPCC</strong> will thereafter be independent of<br />

imported clinker.<br />

5-stage pre-calciner kiln<br />

2,500 tons per day<br />

Raw meal silo<br />

8,000 tons<br />

The project has been a success both for <strong>TPCC</strong> and for<br />

<strong>HeidelbergCement</strong> Group. The project will be completed<br />

on time and within budget. No major problems have oc-<br />

curred during the construction phase; notably without any<br />

accidents resulting in injuries or loss of life.